1 / 41

Lecture

Lecture. 4. MGMT 650 Network Models – Shortest Path Project Scheduling Forecasting. Shortest Path Problem. Belongs to class of problems typically known as network flow models What is the “best way” to traverse a network to get from one point to another as cheaply as possible?

osmond
Télécharger la présentation

Lecture

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lecture 4 MGMT 650 Network Models – Shortest Path Project Scheduling Forecasting

  2. Shortest Path Problem • Belongs to class of problems typically known as network flow models • What is the “best way” to traverse a network to get from one point to another as cheaply as possible? • Network consists of nodes and arcs • For example, consider a transportation network • Nodes represent cities • Arcs represent travel distances between cities • Criterion to be minimized in the shortest path problem not limited to distance • Other criteria include time and cost

  3. Example: Shortest Route • Find the Shortest Route From Node 1 to All Other Nodes in the Network: 5 2 5 6 4 3 2 7 7 3 1 3 1 5 2 6 4 6 8

  4. Management Scientist Input

  5. Example Solution Summary NodeMinimum DistanceShortest Route 2 4 1-2 3 6 1-4-3 4 5 1-4 5 8 1-4-3-5 6 11 1-4-3-5-6 7 13 1-4-3-5-6-7

  6. Applications • Stand alone applications • Emergency vehicle routing • Urban traffic planning • Telecommunications • Sub-problems in more complex settings • Allocating inspection effort in a production line • Scheduling operations • Optimal equipment replacement policies • Personnel planning problem

  7. Optimal Equipment Replacement Policy • The Erie County Medical Center allocates a portion of its budget to purchase newer and more advanced x-ray machines at the beginning of each year. • As machines age, they break down more frequently and maintenance costs tend to increase. • Furthermore salvage values decrease. • Determine the optimal replacement policy for ECMC • that minimizes the total cost of buying, selling and operating the machine over a planning horizon of 5 years, • such that at least one x-ray machine must be in service at all times.

  8. Lecture 4 Project Scheduling Chapter 10

  9. Project Management • How is it different? • Limited time frame • Narrow focus, specific objectives • Why is it used? • Special needs • Pressures for new or improves products or services • Definition of a project • Unique, one-time sequence of activities designed to accomplish a specific set of objectives in a limited time frame

  10. Project Scheduling: PERT/CPM • Project Scheduling with Known Activity Times • Project Scheduling with Uncertain Activity Times

  11. PERT/CPM • PERT • Program Evaluation and Review Technique • CPM • Critical Path Method • PERT and CPM have been used to plan, schedule, and control a wide variety of projects: • R&D of new products and processes • Construction of buildings and highways • Maintenance of large and complex equipment • Design and installation of new systems

  12. PERT/CPM • PERT/CPM is used to plan the scheduling of individual activities that make up a project. • Projects may have as many as several thousand activities. • A complicating factor in carrying out the activities is that some activities depend on the completion of other activities before they can be started.

  13. PERT/CPM • Project managers rely on PERT/CPM to help them answer questions such as: • What is the total time to complete the project? • What are the scheduled start and finish dates for each specific activity? • Which activities are critical? • must be completed exactly as scheduled to keep the project on schedule? • How long can non-critical activities be delayed • before they cause an increase in the project completion time?

  14. Project Network • Project network • constructed to model the precedence of the activities. • Nodes represent activities • Arcs represent precedence relationships of the activities • Critical path for the network • a path consisting of activities with zero slack

  15. 0 2 4 6 8 10 12 14 16 18 20 Locate new facilities Interview staff Hire and train staff Select and order furniture Remodel and install phones Furniture setup Move in/startup Activity Planning and Scheduling

  16. Orderfurniture Furnituresetup Locatefacilities B F A Move in Remodel E S G Hire andtrain Interview D C Project Network – An Example 6 weeks 3 weeks 8 weeks 11 weeks 1 week 9 weeks 4 weeks

  17. Critical Path Management Scientist Solution

  18. Uncertain Activity Times • Three-time estimate approach • the time to complete an activity assumed to follow a Beta distribution • An activity’s mean completion time is: t = (a + 4m + b)/6 • a = the optimistic completion time estimate • b = the pessimistic completion time estimate • m = the most likely completion time estimate • An activity’s completion time variance is 2 = ((b-a)/6)2

  19. Uncertain Activity Times • In the three-time estimate approach, the critical path is determined as if the mean times for the activities were fixed times. • The overall project completion time is assumed to have a normal distribution • with mean equal to the sum of the means along the critical path, and • variance equal to the sum of the variances along the critical path.

