1 / 7

Brazilian Tunable Filter Imager (BTFI) Preliminary Design Review (PDR) ‏

Brazilian Tunable Filter Imager (BTFI) Preliminary Design Review (PDR) ‏. Team Management (Claudia & Keith) ‏ Version 1.0. USP-IAG Universidade de São Paulo 18-19th June 2008. BTFI Team Management. BTFI phases: Design Post-PDR to final specifications and drawing set Fabrication

nalani
Télécharger la présentation

Brazilian Tunable Filter Imager (BTFI) Preliminary Design Review (PDR) ‏

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Brazilian Tunable Filter Imager(BTFI)Preliminary Design Review (PDR)‏ Team Management (Claudia & Keith)‏ Version 1.0 USP-IAG Universidade de São Paulo 18-19th June 2008

  2. BTFI Team Management • BTFI phases: • Design • Post-PDR to final specifications and drawing set • Fabrication • Assembly, Integration & Test • Commissioning

  3. BTFI Core Team(in no particular order!)‏ • Claudia Mendes de Oliveira (CMdO – IAG/USP)‏ • Keith Taylor (KT - contracted)‏ • Rene Laporte (Rene - INPE)‏ • Fernando Laurenco (FL – INPE)‏ • Cesar Strauss (CS – INPE)‏ • Luiz Reitano (Reitano – INPE)‏ • Antonio Cesar de Oliveira (ACdO – LNA)‏ • Fernando Fontes (FF – contracted)‏ • Dani Guzman (Dani – contracted: AstroInventions)‏ • Giseli Ramos (Giseli – IAG/USP)‏ • Bruno Quint (Bruno – IAG/USP)‏ • Luiz Cavalcanti (Luiz – IAG/USP)‏ • Javier Ramirez Fernandez (Javier – USP)‏ • Antonio Kanaan (AK – UFSC)‏ • Fabricio Ferrari (FFe – U. Santa Maria)‏

  4. Design Phase Responsibilities • Optical • Final iteration with manufacturers (DJ – subcontract)‏ • Placing orders (CMdO @ IAG)‏ • Opto-Mechanical • Design (Rene + FL @ INPE)‏ • Drawings (FL + Reitano @ INPE)‏ • Instrument Control Electronics • Design (Denis + CS @ INPE)‏ • Detector Controller • Design (Olivier – PhotonEtc sub-contract)‏ • Comms PCB & Power Supply (Denis + CS @ INPE)‏ • FP Controller • Design (Jean-Luc Gach + Luiz @ LAM)‏ • Software • Instrument Control (Giseli + FF @ IAG)‏ • CCCP-v2 (Olivier Daigle @ U.Montreal + Giseli @ IAG)‏ • OtF to Pipeline DR (CMdO + KT + Bruno @ IAG + AK + Ffe @ UFSC/USM)‏

  5. Fabrication Phase Responsibilities • Optical • Managing procurement (KT)‏ • Opto-Mechanical • Fabrication (eg: MetalCard and/or Proteo)‏ • Instrument Control Electronics • Fabrication (Denis + CS @ INPE)‏ • Detector Controller • Fabrication (PhotonEtc)‏ • Comms PCB & Power Supply (Brazilian Industry)‏ • FP Controller • Fabrication (@ LAM)‏ • Software coding • Instrument Control (Giseli + FF @ IAG)‏ • CCCP-v2 (Olivier Daigle @ U.Montreal + Giseli @ USP)‏ • OtF to Pipeline DR (Bruno @ IAG + AK + FFe @ UFSC/USM)‏

  6. AI&T Phase Responsibilities • Optical • Evaluation & acceptance testing + I&T (KT + Rene + ACdO @ LNA?)‏ • Opto-Mechanical • Acceptance (Rene + Reitano - INPE)‏ • I&T (Rene + Reitano + ACdO @ INPE or LNA)‏ • Instrument Control Electronics • Test (Denis + CS)‏ • Detector Controller • Debug and evaluate (Dani – sub-contract to AI)‏ • Test (Javier @ USP + Dani)‏ • FP Controller • Debug, evaluate and test (Luiz @ IAG)‏ • Software test & debug • Instrument Control (Giseli + FF @ IAG)‏ • CCCP-v2 (Giseli @ IAG)‏ • OtF to Pipeline DR (Bruno + CMdO + KT @ IAG + AK + FFe @ UFSC/USM)‏

  7. Commissioning Responsibilities • Final Instrument Integration (@ INPE or LNA- tbc)‏ • Opto-mechanical (Rene, Reitano, CdO)‏ • Control Electronics (Denis + CS)‏ • Detector Controller (Javier + Giseli + FF)‏ • FP Controller (Luiz)‏ • Software • Instrument Control (Giseli and/or FF)‏ • CCCP-v2 (Giseli)‏ • Data Redn spec - OtF to Pipeline (Bruno + AK)‏ • On-site Integration & Final Test (@ SOAR)‏ • Rene, Reitano, ACdO, Denis, CS, Giseli, FF, Luiz, Bruno, AK • Commissioning (@ SOAR)‏ • CMdO, KT, Rene, ACdO, Denis, Giseli, Luiz, Bruno, AK, FFe, FF