1 / 15

CCC - AB/CO viewpoint

CCC - AB/CO viewpoint. P. Charrue on behalf of AB/CO/IN. Outline. Layout CCC and CCR Timetable from now till 1 Feb. 2006 Intercom Video and Fixed Display Fast Analog ConCluCion. Outline. Layout CCC and CCR Timetable from now till 1 Feb. 2006 Intercom Video and Fixed Display

pdaryl
Télécharger la présentation

CCC - AB/CO viewpoint

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CCC - AB/CO viewpoint P. Charrueon behalf of AB/CO/IN

  2. Outline • Layout CCC and CCR • Timetable from now till 1 Feb. 2006 • Intercom • Video and Fixed Display • Fast Analog • ConCluCion P. Charrue - AB/CO/IN

  3. Outline • Layout CCC and CCR • Timetable from now till 1 Feb. 2006 • Intercom • Video and Fixed Display • Fast Analog • ConCluCion P. Charrue - AB/CO/IN

  4. Typical CCC Working Place 16 LCD 46” Fixed Displays 240 TFT 19” 100 keyboardsand mices 20 Phones 100 PCs 40 chairs P. Charrue - AB/CO/IN

  5. Layout CCR ~90 racks for all electronics and computers • Access • Central Timing • CATV & Teletext • ASOS • RF • PC from PS • HPUX servers • HP ProLiants P. Charrue - AB/CO/IN

  6. 7 Nov 2005 1 Feb 2006 5 Dec 2005 19 Sept 2005 24 Oct 2005 AB/CO Timetable Preparation - Racks layout - cabling - 46” screens pre-cabling - Order of PCs and Screens CCR Ready - Start mounting racks - Electricity and network installation - Installation of electronics and computers CCC delivered to CERN - CCR is operational : Start operational services - Consoles installation - Install PCs and screens CCC functional tests CCC is operational P. Charrue - AB/CO/IN

  7. Outline • Layout CCC and CCR • Timetable from now till 1 Feb. 2006 • Intercom • Video and Fixed Display • Fast Analog • ConCluCion P. Charrue - AB/CO/IN

  8. Intercom • In the SPS corner, the exact copy of what was available in 2004 will be installed • In the PS corner, a COMMEND station interfaced to the ‘old’ PS intercom will be installed • COMMEND intercom for access is under IT/CS and TS/CSE responsibility • No intercom foreseen for LHC P. Charrue - AB/CO/IN

  9. Video and Fixed Displays • 3 CATV networks available going all around the CCC • PS, SPS and SITE • TUNER card(s) will be installed in the 2nd line consoles for display • MPEG digitized signals available • Support for digitization ‘à la source’ • One signal takes ~5 Mbit/s of bandwidth • Specific software (e.g. VLC) to display anywhere P. Charrue - AB/CO/IN

  10. Video and Fixed Displays • 16 Huge 46” Fixed Displays on the CCC walls • 4 home made BlackBoxes each one controlling 4 Fixed Displays • CATV input • MPEG input • Possible capture of any screen of any console to be displayed on the Fixed Display P. Charrue - AB/CO/IN

  11. 46” 46” 46” 46” Fixed Display Layout BlackBox Console CATV MPEG 100/1000 Mbit/s

  12. Fast Analog Signal • OASIS deployed to acquire the signals near the equipment, digitize them, transport them, and display them in the CCC Consoles • Support from CO for : • the OASIS Hardware (Crates, cards) • the OASIS visualisation software • LabVIEW support • Possibility to display scope images of analog signals arriving in the CCR, distributed and displayed via CATV (ASOS project) • No support for analog cables directly in the consoles. P. Charrue - AB/CO/IN

  13. Misc • AB/CO will provide 16 push buttons in each PS, SPS and LHC corners to allow operators to inhibit/request beams • Teletext support • The Alcatel IP-touch phones look great and can offer ‘nice’ programmable features. P. Charrue - AB/CO/IN

  14. Outline • Layout CCC and CCR • Timetable from now till 1 Feb. 2006 • Intercom • Video and Fixed Display • Fast Analog • ConCluCion P. Charrue - AB/CO/IN

  15. ConCluCion • A huge installation work is coming in the next 4 months till 1st February 2006 • We are confident that the CCR and the CCC will be installed and available for operation for the 1st February 2006 • Still different solutions for PS and SPS (intercom, digital and analog signals, access, …) • But now that we will all work in the same place homogenization must be possible P. Charrue - AB/CO/IN

More Related