Stress Corrosion Cracking (SCC). Josef Kopec, P.Eng. First SCC Inquiry. 1985-1992 one company 5 SCC ruptures First Inquiry 1993 Considering current knowledge of SCC Concluded that SCC managed properly. SCC Inquiry 1996. Two ruptures in 1995

olin
Télécharger la présentation

Stress Corrosion Cracking (SCC)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Stress Corrosion Cracking (SCC) Josef Kopec, P.Eng.

  2. First SCC Inquiry • 1985-1992 one company 5 SCC ruptures • First Inquiry 1993 • Considering current knowledge of SCC • Concluded that SCC managed properly

  3. SCC Inquiry 1996 • Two ruptures in 1995 • Evidence SCC widespread on both gas and liquid pipelines • Since 1977 - 22 failures • 12 ruptures, 10 leaks • Provide a forum to share SCC knowledge • Knowledge shared around world

  4. Inquiry Report Recommendations in 6 Key Areas • SCC management program for all pipelines • Changes to the design of pipelines • Continued research • Establishment of SCC database • Improved emergency response practices • Continued information sharing

  5. Post-SCC Inquiry • SCC Inquiry Report • NEB SCC Liaison Group • Community visits • SCC Management Plans submitted by All NEB regulated companies & reviewed • Meetings with numerous companies

  6. NEB SCC Liaison Group • Industry Groups and Regulators • Monitor progress of implementation of recommendations • SCC research - funding • CEPA/CAPP SCC database & trending

  7. Ongoing activities • Qualitative Risk Ranking of Companies SCC Susceptibility • SCC Management Plan Updates (1999) • Company Meetings • NEB SCC Liaison Group

  8. Canadian Energy Pipeline Association (CEPA) 2000 SCC Database Trending Report Results • note: physical inspection

  9. Significant SCC Reported(December, 2003) Significant SCC reported to the NEB as per the requirements of Inquiry report

  10. Plans and Priorities -SCC Integrity Issues • Continue to meet with companies • Continue to monitor incidents of SCC • Integrate SCC Management with Integrity Management Plan audits

  11. SCC in Perspective Causes of in-service pipeline ruptures: 1985-95 General Corrosion Other Contact Damage (contact by earth moving equipment, etc.) SCC (Geotechnical landslides, etc.)

  12. On-going Integrity Issues • SCC is one of many time dependent integrity concerns • On going monitoring of: • ERW seam problem • Corrosion - • General, Narrow Axial External Corrosion, Corrosion Fatigue • Hard Spots

  13. Management of Integrity Issues • Management system audits • Require companies to perform Engineering Assessments • Information sharing with other Regulators and Industry • meetings • conferences

  14. Common Goal • NEB regulated facilities and activities are safe and perceived to be safe