An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HSST Work Schedules HSST WP-07/06.0

  2. Background • The HSST presented its work schedule and intentions for NPAs to the OST at the 2007-02 meeting. • This included the response to OST Action 06-2 Item 21 which required the HSST to check alignment of JAR-OPS 3 with JAR-OPS 1 and develop proposals as necessary • The HSST had conducted a full alignment assessment and produced WP-06/14.4 – Harmonisation JAR-OPS 1/3. • This was further distilled into WP-07/02.1 detailing the HSST actions following the harmonisation work. • This paper also introduced an assessment of priority to these actions based on the perceived urgency or effects on safety

  3. Background • The following suggestions were made during OST 07-2, and agreed to: • The two priority 1 tasks identified in the JAR-OPS 1/3 harmonisation proposal (ACAS and In-flight Fuel Management) to be progressed by the HSST and material to be transferred to EASA • The GPWS/TAWS/ACAS proposal related to JAR-OPS 1/3 harmonisation to be sent for inclusion in the EASA inventory • The JAR-OPS 1/3 harmonisation table created by HSST to be submitted for inclusion in the EASA inventory

  4. Progress • JAR-OPS 1/3 Harmonisation Table forwarded to EASA • The HSST at 07-03 meeting decided that due to the ongoing work with IR-OPS, any additional work on producing ‘JAR-OPS 3’ text for GPWS/TAWS would be nugatory as it would be similar to the aeroplane text and harmonised within the new material • There was therefore no further action proposed • ACAS has been progressed under WP-07/04.3 and agreed at the HSST meeting in Oct 07. • EASA comment had indicated that the material will already have been covered by harmonisation within IR-OPS and that the paper is not essential. • The HSST decided to complete its development and forward a rulemaking proposal form if considered appropriate by the OST

  5. Progress • In-flight Fuel Management. When the HSST completed the original harmonisation check it was considered that the text in JAR-OPS 3 was potentially unsafe and could be improved • Since that check, JAR-OPS 1 has been further amended and the work of the IR-OPS WG also had to be considered • The HSST Notes 2007-03 recorded the following decision: • Hold development of the WP pending outcome of the WG Ops.001 drafts

  6. Proposal OST endorsement sought for: • Agreement for the suggested work on GPWS/TAWS to be suspended pending suitable harmonised text being developed within IR-OPS • Agreement for the text proposals for ACAS to be progressed and forwarded to EASA in due course • Agreement for the suggested work on In-Flight Fuel Management to be suspended pending suitable harmonised text being developed within IR-OPS

  7. Continuing Work Plan • One subject still open and in JAA T Ops Regulatory Work Overview table – Recurrent Training & Checking • Ongoing subject regarding Subpart N whichalso had additional papers dealing with OPCs and FSTDs • Deficiencies of Subpart N evident • At HSST 07-4, decision taken to amalgamate this effort into a complete review of Subpart N covering at least: • Harmonisation with Annex 6 and JAR-FCL • Harmonisation with aeroplane requirements • Training proportional to the operation • Multiple types / operations concepts

  8. Continuing Work Plan • Subpart N WG formed to report by end of Mar 08 • Next meeting of HSST planned for Feb 08 • No other work subjects planned • Future of group subject to EASA • OST endorsement sought for proposed plan as detailed above