1 / 34

Entergy Mississippi, Inc. Proposed Transmission Reliability Projects

Entergy Mississippi, Inc. Proposed Transmission Reliability Projects. Entergy Transmission Planning Summit New Orleans, LA July 10, 2003. 2004/2005 EMI Transmission Reliability Projects. Capacitor Banks 2004. Andrus-Greenville Upgrade Line Carryover 2003-04. Tillatoba Auto 2005-06.

omar
Télécharger la présentation

Entergy Mississippi, Inc. Proposed Transmission Reliability Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Entergy Mississippi, Inc.Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003

  2. 2004/2005 EMI Transmission Reliability Projects Capacitor Banks 2004 Andrus-Greenville Upgrade Line Carryover 2003-04 Tillatoba Auto 2005-06 Livingston Rd. & Ridgeland Convert to 230kV 2005-06 Rankin-S. Jackson New 230kV Line Carryover 2003-2005 Franklin-Brookhaven Upgrade Line 2004-05 Georgetown-Hazelhurst New Line 2005-06 Franklin Auto 2003-04 Carryover Amite-Fernwood Upgrade Line 2005-06

  3. Andrus to Greenville:Build New 115 kV Line Scenario: • The 115kV Gerald Andrus to Greenville loop is located in North Mississippi. It consists of two lines, 5.3 miles each. These lines serve the city of Greenville. • The single contingency loss of either side of the loop overloads the remaining section by 30%. Recommended Solution: • To relieve the overloading condition described above, reconductor the existing, 954 ACSR conductors to 954 ACSS to obtain a line rating of 359 MVA on the two lines from Gerald Andrus to Greenville. The new ACSS conductor provides a higher ampacity than a comparable size ACSR conductor due to its metallurgical properties. This will allow most of the existing structures to be re-used providing a lower cost solution than the original proposal to build a third line from Gerald Andrus to Greenville. Estimated Cost: $2,700,000

  4. Franklin 500/115 kV Substation:Add Second 500/115 kV Autotransformer Scenario: • Franklin substation has three single-phase autotransformers, 500 MVA total, 500/115kV with a single-phase spare in place. • Loss of one phase causes overloads on 115kV system and widespread undervoltages within the entire south Mississippi and north of Lake Pontchartrain area in ELI’s service territory. • As an interim solution, an undervoltage loadshed scheme has been installed for the loss of the transformer. Recommended Solution: • Install a parallel three phase autotransformer with breakers & relaying Estimated Cost: $8,800,000

  5. Jackson Improvement Plan Phase I:Rankin to S. Jackson: Build New 230 kV Line Scenario: • The 115kV system serving the Jackson area is heavily loaded. Single contingencies in the North and South Jackson area will cause overloads as high as 33% on the 115kV transmission system. The solution is to shift load off of the 115 kV system to the 230 kV system by converting Livingston Rd. 115 kV and Ridgeland 115 kV to 230 kV. The completion of the 230kV loop around Jackson will allow for shifting load to the 230 kV system. The line is currently scheduled for an ISD of 2005. The Livingston Rd. and Ridgeland 230 kV conversions are proposed to be in service in 2005 and 2006. Recommended Solution: • Construct the Rankin to S. Jackson 230kV line. This will also allow for additional S. Jackson area load on the 115kV system to be moved to the 230kV system. • The proposed Rankin to S.Jackson 230kV line will be approximately 20 miles long. Estimated Cost: $10,200,000

  6. Franklin to Brookhaven:Increase Line Capacity Scenario: • The Franklin to Brookhaven transmission path consist of two 115kV transmission lines. The Franklin to Brookhaven lines are critical sources into the south Mississippi area. It provides power from the 500kV system at Franklin. The north line ( Franklin-Vaughn-W. Brookhaven-Brookhaven) is constructed of 666 ACSR. • The loss of the south line ( Franklin-Brookhaven S.-Brookhaven) will overload the north line by 23%. Load will have to be shed during the peak season to reduce the overload to 100%. There are no operating procedures to mitigate this circumstance. This overload will increase when a second autotransformer is added to Franklin. Recommended Solution: • Upgrade the line from Franklin to Vaughn to West Brookhaven to Brookhaven (18.26 miles) with 1590 ACSR. Upgrade all appropriate switches, bus work and other devices as necessary. Estimated Cost: $4,940,000

