1 / 120

時間管理補充資料—林老師提供

時間管理補充資料—林老師提供. AOA. AON. Activity Relationships. Activity Relationship. Figure 18.1. AOA. AON. S. T. U. S. T. U. 1. 2. 3. 4. Activity Relationships. Activity Relationship S precedes T, which precedes U. Figure 18.1. AOA. AON. S. 1. S. U. 3. 4. U. T. 2. T.

naava
Télécharger la présentation

時間管理補充資料—林老師提供

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 時間管理補充資料—林老師提供

  2. AOA AON Activity Relationships Activity Relationship Figure 18.1

  3. AOA AON S T U S T U 1 2 3 4 Activity Relationships Activity Relationship S precedes T, which precedes U. Figure 18.1

  4. AOA AON S 1 S U 3 4 U T 2 T Activity Relationships Activity Relationship S and T must be completed before U can be started. Figure 18.1

  5. AOA AON 3 T T S 1 2 S U 4 U Activity Relationships Activity Relationship T and U cannot begin until S has been completed. Figure 18.1

  6. AOA AON S 1 4 S U U 3 T V 2 5 T V Activity Relationships Activity Relationship U and V cannot begin until both S and T have been completed. Figure 18.1

  7. AOA AON S U 1 3 5 S U Dummy T V 2 4 6 T V Activity Relationships Activity Relationship U cannot begin until both S and T have been completed; V cannot begin until T has been completed. Figure 18.1

  8. AOA AON S T V 1 2 4 5 S T V Dummy U 3 U Activity Relationships Activity Relationship T and U cannot begin until S has been completed; V cannot begin until both T and U have been completed. Figure 18.1

  9. St. Adolf’s Hospital

  10. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. B Select site and do site survey. C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview applicants and fill positions in nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the hospital. I Develop an information system. J Install the equipment. K Train nurses and support staff. St. Adolf’s Hospital Example 18.1

  11. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop an information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J St. Adolf’s Hospital Example 18.1

  12. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J St. Adolf’s Hospital AON Network Example 18.1

  13. Immediate Activity Description Predecessor(s) AON Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A Start St. Adolf’s Hospital Example 18.1

  14. Immediate Activity Description Predecessor(s) AON Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A Start B St. Adolf’s Hospital Example 18.1

  15. Immediate Activity Description Predecessor(s) AON Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A C Start B St. Adolf’s Hospital Example 18.1

  16. Immediate Activity Description Predecessor(s) AON Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A C Start D B St. Adolf’s Hospital Example 18.1

  17. Immediate Activity Description Predecessor(s) AON Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A C Start D B E St. Adolf’s Hospital Example 18.1

  18. Immediate Activity Description Predecessor(s) AON Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A F C Start D B E St. Adolf’s Hospital Example 18.1

  19. Immediate Activity Description Predecessor(s) AON Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A F C G Start D B E St. Adolf’s Hospital Example 18.1

  20. Immediate Activity Description Predecessor(s) AON Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A F C G Start D B H E St. Adolf’s Hospital Example 18.1

  21. Immediate Activity Description Predecessor(s) AON Network I A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A F C G Start D B H E St. Adolf’s Hospital Example 18.1

  22. Immediate Activity Description Predecessor(s) AON Network I A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A F C G Start D B H J E St. Adolf’s Hospital Example 18.1

  23. Immediate Activity Description Predecessor(s) AON Network I A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A F K C G Start D B H J E St. Adolf’s Hospital Example 18.1

  24. Immediate Activity Description Predecessor(s) AON Network I A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A F K C G Start Finish D B H J E Figure 18.2 St. Adolf’s Hospital Example 18.1

  25. Immediate Activity Description Predecessor(s) AOA Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J St. Adolf’s Hospital Example 18.1

  26. Immediate Activity Description Predecessor(s) AOA Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J 2 A Start 1 St. Adolf’s Hospital Example 18.1

  27. Immediate Activity Description Predecessor(s) AOA Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J 2 A Start 1 B 4 St. Adolf’s Hospital Example 18.1

  28. Immediate Activity Description Predecessor(s) AOA Network A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J 2 C A 3 Start 1 5 B D 4 St. Adolf’s Hospital Example 18.1

  29. Immediate Activity Description Predecessor(s) AOA Network F A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J 8 2 I C A 3 7 G Start 1 H 5 6 B E D 4 St. Adolf’s Hospital Example 18.1

  30. Immediate Activity Description Predecessor(s) AOA Network F A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J 8 2 I C A 3 7 J G Start 1 H 5 6 B E D 4 St. Adolf’s Hospital Example 18.1

  31. Immediate Activity Description Predecessor(s) AOA Network F A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J 8 2 I Dummy C A 3 7 J G Start 1 H 5 6 B E D 4 St. Adolf’s Hospital Example 18.1

  32. Immediate Activity Description Predecessor(s) AOA Network F A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J 8 2 I Dummy C K A 3 7 J G Start 1 Finish 9 H 5 6 B E D 4 Figure 18.3 St. Adolf’s Hospital Example 18.1

  33. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J St. Adolf’s Hospital Completion Time

  34. Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time Figure 18.4

  35. Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  36. Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  37. Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  38. Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  39. Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  40. Expected Path Time A-F-K 28 A-I-K 33 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  41. Expected Path Time A-F-K 28 A-I-K 33 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  42. Expected Path Time A-F-K 28 A-I-K 33 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J Start Finish St. Adolf’s Hospital Completion Time I 15 A 12 F 10 K 6 C 10 G 35 B 9 D 10 H 40 J 4 E 24

  43. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J Start Finish St. Adolf’s Hospital Completion Time I 15 A 12 F 10 K 6 C 10 G 35 B 9 D 10 H 40 J 4 E 24 Figure 18.5

  44. St. Adolf’s Hospital

  45. I 15 F 10 A 12 K 6 C 10 G 35 Start Finish H 40 J 4 B 9 D 10 E 24 St. Adolf’s Hospital Earliest Start and Earliest Finish Times Example 18.2

  46. I 15 Earliest start time F 10 A 12 K 6 0 C 10 G 35 Start Finish H 40 J 4 B 9 D 10 E 24 St. Adolf’s Hospital Earliest Start and Earliest Finish Times Example 18.2

  47. Start Finish St. Adolf’s Hospital I 15 Earliest finish time Earliest start time F 10 A 12 K 6 0 12 C 10 G 35 H 40 J 4 B 9 D 10 Earliest Start and Earliest Finish Times E 24 Example 18.2

  48. Start Finish St. Adolf’s Hospital I 15 F 10 A 12 K 6 0 12 C 10 G 35 H 40 J 4 B 9 D 10 0 9 Earliest Start and Earliest Finish Times E 24 Example 18.2

  49. Start Finish St. Adolf’s Hospital I 15 F 10 A 12 K 6 0 12 C 10 G 35 H 40 J 4 B 9 D 10 9 19 0 9 Earliest Start and Earliest Finish Times E 24 9 33 Example 18.2

  50. Start Finish St. Adolf’s Hospital I 15 12 27 F 10 A 12 K 6 0 12 12 22 C 10 G 35 12 22 H 40 J 4 B 9 D 10 9 19 0 9 Earliest Start and Earliest Finish Times E 24 9 33 Example 18.2

More Related