LHC IRQ Tie Bar Redesign Using Sleeves – Preliminary

LHC IRQ Tie Bar Redesign Using Sleeves – Preliminary. T. Nicol May 25, 2007. Current tie bar installation. Preliminary analysis. Assumed vacuum load: 20,000 lb total or 5,000 lb per rod (89,000 N) Maximum distance between vacuum vessel ears: 81” (2050 mm) Assume pinned ends

nardo
Télécharger la présentation

LHC IRQ Tie Bar Redesign Using Sleeves – Preliminary

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC IRQ Tie Bar Redesign Using Sleeves – Preliminary T. Nicol May 25, 2007

  2. Current tie bar installation

  3. Preliminary analysis Assumed vacuum load: 20,000 lb total or 5,000 lb per rod (89,000 N) Maximum distance between vacuum vessel ears: 81” (2050 mm) Assume pinned ends Assume S.F. of 4 Pcr = p2EI/l2 = 20,000 lb For stainless steel the minimum value for I = 0.475 in4 Need ID = 1.25” to be compatible with current geometry Solving for OD yields OD = 1.86” so use 2” Actual I = 0.66 in4 so S.F. ~ 5.6

  4. Attachment to existing ear

  5. Attachment to sliding sleeve

  6. Attachment to existing ear

  7. Attachment to existing ear At the magnet ears, the tie bar attaches with a 30 mm bolt. The bronze to stainless interface slides during pressure loading.

  8. Attachment to sliding sleeve Each tie bar joins at the sliding sleeve ear. This is where each is adjusted for length, preloaded slightly, then locked in position.

  9. Typical assembly of two tie rods at each ear location

  10. Typical assembly of two tie rods at each ear location

  11. Typical tie rod assembly Tie rod sleeve – 2” OD, 1.25” ID Threaded insert – 30 mm thread ID, 42 mm thread OD Insert – 30 mm thread ID, 42 mm smooth OD Jam nut

  12. Tie rod assembly using sleeves – v2

  13. Typical assembly – v2 Outer nut omitted to prevent excessive load in the event of a cryogen spill inside the vacuum vessel

  14. Typical assembly – v2 Nut to tighten sleeve against intermediate ear Nut to tighten assembly against vacuum vessel ear 2” OD, 1.25” ID sleeve Tie rod, nuts, and spherical washers are the same as those in the current system Spherical washers Tie rod

  15. Typical assembly – v2

  16. Typical assembly – v2

  17. Typical assembly – v2

  18. Q3 to DFBX tie rod assembly using sleeves – v2

  19. Q3 to DFBX typical assembly – v2

  20. Q3 to DFBX typical assembly – v2

  21. Q3 to DFBX typical assembly – v2

  22. Q3 to DFBX typical assembly – v2

  23. Q3 to DFBX typical assembly – v2

  24. Q1 to Q2 tie rod assembly MB-390923(420 mm sleeve) MB-390925(1162 mm sleeve) 30 mm tie rod Typical end detail 30 mm hex nuts (2) Spherical washers (2 pairs) 30 mm jam nut (1)

  25. Q2 to Q3 tie rod assembly MB-390924(620 mm sleeve) MB-390925(1162 mm sleeve) 30 mm tie rod Typical end detail 30 mm hex nuts (2) Spherical washers (2 pairs) 30 mm jam nut (1)

  26. Q3 to DFBX tie rod assembly MB-390926(682 mm sleeve) 30 mm tie rod Stiffener plates (2) Typical end detail 30 mm hex nuts (2) Spherical washers (2 pairs) 30 mm jam nut (1)