1 / 57

I-35W Bridge Collapse

I-35W Bridge Collapse. Dan Dorgan Presentation to SCOH Annual Meeting. I-35W Bridge History. Construction started in 1964 Opened to traffic in 1967 Steel truss deck, 113 feet, 4 inches wide 64 feet high, 1,907 feet long, 14 spans Four lanes of traffic in each direction

pascal
Télécharger la présentation

I-35W Bridge Collapse

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. I-35W Bridge Collapse Dan Dorgan Presentation to SCOH Annual Meeting

  2. I-35W Bridge History • Construction started in 1964 • Opened to traffic in 1967 • Steel truss deck, 113 feet, 4 inches wide • 64 feet high, 1,907 feet long, 14 spans • Four lanes of traffic in each direction • Carried 140,000 vehicles daily, including 5,700 commercial vehicles • $440,740 to construct the piers • $4,823,262 to construct the bridge • Scheduled for reconstruction in 2020-25

  3. I-35W Bridge - Looking North July, 1967

  4. Bridge Rating • Inspected annually since 1993; before that, was inspected every two years • Superstructure rated “structurally deficient” in 1990 • This was due to: • Corrosion where the paint had deteriorated • Poor weld details in the steel truss members and floor beams • Bearings that were not moving as they were designed to move • Existing fatigue crack repairs to the approach span beams

  5. Maintenance Work at Time of Collapse • Replace concrete overlay, repair joints and lighting, and install guardrail • Work completed on outside two lanes each direction • Scheduled completion date - September 30, 2007 • Cost - $9 million • Contractor employees and Mn/DOT inspectors on bridge at collapse

  6. The Collapse • Occurs at 6:05 p.m. Wednesday, August 1, 2007 • Over 100 vehicles were on the bridge at time of collapse • 13 fatalities • 105 injuries

  7. Corps of Engineers video

  8. The Response The First 24 Hours

  9. Mn/DOT’s Regional Transportation Management Center (RTMC) Mn/DOT’s Immediate Response • 6:05 p.m. - Numerous concurrent calls to State Patrol Dispatch (911) and from field employees to RTMC and Maintenance Dispatch • 6:10 p.m. - District Emergency Operations Center activated and DEOC staff report to RTMC • Immediate traffic control for ramp and freeway closures provided by FIRST units, maintenance units, and contractors in the vicinity

  10. Statewide Incident Response • 6:20 p.m. – State Emergency Operations Center and Joint Information Center activated. • Unified command center set up on collapse site. Authority in command changed as incident progressed: • Mpls. Fire Department in charge of rescue • Hennepin County Sheriff in charge of recovery (Mn/DOT assisted with some demolition) • Mn/DOT assumed command after recovery was completed

  11. Emergency Service Response • Mn/DOT Metro district provides maintenance staff and equipment • Mn/DOT structural engineers called to site • Effective response due to communications, planning, equipment, training, and experience with incidents on the Metro area freeway system

  12. Traffic Response • 6:20 p.m. - began converting temporary traffic control measures to more long term traffic control standards. • 20 changeable message signs activated • Mn/DOT assisted state patrol and other enforcement personnel • Instituted 24-hour staffed traffic control • By 7 p.m. – Over 150 employees activated • 11:00 p.m. - Detour maps for a.m. rush posted on Mn/DOT Web site • Overnight – closed I-35W with temporary barricades and converted Hwy 280 to a freeway.

  13. Public and Media Response • 6:10 to 8 p.m. continuous Mn/DOT traffic radio coverage • Detour maps and info provided on Web and 511 Traveler Information • Media briefings, interviews • Coordinated responses with other agencies/governor’s office http://www.511mn.org http://www.dot.state.mn.us/i35wbridge/index.html

  14. Security Response • Mn/DOT safety officers statewide called in • Homeland Security & FBI investigate criminal or terrorism potential • OSHA ensures safety • Navy divers assist recovery • U.S. Secret Service for president visit • No-fly zone activated

  15. Internal Agency Response • Employees knew what to do, when to go, who to report to • Aug. 2 – Lt. Gov. e-mail to employees • Aug. 2 – State employee assistance available • Aug. 6 – Lt. Gov./Deputy thank employees • Aug. 8 – Tips to employees on handling threats • Critical incident stress debriefings provided

  16. The Response Local and National

  17. Governor’s Response • Aug. 2 - Governor Tim Pawlenty declares a state of emergency and activates State Emergency Operations Center

  18. U.S. DOT Response • Aug. 2 – U.S. DOT Secretary tours site and announces $5 million grant to help pay for early expenses

  19. Executive Branch Response • Aug. 3 - First Lady Laura Bush visits the site, victims families • Aug. 4 - President Bush pledges to cut red tape that could delay recovery • Aug. 21 - President declares emergency under Robert T. Stafford Act authorizing funds for safety and recovery efforts President Bush participates in a briefing with Minneapolis Mayor R.T. Rybak and Gov. Tim Pawlenty

