1 / 31

Activity-Based Costing

Activity-Based Costing. Key Concepts. Costs. Life cycle First Operating & Maintenance Disposal Sunk Future Opportunity Direct Indirect Overhead Fixed Variable. Cost Structure for Manufacturing. Direct material Direct labor Sum is prime costs Indirect material

nkornegay
Télécharger la présentation

Activity-Based Costing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Activity-Based Costing Key Concepts rd

  2. Costs • Life cycleFirstOperating & MaintenanceDisposalSunkFutureOpportunityDirectIndirectOverheadFixedVariable rd

  3. Cost Structure for Manufacturing • Direct material • Direct labor Sum is prime costs • Indirect material • Indirect labor Factory overhead • Fixed and miscellaneous Sum is cost of goods made • General and administrative • Selling Sum is cost of good sold • Profit Sum is selling price rd

  4. Cost Estimating • What cost components must be estimated? • First component ~ equipment, delivery, installation insurance, training • Elements – Direct labor and materials, maintenance • What approach to cost estimation will be applied? • Bottom-up, design-to-cost or top-down • How accurate should estimates be? • ROMs ~  20% of actual costs, Detail  5% • What estimation techniques will be used? • Unit, cost indices, learning curves, capacity, analogy rd

  5. Cost Estimation • Cost component • estimates • Cost • Estimates Required price Bottom-Up Required price Top-Down DTC rd

  6. Unit Method • CT = U x N • Cost of operating a car (43 cents / mile) • Cost to bury fiber cable ($30K / mile) • Cost to construct a parking space in parking garage $4500 • Cost to construct Interstate highway ($6.2 M /mile) • Cost of house construction ($225 /ft2) rd

  7. Total Cost Estimate rd

  8. Cost Indexes • Cost index is a ratio of the cost of something today to its cost sometime in the past. • CPI ~ Consumer Price Index rd

  9. Cost Capacity • C2 = C1 (Q2 /Q1)x (It /I0) • The total cost for a digester with a flow rate of ½ MGD was $1.7M in 2000. Estimate the cost for a flow rate of 2 MGD. The cost index in 2000 of 131 is now 225 and the exponent x = 0.14 for the range flow 0.2 to 40 MGD. • C2 = 1,700,000 * (2/0.5)0.14 (225/131) • = $3,546,178. • Component Size Range Exponent • Activated sludge plant 1-100 MGD 0.84 • Aerobic digester 0.2-40 MGD 0.14 • …. … … rd

  10. Cost Estimating Relationships • Factor Method (Hans J. Lang) • CT = h x CE • Total cost = factor times cost of major equipment where h is usually used as 4. • Delivered equipment cost is $1.55M imply a total cost of • 4 * $1.55M = $6.2M • Factor method can be broken down into direct and indirect costs. h = 1 + => CT = [CE(1 + )](1 + fd) rd

  11. Learning Curve • TN = T1 Nb where N is unit number, T1 is cost or time for first item, TN is the cost or time for the Nth unit and b is the slope of the learning curve in decimal. • b = (Log learning-rate 2) = Ln L / Ln 2 • Unit Hours Cumulative(sim-lc 100 10 90) 1 100.00 100.00 • 2 90.00 190.00 • 3 84.62 274.62 • 4 81.00 355.62 • 5 78.30 433.92 • 6 76.16 510.08 • 7 74.39 584.47 • 8 72.90 657.37 • 9 71.61 728.98 • 10 70.47 799.45 rd

  12. Learning Curve Example • To build 25 FEMA test units took 200 hours for the first one. The direct and indirect labor costs average $50.hour and 80% learning curve is assumed. Estimate the total labor cost for the 25 units. (sim-lc 200 25 80) • Unit Hours Cumulative Unit Hours Cumulative 1 200.00 200.00 16 81.92 1784.03 • 2 160.00 360.00 17 80.34 1864.36 • 3 140.42 500.42 18 78.87 1943.24 • 4 128.00 628.42 19 77.51 2020.75 • 5 119.13 747.55 20 76.24 2096.99 • 6 112.34 859.88 21 75.05 2172.04 • 7 106.90 966.78 22 73.94 2245.98 • 8 102.40 1069.18 23 72.89 2318.87 • 9 98.59 1167.77 24 71.90 2390.76 10 95.30 1263.07 25 70.96 2461.72TC = 2461.72 * 50 = $123,086 • 11 92.42 1355.50 • 12 89.87 1445.37 • 13 87.58 1532.95 • 14 85.52 1618.47 • 15 83.64 1702.11 rd

  13. Indirect Cost (Overhead) • Traditional Overhead = Estimated total indirect cost • Estimated basis level • Allocation Basis Indirect Cost Category • Direct labor hours Machine shop, human resources, supervision • Direct labor cost Machine shop, supervision, accounting • Machine hours Utilities, IT network servers • Cost of materials Purchasing, receiving, inspection • Space occupied Taxes, utilities, bldg maintenance • Amount consumed Utilities, food services • Number of items Purchasing, receiving, inspection • Number of accesses Software • Number of inspections Quality assurance rd

  14. Blanket Rate • Example • Blanket indirect cost rate = total expected indirect costs • total estimated materials costs • Automated vs. non-automated could cause discrepancy with low value items mixed with high value items resulting in over-accumulating of indirect costs for -lower value items. rd