  7. Jackson Improvement Plan Phase II:Convert Livingston Road & Ridgeland to 230 kV Scenario: • The 115kV line from Lakeover-NE Jackson-Rex Brown is 25 miles long. • The loss of the Lakeover - Livingston Rd. 115 kV, Livingston Rd. – Ridgeland 115 kV, Rex Brown – N. Jackson 115 kV or N. Jackson - Canton Rd. 115 kV in 2004 causes overloads on 4 lines by as much as 33%. By 2007, 5 lines would overload by as much as 35%. Recommended Solution: • Convert the Livingston Rd 115kV substation to 230kV in 2005 and convert the Ridgeland 115kV Substation to 230kV in 2006 on the Lakeover to Luckney to Rankin 230kV line. Estimated Cost: $1,700,000

  8. Tillatoba 230/115 kV Substation:Add Second 230/115 kV Autotransformer Scenario: • Tillatoba substation has three single-phase autotransformers, 392 MVA total, 230/115kV with one single-phase spare in place. • The loss of the Tillatoba 230/115kV autotransformer causes low voltages and numerous overloads throughout the northern Mississippi area. This contingency causes 18 buses to fall below 92% voltage and 9 line overloads. Recommended Solution: • Install a parallel single-phase autotransformer with Breakers & Relaying Estimated Cost: $4,800,000

  9. Georgetown to Hazelhurst:Build New 115 kV Line Scenario: • The SW Jackson to Byram to Brookhaven line is 53 miles long with 234MWs of load. • The loss of SW Jackson - Elton 115 kV or Elton - Byram 115kV lines will overload the segments from Brookhaven to Hazlehurst by as much as 43% in 2004. Voltages as low as 78% would be caused on 16 buses from Terry to Brookhaven to McComb to Tylertown . By 2007, the voltages would decrease to as low as 62% on 29 buses, and the loss of Wesson - Brookhaven 115 kV or Wesson to James Rd. will cause overloads by 15% on SW Jackson - Elton - Byram 115kV line. This project will also delay the need to upgrade Ray Braswell – West Jackson 115 kV and Ray Braswell – Forest Hill 115 kV lines. Recommended Solution: • Build a new 115kV line from Georgetown to Hazelhurst using 1272 conductor to obtain a line rating of 261 MVA. Estimated Cost: $9,300,000

  10. Amite to Fernwood:Increase Line Capacity Scenario: • The Amite to Fernwood 115kV line, located in south Louisiana, north of Lake Pontchartrain, extending north into southern Mississippi is 32 miles long. Amite is approximately 17 miles from the Mississippi state line and Fernwood is approximately 15 miles from the state line. This 115kV line, constructed with 4/0 ACSR conductor, is part of the Amite to McComb tie between MPL and LPL. • Single contingencies in Mississippi of Brookhaven to Mallalieu, Mallalieu to Norfield, Norfield to McComb or Franklin Auto in 2004 will cause overloads up to 70% on the Amite-Kentwood-Colonial Pipeline-Fernwood line segments. Recommended Solution: • Reconductor the existing, 4/0 ACSR (68MVA) conductors to 1272 to obtain a line rating of 261 MVA on the line from Amite to Fernwood line. Estimated Total Cost: $14.4M for ELI & EMI • EMI’s portion: ~$7,000,000

  11. 2006 - 2008 EMI Planned Carryovers Tillatoba Auto Carryover 2005-06 Livingston Rd. & Ridgeland Convert to 230kV Carryover 2005-06 Georgetown-Hazelhurst New Line Carryover 2004-06 Amite-Fernwood Upgrade Line Carryover 2005-06

