An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Puesta Del Sol II Progress and Update Report May, June, & July, 2000

  2. Side View Top View The Stainless Steel Ladder $2,100 US

  3. Guards uniforms & security • Uniform • Hat • Days.......Rafael • Nights.....Tolentino • Sundays.. Rafael Tolentino Luis

  4. No Glass Containers

  5. Pool Maintenance • Pressure wash monthly • Ordered 5 new lights • Ordered tile to fix small damaged tiles • To regrout in September

  6. Wind Turbines • Installed 4 Wind Turbines on sewer vents • Act as wind powered extractors creating a negative pressure on sewer vents • Reduce odor on windy days in the condos

  7. AC Leak on Roof.....7 South

  8. Old leak coming through AC plumbing Fiberglassed panels on roof and side To do similar work on South side to prevent future leak Leaking roof 7 North

  9. Attic Tour...TV....OTIS

  10. Water Meters ......16 installed

  11. Spiral Stairs to be repainted

  12. The Box on the side

  13. POOL AREA regrout pool replace pool lights replace glass install barrier I and II install Jacuzzi pump rewire pool room BUILDING clean cistern replumb water pump elevator, tile floor. paint shaft. & cable repairs paint spiral stairs general cleaning & painting September 16 to 23....closed