  20. Congressional Response • Congress authorizes $250 million in Emergency Relief money to repair and restore highway facilities to pre-disaster conditions

  21. Mn/DOT’s Continuing Response • Investigation • Inspections • Traffic Recovery • Bridge Demolition • Bridge Replacement • Media/Public Responses

  22. Continuing Response Investigation

  23. The Search for a Cause • Cause may not be known for 12-14 months

  24. The Search for a Cause • National Transportation Safety Board leads investigation • Forensic engineering firm assisting investigation • Consultant to review inspection procedures

  25. Continuing Response Inspection

  26. Inspection • Aug. 2 - Governor directs Mn/DOT to inspect all bridges on the trunk highway system in priority order • Aug. 6 – Mn/DOT completes inspection of five bridges with the same arch deck truss design as I-35W bridge • Inspection continues of state bridges, structurally deficient and fracture critical bridges priority • Aug. 10 – Mn/DOT requests that local agencies and private owners accelerate inspections of their bridges • Dec. 1 - Mn/DOT’s goal to complete all state bridges inspections

  27. Inspection • Approximately 13,600 > 20 ft. long bridges in Minnesota - 3,800 TH, 9,800 local • 197 fracture critical bridges in Minnesota – 72 TH and 125 local • 34 pin assembly bridges - 15 TH and 19 Local • 1,111 structurally deficient bridges – 106 TH and 1,005 local

  28. Continuing Response Traffic Recovery

  29. Traffic Restoration • Work to convert Hwy 280 to a freeway including closing at-grade signalized intersections to cross traffic, upgrading ramp termini signal systems and lengthening frontage road • Add lane each direction on I-94 from Hwy 280 to I-35W by overlaying and restriping shoulders • Many temporary projects on other Metro alternate routes

  30. Traffic Distribution After Collapse

  31. Transit • Metro Transit assigned 25 extra buses, ridership jumps 25-50% • Advised public to “buy bus passes, stagger work hours, carpool” • Began studying additional service enhancements Park-and-Ride use jumps after I-35W bridge collapse

  32. Continuing Response Bridge Demolition

  33. Bridge Demolition and Removal • Aug. 6 – demolition begins to aid recovery, Carl Bolander & Sons Co., awarded demolition contract • Aug. 20 – recovery completed, site turned over to Mn/DOT • Sept. 6 - Navigation channel opened to commercial traffic

  34. Bridge Demolition and Removal • As of Sept. 26: • Steel removed from river • Corps will sweep channel • Restrictions still on recreational river traffic • Some demolition will continue after Oct. 15 • NTSB on site through end of year

  35. Continuing Response Bridge Rebuild

  36. Bridge Rebuild • 189’ wide • 10 lanes of traffic, five in each direction • Designed to handle Bus Rapid Transit (BRT) and/or a managed lane (like I-394 MnPASS) • Designed to be LRT ready

  37. Bridge Rebuild – Design Build • Aug. 4 – Design Build teams pre-qualified • Aug. 14 – public involvement process begins • Aug. 21 – layout submitted to Minneapolis • Aug. 23 - RFP delivered to five design-build teams • Aug. 23 – all but 3 environmental permits acquired • Sept. 19 – project bid letting • Oct. 15 - work scheduled to begin • Dec. 2008 – projected bridge completion date

  38. Bridge Rebuild - Review Process • Minneapolis Municipal Consent hearing Sept. 20 • Technical Review Committee reviewed proposed design • Visual Quality Advisory Committee met with Design-Build teams

  39. Bridge Rebuild-Stakeholder Involvement • Six open houses • Community group Meetings • Presentations/listening sessions • Meetings with local, state, federal officials • E-mail alerts/ notifications • Web site, online comment form • Handouts at park-and-ride lots

  40. Responding to What We Heard • Build bridge to accommodate future LRT • Build a quality, attractive bridge we can be proud of • Mitigate construction impacts • Maintain key road and bike accesses • Require DBE involvement • Keep us involved!

  41. Bridge Rebuild-Environmental Review • Environmental reviews accelerated due to cooperation among agencies • Includes a thorough analysis of the full range of potential environmental issues for all aspects of the project • Met NEPA requirements

  42. Bridge Rebuild Legislative/Congressional Hearings • Aug. 15 – Hearings with Minnesota House and Senate Transportation Committee • Sept. 5 – Mn/DOT staff testified before the U.S. House of Representatives Committee on Transportation & Infrastructure

  43. Bridge Rebuild - Economic Impacts • Economic factors create urgency to rebuild quickly • Daily costs to motorists of additional travel time and distance estimated at $400,000 • Reduction in state’s average net economic output is an additional $113,000 per day

  44. Continuing Response Media/Web info

  45. Media and Public Response • Media interest worldwide • Media briefings, interviews • Mn/DOT directed to be transparent in info provided • AG’s office required retention of all incident-related data • 50+ data practices requests • Dedicated I-35W Web site includes all documents

  46. Conclusions What Went Right? Lessons Learned?

More Related