Equipment Costing

Equipment Costing. Chapter 22 (p558-597) CH EN 4253 Terry A. Ring. 6/10 th scale up/down Factor. Used for scaling the total capital cost for a chemical plant of a different size Cost 2 /Cost 1 = (Capacity 2 /Capacity 1 ) 0.6 Accounts for economy-of-scale. Accounting for Inflation.

Télécharger la présentation

Equipment Costing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Equipment Costing Chapter 22 (p558-597) CH EN 4253 Terry A. Ring

  2. 6/10th scale up/down Factor • Used for scaling the total capital cost for a chemical plant of a different size • Cost2/Cost1 = (Capacity2/Capacity1)0.6 • Accounts for economy-of-scale

  3. Accounting for Inflation • Cost to purchase = Base Cost*(I/Ibase) • Base Cost, CB, = Historical price at Ibase • I is a Cost Index at present time • Chemical Engineering, CE, Plant Cost Index • Marshall and Swift (MS) Equipment Cost Index • Nelson-Farrar (NF) Refinery Construction Cost Index • Engineering News-Record (ENR) Construction Cost Index • Cp(I) = Cp(Ibase)*(I/Ibase) • Cp(Ibase)=FT*Fm*Cbase(Ibase)

  4. Cost Estimate Methods • Order of Magnitude Estimate • Method of Hill • Marshall Swift for I/Ibase • Six Tenths Rule for Production Capacity • CTCI-2 (I)=CTCI-1 (Ibase)*(I/Ibase)* (Capacity2/Capacity1)0.6 • Study Estimate (±35%) • Method of Lang • CTCI=1.05*fL-TCI ∑ (Ii/Ibase-i) Cp-i • Lang factors for different types of Plants • Solids -3.10, Solids&Fluids 3.62, Fluids 4.73 • Sum over all major equipment • Preliminary Estimate (±20%) • Method of Guthrie • Bare module cost, CBM= Cp-base(I/Ibase)[FBM+(FdFpFm-1)] • d= design factor, p = pressure factor, m =materials factor • CTCI= ∑ CBM_i • Quote Estimate

  5. Purchase Costs for Equipment • Size Factor, S, depends on type of equipment • Cp(Ibase)=A*(S)b • Cp(Ibase)=exp(Ao+A1[lnS]+A2[lnS]2+…) • Your book gives 2006 base costs • Ibase = 500 (2006) average

  6. Pumps & Electric Motors • Pump Types (Centrifugal, Gear, Plunger) • Centrifugal Pump • Size factor, S=Q(Head)0.5 • Base Cost, CB=exp(9.2951- 0.6019[ln(S)] +0.0519[ln(S)]2) • Cp=FTFMatCB • Fm materials factor see Table 22.21 • FT pump type factor see Table 22.20 • Other types of pumps have different CB formulas • Electric Motor to drive pump • Size Factor=Power consumption, PC=PT/ηp/ηM=PB/ηM=QHρ/(33,000ηpηM) • Q= flow rate, H = head, ρ = density • Efficiencies (pump and motor) are a function of flow rate and break horsepower (power without any losses), respectively • CB=exp{5.4866+0.013141[ln(PC)]+0.053255 [ln(PC)]2 +0.028628 [ln(PC)]3-0.0035549[ln(PC)]4} • Cp=FTCB • FT= motor types factor see Table 22.22 • ηM=~90% • Installation, etc, FBM=3.3 • CBM=FBM*∑CP

  7. Fans • Fan • Sizing factor is the volumetric flow rate, Q • Different CB formula for different types of fans • CP=FHFM CB • FH Head factor see Table 22.24 • FM material of construction factor • Fiberglass 1.8 • Stainless steel 2.5 • Nickel Alloy 5.0 • Motor size by PC=QHt(in. water)/(6,350 ηFηM) • ηM =~90%, FBM = 2.15 • CBM=FBM*∑CP

  8. Blowers • Sizing factor is the power consumption, PC • Centrifugal (turbo) Blower CB=exp{6.6547+0.7900[ln(Pc)]} • CP=Fm-fansCB • Motor • Motor size by PC=QHt(in. water)/(6,350 ηFηM) • ηM =90% , FBM = 2.15 • CBM=FBM*∑CP

