An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Radiation Monitoring in ALICE Andreas Morsch ALICE Technical Board 27/4/2004

  2. Outline • Introduction • Radiation Monitoring at CERN • Technologies • ALICE requirements • Time Schedule

  3. Introduction • We need Radiation Monitoring for • Mapping of radiation field, to check accuracy of background simulations and identify possible leaks • Long-term monitoring of integrated radiation exposure • Online monitor for beam conditions and possibility to request beam-abort • Post-mortem analysis of accidents

  4. Radiation Monitoring at CERN • Two Working Groups • RADWG: Radiation Monitoring of the LHC Machine • RADMON: LHC Experiment Radiation Monitoring • Chair: E. Tsesmelis • So far three full meetings (including one common RADWG+RADMON meeting) • Last meeting 6/4/2004 • http://lhc-expt-radmon.web.cern.ch/lhc-expt-radmon/

  5. Radiation Monitoring at CERN • CERN PH-TA1-SD Group • Support and development in the field of Solid State Detectors • Radiation Hardness Tests • Significant amount of theoretical knowledge and practical experience in radiation related effects and dosimetry (RD50 Collaboration) • Irradiation facility in the PS East Hall. • Passive dosimetry • In collaboration with F. Ravotti (TS/LEA): active dosimetry, development of online monitors for CMS • Proposal: • Continue and extend dosimetry developments to serve all LHC experiments.

  6. TA1-SD Proposal • Develop and characterize dosimeter boards with on-line readout for and together with the LHC experiments • Boards being as flexible as possible (dose/fluence range, sensitivity, particle type, shape of board …) in order to allow and optimal adoption to specific sub-detector environments. • Output signal compatible to all Detector Control Systems • Provide the dosimeter boards and/or active dosimeters to the experiments • Support the experiments in qualifying passive dosimeters

  7. What TA1-SD will not do • Impose their radiation monitoring concepts on the experiments • Integrate the dosimeters / dosimeter boards into the experiments

  8. Passive Dosimeters Data: I.Floret (SC/RP – High level dosimetry)

  9. Active Radiation Monitors RadFETs Build-up of charge in MOSFETs SiO2 layer (Ionizing Dose)  (integrating measurement). p-i-n diodes Optically Stimulated Luminescence (OSL) Bulk damage in high r Si-base (particle fluence)  (integrating measurement). Charge buildup in sensitive material detrapped by IR stimulation (Ionizing Dose)  (instantaneous measurement).

  10. (0.4 mm) BPW34F/Pad  Fequivalent[cm-2] {HEP, nF} (1.6 mm) OSLs  D [Gy] {g, HEP} Pad BPW34F n-OSLth  Fth [cm-2] {nth} Front-end Front-end Front-end n-OSLF  FF [cm-2] {nF} DCS Dosimeter Integration RadFETs  TID [Gy] {g, HEP} • We plan to put a very early prototype board into our irradiation facility this year

  11. Other Projects • LHCb • Metal foil detector for RM of Si Tracker • low-mass, simple, cheap, any-size and shape, ... • thickness < 1mm possible • TeVatron and HERA • Large experience • Redundant measurements • Many technologies • Still evolving

  12. ALICE Requirements • Integrated dose / year • 0.1 mGy – 0.3 kGy • Hadron fluence 107 – 1011 cm-2 / year • Monitor beam condition with possible request of beam abort • ~20 positions inside and outside L3 at different distance from beam pipe

  13. Time Schedule (Experiments) • - June 2004 • Experiments nominate contact persons • For ALICE: Marc Tavlet, CF, AM • Until end 2004 • Experiments work together with Ch. Joram on a document describing the conceptual lay-out of the RM system • Discussion based on questionnaire

  14. Questions to experiments • Measurement for which purpose? • (Beam dump?  Beam Condition Monitor Group) • Detector protection (e.g. switching off a sub-detector) ? • Test of radiation shielding? • Long term monitoring? • Analysis of beam accidents? • Instantaneous dose rate measurement needed ? • trigger on too high dose rate/flux needed? if so, in which time scale? • Measure which kind of information? • ionizing dose • displacement damage • thermal neutrons • Dose/Fluence range and sensitivity needed? • Active and/or passive devices ? • readout cycle? / replacement cycle?

  15. Questions to experiments • Number of monitoring modules? • Environment of module? • Temperature and Temperature stability? • Space constrains? • Maximum size of sensor module? • Distance between sensor and readout electronics (cable length)? • Lifetime of modules? • Will we be able to repair/replace/upgrade them? • Readout: • Radiation hard electronics on-board needed (OSL needed)? • Specific restrictions due to the individual experiments? • Which kind of signals can be accepted by the detector control system of the Experiment? • Deadlines • Decision about size of the module • Decision about number of cables • Decision about signal type • Installation deadline • Service/Maintenance after installation • Which kind of service/maintenance is expected after installation?

  16. Time Schedule (TA1) • End 2004 • First prototype of integrated board and readout system tested • Mid 2005 • Components of radiation monitoring board fixed • End of 2005 • Full prototype tested • Start of mass production