1 / 7

L1 SciFi  Trigger (CTT/CPS/FPS) Commissioning Overview

L1 SciFi  Trigger (CTT/CPS/FPS) Commissioning Overview. Status Problems Plans. Overview SciFi  & Preshower Trigger System. Basic scheme: Analog front-end Mixer crate Digital front-end w/ controller Collector/Broadcaster system (octant/sextant/quadrant) Trigger Term (singlet) board

mya
Télécharger la présentation

L1 SciFi  Trigger (CTT/CPS/FPS) Commissioning Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. L1 SciFi Trigger (CTT/CPS/FPS) Commissioning Overview • Status • Problems • Plans Trigger Meeting

  2. Overview SciFi& Preshower Trigger System • Basic scheme: • Analog front-end • Mixer crate • Digital front-end w/ controller • Collector/Broadcaster system (octant/sextant/quadrant) • Trigger Term (singlet) board • (Muon) trigger manager • Links: • Internal all LVDS • Serial copper (AMCC) for 80 sector links to muon • Serial fiber (g-link) to L2, L3 • 7 crates in 3 separate subsystems; • test by chain DFEA DFES DFEF Trigger Meeting

  3. Components & Subsystems • Digital Board daughter cards come in two flavours: • single width for Axial trigger (DFEA) • double width for everything else : • DFEF, DFES, • Collector ('octet') cards CTOC, FPSS, CPSS, • Concentrator ('singlet') cards CTTT and FPTT. • System has 7 crates, 3 separate chains: • axial tracker & central preshower DFEA - CTOC - CTTT - MTM - L1FW (with L2 sidechain CTOC - CTQD - L2CTT) • Forward Preshower DFEF - FPSS - FPTT - MTM -L1FW (with L2 side chain FPSS - L2FPS) • L2 only chain DFES - CPSS - L2CPS DFE Daughtercard Trigger Meeting

  4. L1 SciFi  Hardware Installation • common motherboard: full production done (stuffed boards in hand). • DFE single width daughter card: full production in hand. • DFEA assemblies: about 50% of tested DFEAs should be ready by May 5th; hopefully 100% before end of access. • Double width daughter card: three prototypes tested ok= enough for chain tests; problem with production (BGA attachment). Doing temperature profile for soldering right now; very little chance of production and testing before end of access. • Crates, backplanes & power supplies: crates need to be removed, and additional alignment hardware for transition modules installed. • cables: • SVX/Sequencer installed. • optical fibers installed. • Long LVDS: installed. • Short LVDS: to be installed with modules. Trigger Meeting

  5. L1 SciFi  Firmware Status • Previously missing items: • L3 sender done • CTTT done • Still to be done: • chain tests (in hardware) • overall, about 1 month behind schedule (compared to schedule from early February 2001) • => should have CFT hit-count trigger installed about mid-May. Trigger Meeting

  6. L1 SciFi  Trigger Software Trigger Meeting

  7. L1 SciFi Trigger Commissioning • Plan for 2 week access: • fix crates (transition module alignment) • install DFEC and one module (DFEA) in each crate • install 50 % (100% ?) of DFEAs • CFT hit-count chain test; finish CFT/CPS L1 functionality • rewrite DFEC software • solve double-wide production problem • work on status display and monitoring • Goal: working CFT system by the time AFE8's are installed and working (mid-July?) Trigger Meeting

More Related