  20. Example

  21. Management Scientist Solution

  22. Key Terminology • Network activities • ES: early start • EF: early finish • LS: late start • LF: late finish • Used to determine • Expected project duration • Slack time • Critical path

  23. A 0 7 7 0 7 C 0 6 6 1 7 B 7 10 3 7 10 D 6 9 3 7 10 E 10 12 2 10 12 Example: Two Machine Maintenance Project Immediate Completion ActivityDescriptionPredecessorsTime (wks) A Overhaul machine I --- 7 B Adjust machine I A 3 C Overhaul machine II --- 6 D Adjust machine II C 3 E Test system B,D 2 Start

  24. Normal Costs and Crash Costs

  25. Linear Program for Minimum-Cost Crashing Let: Xi = earliest finish time for activity i Yi= the amount of time activity i is crashed 10 variables, 12 constraints Crash activity A by 2 days Crash activity D by 1 day Crash cost = 200 + 150 = $350 Crash activity A by 1 day Crash activity E by 1 day Crash cost = 100 + 250 = $350

  26. Lecture 4 Forecasting Chapter 16

  27. Forecasting - Topics • Quantitative Approaches to Forecasting • The Components of a Time Series • Measures of Forecast Accuracy • Using Smoothing Methods in Forecasting • Using Trend Projection in Forecasting

  28. Time Series Forecasts • Trend - long-term movement in data • Seasonality - short-term regular variations in data • Cycle – wavelike variations of more than one year’s duration • Irregular variations - caused by unusual circumstances

  29. Forecast Variations Irregularvariation Trend Cycles 90 89 88 Seasonal variations

  30. Smoothing/Averaging Methods • Used in cases in which the time series is fairly stable and has no significant trend, seasonal, or cyclical effects • Purpose of averaging - to smooth out the irregular components of the time series. • Four common smoothing/averaging methods are: • Moving averages • Weighted moving averages • Exponential smoothing

  31. Example of Moving Average • Sales of gasoline for the past 12 weeks at your local Chevron (in ‘000 gallons). If the dealer uses a 3-period moving average to forecast sales, what is the forecast for Week 13? • Past Sales WeekSalesWeekSales 1 17 7 20 2 21 8 18 3 19 9 22 4 23 10 20 5 18 11 15 6 16 12 22

  32. Management Scientist Solutions MA(3) for period 4 = (17+21+19)/3 = 19 Forecast error for period 3 = Actual – Forecast = 23 – 19 = 4

  33. MA(5) versus MA(3)

  34. Exponential Smoothing • Premise - The most recent observations might have the highest predictive value. • Therefore, we should give more weight to the more recent time periods when forecasting. Ft+1 = Ft + (At - Ft), Formula 16.3

  35. Linear Trend Equation Suitable for time series data that exhibit a long term linear trend • Ft = Forecast for period t • t = Specified number of time periods • a = Value of Ft at t = 0 • b = Slope of the line Ft Ft = a + bt a 0 1 2 3 4 5 t

  36. Linear Trend Example Linear trend equation F11 = 20.4 + 1.1(11) = 32.5 Sale increases every time period @ 1.1 units

  37. Actual vs Forecast Linear Trend Example 35 30 25 20 Actual Actual/Forecasted sales 15 Forecast 10 5 0 1 2 3 4 5 6 7 8 9 10 Week F(t) = 20.4 + 1.1t

  38. Measure of Forecast Accuracy • MSE = Mean Squared Error

  39. Forecasting with Trends and Seasonal Components – An Example • Business at Terry's Tie Shop can be viewed as falling into three distinct seasons: (1) Christmas (November-December); (2) Father's Day (late May - mid-June); and (3) all other times. • Average weekly sales ($) during each of the three seasons during the past four years are known and given below. • Determine a forecast for the average weekly sales in year 5 for each of the three seasons. Year Season1234 1 1856 1995 2241 2280 2 2012 2168 2306 2408 3 985 1072 1105 1120

  40. Management Scientist Solutions

  41. Interpretation of Seasonal Indices • Seasonal index for season 2 (Father’s Day) = 1.236 • Means that the sale value of ties during season 2 is 23.6% higher than the average sale value over the year • Seasonal index for season 3 (all other times) = 0.586 • Means that the sale value of ties during season 3 is 41.4% lower than the average sale value over the year

More Related