1 / 82

Chatham-Kent Health Alliance

Chatham-Kent Health Alliance. Facility Renewal and Capital Infrastructure Needs Tri Board Meeting October 26, 2010. Facility Renewal and Capital Infrastructure Needs October 2010.

oriole
Télécharger la présentation

Chatham-Kent Health Alliance

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chatham-Kent Health Alliance Facility Renewal and Capital Infrastructure Needs Tri Board Meeting October 26, 2010

  2. Facility Renewal and Capital Infrastructure NeedsOctober 2010 • Chatham-Kent Health Alliance is a partnership of 3 hospital corporations: Public General ( PGH), St. Joseph’s Hospital ( SJH) and Sydenham District Hospital (SDH). • Request to review current state and capital needs for facility upgrades • PGH – dates back to 1954 • SDH – dates back to 1955 • Both facilities have reached a critical point in their life expectancy and are in need of major investment to maintain patient and staff safety.

  3. Facility Renewal and Capital Infrastructure NeedsOctober 2010 • !magine redevelopment project is 10 plus years away • Inadequate resources available over the years to support infrastructure upgrades • Sydenham and Public General buildings are outdated and do not meet code in many areas, (i.e. building, medical gas, fire codes, etc.)

  4. Facility Renewal and Capital Infrastructure NeedsOctober 2010 • Costs are estimates • Many upgrades cannot be done in isolation of one another • Any changes to current systems will require all code upgrades • Significant capital facility upgrades will require Ministry approval • Cannot bring certain systems up to code given building structure limitations • Does not include capital needs for the SJC or offsite properties, i.e. 47 Emma, MHA, adjacent houses. • Multi-year coordinated plan and dedicated annual resources required to proceed with any upgrades

  5. Facility Renewal and Capital Infrastructure NeedsOctober 2010 • References used: • Cohos Evamy Facility Audit Report July 2009 • Honeywell Energy and Facility Renewal Report 2009 • Emergency Department Hay Study 2009 (LHIN study) • Asbestos Audits – Advanced Environmental Corporation 2007 • Stantec Facility Audit Report SDC 2005 • Applied Building Sciences LTD Facility Audits – 2002 & 2004 PGC and SDC • Additional Inspections, i.e. Medical Gas, Fire Marshall, HIROC, Roofing Inspections, etc. • External Contractors and CKHA Engineering Staff

  6. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus

  7. Roofing Cost Estimate $1,000,000 Multi-Year project will be complete 2010-2011 $ not included in total request Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus

  8. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusRoof Replacement Plan

  9. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus Windows • Cost Estimate $ 1,500,000 • Connected to envelope deterioration project • Add: Building Envelope • Asbestos Abatement

  10. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusExterior Window

  11. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusInterior Window

  12. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus Building Envelope • Cost Estimate $ 1,500,000 + • Connected to Window deterioration project • Add: Window Replacement • Asbestos Abatement

  13. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusHeat Loss from Building Envelope

  14. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusHeat Loss from Building Envelope

  15. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus Balconies • Cost Estimate $330,000 • Deterioration to the point of unsafe • Do not meet code • Currently locked for safety, no access • Add: Building Envelope repair if balconies need to be removed

  16. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusExterior Balcony

  17. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusExterior Balcony

  18. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Fire System Upgrade • Cost estimate $ 1,000,000 • Does not meet code • Currently equipped with smoke and heat detectors • Must bring up to code when doing any renovation (only 2 sprinklers at present time) • Add: Structural changes (Ceiling heights) • Asbestos abatement • Electrical upgrade

  19. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus Elevators Upgrade • Cost Estimate $ 250,000 • Interior Upgrades 2010 – floors, walls, lighting • Control Systems need complete upgrade • Only one elevator accommodates a stretcher • Add: Electrical system upgrade • Asbestos abatement

  20. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham CampusElevator Mechanical Room

  21. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusElevator Control Panels

  22. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus Ventilation System Upgrade • Cost Estimate $5,000,000 - $7,000,000 • End of life, does not meet code • Current ceiling heights do not allow for proper replacement to meet code • Add: Structural Changes (ceiling heights) • Electrical upgrade • Fire system upgrade • Medical gas system upgrade • Asbestos abatement

  23. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham CampusOperating Room Air Handler • Manual controlled, No humidification – original unit

  24. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusGeneral Air Supply – East Wing • Dampers are not working, over 15 years ago 35% of coils were removed do to coils were leaking (frozen), no humidification • Never reinstalled