  15. Economic Value Added (EVA) • EVA ~ adding value to the shareholders • looks at the difference between net operating profit and the cost of capital. rd

  16. Activity Based Cost (ABC) Accounting • Rate sensitive to value added is a production hour rate method. • Using more than one basis led to the ABC method. • Factory costs are the sum of the costs of goods. • Automation advances result in decreased direct hours. • Once 35% to 45% of final cost due to labor; now 5 to 15% • Indirect cost comprise as much as 35% to 45% of total cost rd

  17. Four Key Concepts • Activity accounting ~ decomposes into a cause-and-effect rationale of how activities results in outputs • Cost Drivers ~ an event that affects cost/performance of a group of related activities. Number of machine hours, engineering change notices, purchase orders • Direct traceability ~ attributing costs to products or processes that consume resources • Non-value-added costs • ABC identify and place a cost on the activities performed so that management can determine desired changes rd

  18. Example • XYZ makes 2 models Qt = 50K each Model A • Direct material cost $2,800,600Direct labor cost $ 350,000Direct labor hours 35,000  $7MModel BDirect material cost $ 1,500,000Direct labor cost $ 250,000Direct labor hours 25,000  $5M • Total Manufacturing overhead costs $12,000,000 • Traditional (volume-based absorption) costing systemCost rate = Total Overhead Costs / Total Direct Labor Hours • = 12M / 60K hours = $200 per direct labor hour Allocated overhead 35K hours * $200 = $7M Model A => $10,150,600Allocated overhead 25K hours * $200 = $5M Model B => $6,750,000 • Total costs for 50K units $10,150,600/50K = $203 A and $135 B … continued  rd

  19. Activity-based Costing DataSix Main Activities for Manufacturing Activity $ Costs Cost Driver Budgeted RateProduction $8M # of machine hrs 200K hoursEngineering 1M # ECO 40K orders Material Handling 1M # of material moves 60K movesReceiving 800K # of batches 500 batchesQuality Assure 800K # of inspections 20K inspectionsPack & Ship 400K # of products 100K products rd

  20. ABC Driver Rates for Models A & B Activity Model A Model B Production 50K hours 150K hoursEngineering 15K orders 25K ordersMaterial Handling 20K moves 40K movesReceiving 150 batches 350 batchesQuality Assurance 6K inspections 14K inspectionsPack & ship 50K products 50K products rd

  21. EVA Example NOPAT Net Operating Profit After Taxes rd

  22. ABC for XYZ • Applied Activity Rate Model A Model BProduction $40/machine hr $2M $6MEngineering $25/ECO $375K $625KMaterial Hand $16.67/move $333,400 $666,600Receiving $1,600/batch $240,000 $560,000QA $40/inspection $240,000 $560,000Pack & Ship $4 / product $200,000 $200,000 • Total Overhead Costs $3,388,400 $8,611,600 • Direct material cost $2,800,600 $1.5M Direct labor costs $350,000 $250KTotal costs $6,539K$10,361,600 Cost per unit $130.78 $207.23 • Cost per unit (traditional) $203 $135 • $12M = $3,388,400 + $8,611,600Example: Production consumes 50K + 150K = 200K machine hours. $8M/200K = $40/machine hr. rd

  23. Activity-based Costing vs. Traditional(Volume-based absorption VBC) Model A is less expensive to make than Model B.\ Traditional based cost estimates on Model A being responsible for more overhead costs than B using direct labor hours as its base. In reality Model B incurs more overhead because of difference in number of transactions. rd

  24. ABC Example • A firm with 4 plants used traditional methods for business travel. See table below. Last year $500K in travel expenses were distributed at a rate of $500K/29,100 = $17.18 / employee. A switch to ABC was considered. rd

  25. Travel Voucher Basis 500,000, 500 = $1000/voucher rd

  26. Problem • If the processing cost decreases by a constant 4% every time the output is doubled, the slope parameter of the learning curve is closest to: • -0.009 b) -0.059 c) 0.991 d) -1.699 • (Log 0.96 2)  -0.058894 rd

  27. Problem • The cost of a robot is $80K and the cost for one with twice the capacity is $120K. The value of the exponent in the cost-capacity equation is closest to • 0.51 b) 0.58 c) 0.62 d) 0.69 • C2 = C1 (Q2 /Q1)x (It /I0) • 120 = 80*2x • x = 0.58496 rd

  28. Problem • Delivered equipment costs $650K with direct cost factor 1.82 and indirect cost factor 0.31. The total plant cost estimate is approximately • $2,034,500 b) $1,734,500 • $1,384,500 d) $1,183,000 • TC = (1 + 1.82 + 0.31) * 650K = $2,034,500 rd

  29. Problem • Police want to allocate indirect cost for speed monitoring of 3 toll roads. An allocation basis that may not be reasonable is • Miles of toll road monitored • Average number of cars patrolling per hours • Amount of car traffic per section of toll road • Cost to operate a car. rd

  30. Problem • First one took 24.5 seconds to paint with a 95% learning rate. How long to paint the 10th one? • 20.7 seconds b) 0.46 seconds • 2.75 seconds d) 15.5 seconds • T10 = 24.5 * 10 (Log 0.95 2) • = 20.66 sec. rd

  31. Problem • Cost of capital is 12%. Consider the two firms below. • Which seems better? Firm B, but Firm A is better. rd

More Related