THOTAPALLY BARRAGE PROJECT

THOTAPALLY BARRAGE PROJECT. LEFT HEAD SLUICE. Under Execution. PACKAGE-3. LEFT EARTH DAM 4197M. LEFT LINK CHANNEL 540M. EXISTING REGULATOR. EXISTING LEFT MAIN CANAL 64,000 ACRES. 500M. RESERVOIR FRL +105.00M. SPILLWAY 117M. CAPACITY 2.52 TMC. RIGHT LINK CHANNEL 210 M.

osma
Télécharger la présentation

THOTAPALLY BARRAGE PROJECT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. THOTAPALLY BARRAGE PROJECT LEFT HEAD SLUICE Under Execution PACKAGE-3 LEFT EARTH DAM 4197M LEFT LINK CHANNEL 540M EXISTING REGULATOR EXISTING LEFT MAIN CANAL 64,000 ACRES 500M RESERVOIR FRL +105.00M SPILLWAY 117M CAPACITY 2.52 TMC RIGHT LINK CHANNEL 210 M PACKAGE-3 RIVER NAGAVALI Km. 52.450 PROPOSED RIGHT MAIN CANAL 1,20,000 ACRES RIGHT HEAD SLUICE RIGHT EARTH DAM 4197M PACKAGE-4 EXISTING RIGHT CANAL Km. 107.00

  2. THOTAPALLY BARRAGE SCHEME

  3. THOTAPALLY BARRAGE SCHEME

  4. THOTAPALLY BARRAGE SCHEME Non-EPC-1: Construction of Spill way Regulator across Nagavali River from Km.4.197 to Km.4.314, Vijayanagaram Dist. Name of the Contractor : M/s. Prasad & Co.(PW) Agreement Amount : Rs. 11.12 Crs. Agreement Date : 16-03-2004 Period of Completion : 18 Months(9 Mile Stones) (Now proposed as 25 Months Target Date of Completion : 4/2006 • Investigation : Completed • Designs : Completed • Execution : in progress • Qty. of earth work done : 70,000 cum against 79,900 cum. • Qty. of concrete work done : 38563 cum against 44,700 cum. • No. Machinery deployed : 10 Nos. (Excavators 2 Nos., Tippers 6 Nos., Generators 2 Nos. etc) • Expenditure : 2004-2005 - Rs. 1.96 Crs. • 2005-2006 - Rs. 6.36 Crs. • Cum. Inc. Mob. Adv. only - Rs. 8.34 Crs. • Land Acquisition : Completed

  5. THOTAPALLY BARRAGE SCHEME Non-EPC-2 : Right Earth Dam from Km.4.5 to Km.8.0 including construction of Right Head Sluice at Km.6.680 Name of the Contractor : M/s. Prasad & Co.(PW) Agreement Amount : Rs. 12.85 Crs. Agreement Date : 04-06-2004 Period of Completion : 18 Months (6 Mile Stones) Target Date of Completion : 12/2005 • Investigation : Completed • Design : Completed • Execution : 3.50 Km against 3.50 Km Structures : 1 No Against 1 No. • Qty. of earth work done : 10,10,000 cum against 11,68,405 cum • Qty. of concrete work done : 1081 cum against 8370 cum. • No. of Machinery : Deployed 38 Nos. (Excavators 4 Nos., dozers 2Nos., Tippers 30 Nos. etc) • Expenditure : 2004-2005 - Rs. 6.22 Crs. • 2005-2006 - Rs. 8.61 Crs. • Cum. Inc. Mob. Adv. only - Rs. 14.83 Crs. • Land Acquisition : Required 119.22 Acres, Acquired 119.22

  6. THOTAPALLY BARRAGE SCHEME EPC-1 : Formation of Left side earth dam from Km.0.00 to Km. 4.10 including left side head sluice. Excavation of right main canal and its distributary system from Km.0.00 to Km.52.45. Name of the Contractor : M/s. Skanska Cementation India Ltd., Mumbai. Agreement Amount : Rs. 119.88 Crs. Agreement Date : 25-10-2004/21-3-2005 Period of Completion : 36 Months (12 Mile Stones) Target Date of Completion : 3/2008 • Investigation : Completed • Designs approved : 23.57 KM length against 66 KM. (Right main canal) • Execution : in progress • Qty. of earth work done : 45,000 cum against 15,00,000 cum. • No. of Machinery : Deployed = 8 Nos. (Excavators 2Nos, Tippers 6 Nos.) • Expenditure : 2004-2005 - Rs. 5.88 Crs. • 2005-2006 - Rs. 3.55 Crs. • Cum. Inc. Mob. Adv. only - Rs. 9.43 Crs. • Land Acquisition : Required 6573 Acres, Acquired 1668.52 Acres

  7. THOTAPALLY BARRAGE SCHEME Name of the Contractor : M/s. Maytas-NCC(JV) Agreement Amount : Rs. 170.02 Crs. Agreement Date : 25-10-2004/21-3-2005 Period of Completion : 36 Months (12 Mile Stones) Target Date of Completion : 3/2008 EPC-2 : Earth work excavation of Right main canal from km 52.45 to km. 107, CM & CD works and it’s distributaries & field channels. • Investigation : Completed • Designs approved : Completed Structures approved : 6 Nos. against 78 Nos. • Execution(RMC) : 4 KM length against 54 Km. • Qty. of earth work done : 8.50 Lakhs cum against 120 Lakhs cum. • No. of Machinery : deployed = 24 Nos. (Excavators 4 Nos, Tippers 50 Nos., Dozers 4 Nos. etc) • Expenditure : 2004-2005 - Rs. 8.50 Crs. • 2005-2006 - Rs. 8.00 Crs. • Cum. Inc. Mob. Adv. only - Rs. 16.50 Crs. • Land Acquisition : Required 3557 Acres, Acquired 371.00 Acres.