  25. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus Medical gas system upgrade • Cost Estimate $ 500,000 • System does not meet code, any changes to the system will require the entire system be brought up to code • Add: Structural changes (walls and ceilings) • Asbestos abatement

  26. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Asbestos Abatement • Cost estimate $ 2,000,000 • Must be factored in to any and all changes to SDC • Add: Structural changes (walls and ceilings)

  27. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Sanitary and Storm drain piping • Cost Estimate $ 3,000,000 • Does not meet code (Asbestos piping) • Current piping is all cracked • Requires major demolition to access prior to any potential repair • Add: Structural changes (walls and ceilings) • Asbestos abatement

  28. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusPlumbing Stack – Deteriorated Sewer Piping

  29. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusDeteriorated/ Cracked Piping • all located in brick pipe chase

  30. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusDiscovery of Sewer Piping Installation, after leak investigation

  31. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Waterlines • Cost Estimate $ 2,000,000 • Does not meet code (galvanized piping) • Current piping is corroding • Risers are located in brick pipe chases • Add: Structural changes (walls and ceilings) • Asbestos abatement

  32. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham CampusHot Water Supply Line Corrosion

  33. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham CampusHot Water Supply Line Corrosion

  34. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham CampusDiscovered During Recent Repair - Laundry

  35. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Boilers - Replacement • Cost Estimate $ 200,000 • End of life • RFP issues September 2010 for replacement of one boiler • Add: Electrical upgrade • Asbestos abatement

  36. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusSteam and Hot Water Boilers

  37. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusDeteriorated Boiler Tubing

  38. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus Chiller Replacement • Cost Estimate $ 275,000 • End of life • Supplies only the OR • Add: Electrical upgrade • Asbestos abatement

  39. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusOperating Room Chiller

  40. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus Heating system upgrade (Radiant heating) • Cost Estimate $ 210,000 • End of life • Add: Structural changes (walls and ceilings) • Asbestos abatement • There is an in-floor heating system on the first floor in part of the emergency, ambulatory care department and both side of the hallway in the West wing. • Source of leak cannot be located as system is buried in concrete. This system is shut down and not in use.

  41. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus Electrical system upgrade • Cost Estimate $ 1,000,000 • System is obsolete • Does not meet code • Switched are no longer manufactured • Add: Structural changes (ceilings and walls) • Asbestos abatement

  42. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham CampusOld Electrical Panels

  43. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus OR Upgrades • Cost Estimate $ 1,000,000 • Does not meet current code and standards • Consideration should be given to closing this section if continues to function as regular OR • Add: Electrical upgrade • Medical air systems upgrade • Ventilation system upgrade • Structural changes (walls and ceiling) • Asbestos abatement

  44. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus Installation of negative pressure rooms • Cost Estimate $ 500,000 • Currently no negative pressure room • Safety risk for airborne illness • Current patients transferred to Chatham • Add: Electrical system upgrade • Medical air system upgrade • Plumbing system upgrade • Ventilation system upgrade • Structural changes (walls and ceiling) • Asbestos abatement

  45. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Removal of Sewer tank • Cost Estimate $ 40,000 – $ 50,000 • Current Emergency Department partly build on a sewer holding tank • 2010-2011 Capital plan – drain and connect to municipal line

  46. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Structural/Building reinforcements upgrade • Cost Estimate $ 2,000,000 • Any changes in use or modification to the floor layout of the 1967 structure will require reinforcement of the structural system below the affected area. • (Cohos pg. B-3)

  47. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus Renovation to patient rooms • Cost Estimate $ 4,000,000 • Current rooms do not meet code • Washrooms are small and inaccessible • Do not meet Infection Control standards – sinks are located outside of washroom • Add: Plumbing upgrade • Electrical system upgrade • Ventilation system upgrade • Medical air system upgrade • Structural changes (walls and ceiling) • Asbestos abatement

  48. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham CampusPatient Washroom & Outside Sink

  49. Facility Renewal and Capital Infrastructure Needs October 2010 – Sydenham Campus ED Renovations • Cost Estimate $ 500,000 • Emergency Department LHIN Hay study - physical plant is inadequate by current standards

  50. Facility Renewal and Capital Infrastructure NeedsOctober 2010 – Sydenham Campus Accessibility • Accessibility for Ontarians with Disabilities Act, 2005 (AODA) • Unable to determine cost at this point • Add: Structural changes (walls and ceilings)

More Related