1 / 16

Public-Private Partnerships (PPP) in Highways

Public-Private Partnerships (PPP) in Highways . International Experience and Lessons for Success Transport Learning Week, April 3, 2006 Jose Luis Irigoyen Sector Manager LCSFT. 14. 70. 12. 60. 10. 50. 8. 40. Number . 2003 US$ billion . 6. 30. 4. 20. 2. 10. $2bn. -. 0. 0.

mya
Télécharger la présentation

Public-Private Partnerships (PPP) in Highways

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Public-Private Partnerships (PPP) in Highways International Experience and Lessons for Success Transport Learning Week, April 3, 2006 Jose Luis Irigoyen Sector Manager LCSFT

  2. 14 70 12 60 10 50 8 40 Number 2003 US$ billion 6 30 4 20 2 10 $2bn - 0 0 88 89 91 92 93 94 96 99 2000 01 02 03 1990 95 97 98 Chile China India Rise & fall in developing countries shows vulnerability in era of financial shocks Total Investment in Road Projects with Private Sector Participation 1988-2003 Asian Crisis Mexico Peso Crisis Russia/Brazil Argentina Turkey Total Investment Number of Projects Source: PPI Database

  3. 14,000 Total Investment in Road Projects with Private Participation. Source: PPI Database 12,000 10,000 8,000 6,000 2003 US$ million 4,000 2,000 0 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 Rest of the World China Mexico Brazil Malasya Chile Argentina Years …but also reflects impact of project activity within key countries…

  4. Standard and Poor, 32 toll roads Actual/Forecasted Traffic PPP projects in highways have suffered from optimism bias • Forecasting errors from inability to obtain good data or incorrect assumptions in models • price elasticity of traffic to tolls; • substitute services/intensified competition;

  5. PPP projects in highways have suffered from optimism bias • Forecasting errors from inability to obtain good data or incorrect assumptions in models • price elasticity of traffic to tolls; • substitute services/intensified competition; • Political commitment at too early a stage • before appraisal at sufficient depth to allow graceful exit • project timelines inconsistent w/sound bidding practices • Downplaying vulnerability of PPP projects to changing political, financial, economic context • failure to identify/value political and social costs (eg., toll increases)

  6. 1,000 900 Average Project Size 800 700 600 2003 US$ million 500 400 300 200 100 - 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 Years PPP projects are becoming smaller reflecting financial constraints … and also that bigger projects already done in more active countries Source: PPI Database

  7. Structured project finance has come a long way, but not yet for all ... • Fashioning the finance to specific project needs --with risks and returns borne not by sponsor alone but by different types of investors-- is buzzword • mezzanine finance; • monoline insurance broadens access to capital markets • interest rate and foreign exchange hedging increasingly critical as projects become more finely balanced • but available only for certain projects/countries • mostly projects with investment grade credit rating; • no realistic opportunities for hedging in many countries; • contractual complexity/financial rigidity not always favored by sponsors/allowed by project economics

  8. “Roll over” of short term instruments (high/costly refinancing risk) Local financing: short maturities (3-8 years), high volatile interest rates, insufficient depth of markets Foreign financing: political and sovereign risks exchange risk (toll revenue in local currency) Financing tights suddenly in emerging markets due to crises • The financing dilemma for developing countries 13

  9. Currency devaluation in 5 countries with the most PPPI, 1985-2001 Source: Gray, P. & Irwin, T., Exchange Rate Risk Worsening of regulatory environment during crises erodes support for PPPs • “pass through” formulas that transfer exchange risk to users fail in midst of abrupt devaluations --and turn exchange risk into political or regulatory risk • Distressing results of crises: • Governments breach contracts, affecting access to capital markets. • Users must cope with steep increases in tolls eroding long-term support for PPPs.

  10. Economic & Financial Equilibrium Clauses: • asymmetric information; • poor control of costs (“goldplating”); • unclear renegotiation if procedure to restore equilibrium not defined Approaches to traffic risk mitigation --no conclusive evidence of what’s best Source: Jose Vasallo, 2005 “Traffic Risk Mitigation in highway concession projects: the experience of Chile”

  11. Approaches to traffic risk mitigation --no conclusive evidence of what’s best Minimum Income Guarantee Approach Source: Jose Vasallo, 2005 “Traffic Risk Mitigation in highway concession projects: the experience of Chile”

  12. Risk profile mitigation with LPVR Approaches to traffic risk mitigation --no conclusive evidence of what’s best duration Source: Jose Vasallo, 2005 “Traffic Risk Mitigation in highway concession projects: the experience of Chile”

  13. Stronger alignment between PPP objective & compensation mechanism • New thinking about the transfer of volume risk and whether the premium paid outweighs benefits • UK – from shadow tolls to payments based on combination of service availability and performance • availability payment, 2000; active management payment, 2002 • NAO critical of shadow tolls given operator is unable to influence demand • current trend to focus the compensation mechanism on establishing degree of risk allocation in project needed to induce appropriate performance by private sector

  14. Cancelled Projects 1984-2003 Number of Projects 1990-2003 Source: PPI Database Cancelled Concluded 8% 7% Construction 3% Distressed 2% Operational 80% Bottom line, few cancellations but opportunistic renegotiations the rule… • Statistics mask high incidence of renegotiations • Larger projects more prone to cancellation or distress

  15. Despite slowdown, PPPs remain an attractive option for many governments • tools to bring legitimacy to PPP approaches and project selection and make informed decisions about risk allocation at both policy and project level • impact of PPP programs on road sector dev. & funding • proper accounting, management and funding of contingent liabilities to effectively address public risk • pragmatic approaches to building institutional and regulatory capacity to better deliver on “third P” • instruments to address financial market constraints (w/ due attention to two sides of “creative financing” coin) • Some key areas for WB attention:

  16. Many thanks...jirigoyen@worldbank.org

More Related