1 / 23

NSLS-II Accelerator Installation Plan

NSLS-II Accelerator Installation Plan. Gregory Fries Project Engineer, Accelerator Systems Division CFAC Review of NSLS-II October 5-6, 2010. Outline. Phasing of Installation Coordination with Conventional Facilities Storage Ring Installation Injector Installation Storage and Rigging

pilis
Télécharger la présentation

NSLS-II Accelerator Installation Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NSLS-II Accelerator Installation Plan Gregory Fries Project Engineer, Accelerator Systems Division CFAC Review of NSLS-II October 5-6, 2010

  2. Outline • Phasing of Installation • Coordination with Conventional Facilities • Storage Ring Installation • Injector Installation • Storage and Rigging • Installation Schedule • Experimental Installation • Potential Obstacles • Summary

  3. Phasing of Construction and Installation Beneficial Occupancy Installation

  4. Installation and Operation Zones 1 • Key Points: • Utilities and infrastructure are segmented as shown • BOD handovers aligned with support infrastructure • Installation and testing within these segments • Linac/Booster test/commission may overlap with construction activities B RF RF 2 5 L 4 3

  5. Coordination with Conventional Facilities • Lay-down area for storage containers outside of building • Beneficial occupancy conditions for installation • Systematic hand-off of completed building zones • BNL BORE process to be used for occupancy permits • Access to space with beneficial occupancy for installation while construction continues • Interaction of installation activity with LOB construction to avoid potential interference • CFD represented in ASD installation meetings (O. Dyling) • ASD reviewing all CFD ECNs for impact • ASD installation coordinator named

  6. Key Aspects of Production and Installation Accelerator Production – • We procure injector sub-systems (Linac, Booster Ring) • We build (integrate) Transfer Lines, B-RF and SR components Accelerator Installation – • Storage Ring BNL • Storage Ring RF BNL • Booster RF BNL • Transport Lines BNL • Linac Vendor w/ BNL oversight • Booster Ring Vendor using BNL technicians for all hands–on work w/ BNL oversight

  7. Storage Ring Systems Installation Per Pentant • Mechanical Utilities • Electrical Utilities • Magnet/Girder Assemblies • RF Systems • Vacuum System • Power Supplies • Beam Instrumentation • Beam Line FEs, DWs, IDs (where applicable) • Injection Straight

  8. Storage Ring Pentant 1 Installation: Week 2 22 23 24 25 26 27 Mezzanine Exp’l floor 23 25 26 27 28 24 Tunnel • Activities: • Prepare tunnel • Stage components on floor • Start cable tray on mezzanine Status: ~ 1/3 of material in building Installation starting Service Building

  9. Storage Ring Pentant 1 Installation: Week 6 22 23 24 25 26 27 Mezzanine Exp’l floor 23 25 26 27 28 24 Tunnel • Activities: • Tray and manifolds in place in tunnel • Racks well underway • Stage cable and start pulling Status: Most material in building Installation on mezzanine Installation in tunnel Service Building

  10. Storage Ring Pentant 1 Installation: Week 12 22 23 24 25 26 27 Mezzanine Exp’l floor 23 25 26 27 28 24 Tunnel • Activities: • Girder installation • Populating racks • Terminating cables Status: Most wiring pulled Process utilities connected Service Building

  11. Storage Ring Pentant 1 Installation: Week 18 22 23 24 25 26 27 Mezzanine Exp’l floor 23 25 26 27 28 24 Tunnel • Activities: • Girder installation • Cable pulls all done • Testing underway Status: About 2/3 vacuum complete Service Building

  12. Injector Installation Phases • Mechanical & Electrical Utilities • Booster RF • LtB Transport Line Part 1 • Through wall, up to vac valve in booster vault, needed to commission linac • Linac • Booster • LtB Transport Line Part 2 • TL complete, need to commission booster • BtS Transport line Part 1 • Up to beam dump, needed to commission booster

  13. Injector Installation Phases Layout Phase Separation (end of injector install) BtS TL Part 1 Booster RF Booster Linac LtB TL Part 2 Phase Separation LtB TL Part 1

  14. Component Storage & Staging • Reviewing storage requirements for each ASD group • Finalizing number of sea containers needed at site for storage • Approx. 10-15 - 8 ft x 8 ft x 40 ft containers • Experimental floor will be used for staging • Temporary cages may be installed

  15. Lay-down Areas for Sea Containers Lay-down Area for SR Component Storage Containers Outside Access to Experimental Floor for Unloading Lay-down Area for Linac & Booster Containers

  16. Rigging Requirements

  17. Rigging Summary & Status • Reviewed requirements with the riggers • Will have two dedicated 3-man rigging teams • ASD installation coordinator will be contact to riggers • Rigging requirements will continue to be detailed

  18. Component Transport • Forklift has been ordered • 10,000 lbs. capacity • 208” max lift to reach mezzanine from experimental floor • Dolly system will be used for magnet/girder assembly transport

  19. Installation, Testing & Commissioning Schedule

  20. Installation Schedule • Installation schedule currently being reviewed with each CAM and expanded for completeness, durations and logic • Emphasis will be placed on installation schedule flexibility based on building and component availability

  21. Experimental Installation • XFD Installation follows ASD installation by pentant • Activities Per Beamline • Pentant Hand-off from ASD • Pentant Clean-up • Hutches • Utilities • Beamline Components

  22. Potential Obstacles • Coordinating multiple activities/teams/access during installation • Maintaining component delivery schedules • Will epoxy floor installation on experimental floor impact ASD installation schedule? • XFD installation needs might conflict with required flexibility of ASD installation schedule (hand-over delays)

  23. Summary • Installation schedule in process of being expanded and re-evaluated • Focus on flexibility in installation schedule based on availability of building and components • Building to be available for start of ASD installation Feb ‘11 • Detailing installation logistics • Rigging and storage requirements in process • Good communication established with CFD & XFD • Conclusion: Installation Planning is very advanced

More Related