  12. 2006 - 2008 EMI Transmission Reliability Projects Capacitor Banks 2005-08 Tillatoba to S. Grenada Build New Line 2007-08 Hollandale 230/115 kV Auto 2006-07 Ray Braswell Add Second 500/230kV Auto 2006-2007 Franklin to Brookhaven S. to Brookhaven Upgrade Line 2007-08

  13. Ray Braswell:Add Second 500/230 kV Autotransformer Scenario: • Ray Braswell has one 560 MVA, 500/230kV autotransformer and one 560MVA, 500/115kV autotransformer. • The loss of the Ray Braswell to Lakeover 500kV line will overload both the Ray Braswell 500/230kV and the Ray Braswell 500/115 kV autotransformers by 11% in 2007. Recommended Solution: • Install a parallel 560MVA 500/230MVA autotransformer with breakers & relaying at Ray Braswell. Estimated Cost: $15,000,000

  14. Franklin to Brookhaven South to Brookhaven:Increase Line Capacity Scenario: • The Franklin to Brookhaven transmission path consists of two 115kV transmission lines. The Franklin to Brookhaven lines are a critical source into the south Mississippi area. It provides power from the 500kV system at Franklin. The south line ( Franklin - Brookhaven S. - Brookhaven) is constructed of 954 ACSR conductor. • With the addition of a parallel 500/115 autotransformer at Franklin, the loss of the north line (Franklin to Vaughn to Brookhaven) will overload the south line by 13% in 2007. Load will have to be shed during the peak season to reduce the loading on the line to 100%. There are no operating procedures to mitigate this circumstance. Recommended Solution: • Upgrade the line from Franklin to Brookhaven S. to Brookhaven with 1780 ACSR. Upgrade all appropriate switches, bus work and other devices as necessary. Estimated Cost: $5,000,000

  15. Hollandale Substation:Install 230/115 kV Autotransformer Scenario: • The Greenville to Hollandale 115kV line, located in northwest Mississippi, is 23.5 miles long and the Hollandale to North Vicksburg 115kV line is 59 miles long. • The loss of any section of line from Greenville to Hollandale will cause all the line sections from Vicksburg to Hollandale to overload by as much as 61% in 2007. This will also cause voltages as low as 51% from Redwood to Hollandale. Recommended Solution: • Connect Gerald Andrus - Ray Braswell 230 kV line into Hollandale and install a 230/115kV autotransformer. Before the transformer is installed, the Hollandale – Greenville TCEPA SS – S.E. Greenville 115 kV line must be upgraded to 1272 ACSR (20 miles long). Estimated Cost: $12,000,000 (Includes line upgrade)

  16. Tillatoba to South Grenada:Build New 115 kV Line Scenario: • The 115kV line from Tillatoba to S. Grenada is 19 miles long and part of a 43-mile line to Winona. • The loss of the Tillatoba to Grenada line in 2004 causes voltages as low as 81% on five buses, and overloads on three lines by as much as 34%. In 2007, there are 11 buses with voltages between 92% to 62%, and overloads on 7 115kV lines by 7% to 93%. Recommended Solution: • Build a single separate line from Tillatoba to S. Grenada with 1272 ACSR (or equivalent conductor). The line should be built for 230kV and operated at 115kV. Estimated Cost: $6,000,000

  17. 2009-2013 EMI Transmission Reliability Target Areas Batesville to Getwell Build 230kV line Jackson 230kV Improvement Plan Natchez Area Franklin to McComb Build New 115kV line

  18. Memphis Freeport Tennessee Mississippi Horn Lake Walls Greenbrook DeSoto Plum Point Banks Switch Nesbit Switch Nesbit Robinsonville 230-12.47kV Getwell Banks CEPA 230-115kV Hernando Future 230kV Line Tunica 115 Tunica 230 Coldwater Senatobia Lula Crenshaw Como Sardis Batesville

  19. Questions

More Related