  9. Compressors • Compressor types • Centrifugal, CB=exp{7.2223+0.80[ln(PC)]} • Reciprocating, CB=exp{7.6084+0.80[ln(PC)]} • Screw, CB=exp{7.7661+0.7243[ln(PC)]} • Size factor is the power consumed, PC=PB/ηC • CP=FDriveFMatCB • FDrive =1 (electric motor), 1.15 (steam), 1.25 (gas turbine) • FMat = 1.0 Carbon steel, 2.5 SS, 5.0 Nickel Alloy • CBM=FBM*∑CP • FBM = 2.15

  10. Heat Exchangers • Types of Heat exchangers • Floating, CB=exp{11.667-0.8709[ln(A)]+0.09005[ln(A)]2} • Fixed Head, CB=exp{11.0545-0.9228[ln(A)]+0.09861[ln(A)]2} • U-tube, CB=exp{11.147-0.9186[ln(A)]+0.09790[ln(A)]2} • Kettle, CB=exp{11.967-0.8709[ln(A)]+0.09005[ln(A)]2} • Thermosiphon, CB= • Double pipe, CB=exp{7.1248-0.16[ln(A)]} • Size Factor is HX area, A • CP=FpFMatFLCB • Pressure Factor, Fp= 0.9803+0.018(P(psig)/100)+0.0017(P(psig)/100)2 • Not for double pipe • Materials Factor, Fmat=a+(A/100)b, a & b from Table 22.25 • a≥1.0 note error in first row of Table 22.5 • Tube Length Factor FL= 1.25 for 8 ft, 1.0 for 20 ft. on a sliding scale • CBM = FBM*CP, FBM=3.17 (S&T), 1.80 (DP), 2.17 (Fin/Fan)

  11. Fired Heaters • Size Factor is the heat duty, Q • CB=exp{0.08505+0.766[ln(Q)]} • CP=FPFMatCB • FP=0.986-0.0035(P(psig)\500)+0.0175(P/500)2 • Fmat=1.4 Cr-Mo alloy steel, 1.7 for stainless steel • CBM = FBM*CP, FBM=2.19

  12. Pressure Vessels • Storage Tanks • Distillation Towers • Tray • Packed • Absorber Towers • Stripping Towers

  13. Pressure Vessels • Sizing Factor is the weight of steel, W • Horizontal Vessels, 1,000<W<920,00 lb CB=exp{8.717-0.2330[ln(W)]+0.4333[ln(W)]2} • Vertical Vessels, 4,200<W<1,000,00 lb CB=exp{6.775-0.18255[ln(W)]+0.02297[ln(W)]2} • Add Platform Costs, • Horizontal, 3<Di<12 ft • CPL=1580(Di)0.20294 • Vertical, 3<Di<21 ft • CPL=258.1(Di)0.7396(L)0.70684 • Weight, W=π(Di+ts)(L+0.8Di)tsρs • C=FMCB+CPL • FM= materials factor see Table 22.26 • Installation, etc, FBM=4.16 (V), 3.05 (H) • CBM=FBM*∑CP

  14. Hoop Stress Calc for thickness, ts • Design Pressure is function of operating pressure, Po • For Po> 1,000psig use Pd=1.1Po • For Po< 1,000psig but not for vacuum Pd=exp{0.60608+0.91615[ln(Po)]+0.0015655[ln(Po)]2} • Thickness (Hoop Stress Calculation) • ts= PdDi/(2SE-1.2 Pd) • S = max allowable stress for steel is f(T) • E = weld efficiency (fraction) • Minimum wall thickness for given diameters • May add extra thickness for wind stresses, corrosion • Different calculation for vacuum vessels • Also account for leakage when vacuum vessel is used

  15. Distillation Towers • Pressure vessel with plates or packing and additional nozzles and manholes • Tray Cost CT=NTFNTFTTFTMCBT • NT= no. trays • FNT= 1 for NT>20 otherwise FNT=2.25/(1.0414NT) • FTT = tray type, 1.0 sieve, 1.87 bubble cap • FTM= Materials, f(D) • Carbon Steel FTM=1.0 • 316 SS FTM=1.401+0.0788 Di • Installation, etc, FBM=4.16 • CBM=FBM*∑CP

  16. Packed Distillation Column • Pressure vessel with platforms plus packing • Packing Cost basis is volume of packing, VP • C=VpCPK+CDR • CPK= is installed cost per unit volume • Distributors cost, CDR

  17. Absorbers/Strippers • Pressure Vessel plus platforms and packing • Separate costs for blowers • Separate costs for motors

  18. Other process equipment • Different sizing factors • Different basis cost equations • Same methods used for cost calculation

  19. Other Process Equipment • Various Size Factors • Table 22.32