EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE. Schedule. Guillaume Prévôt APC, Paris. Introduction Procurement status Main milestones. Introduction. The schedule (EUSO-SCH-INST-005-APC_V1.0) has been made from mid 2012 to March 2014 with : 3 weeks of margins

pravat
Télécharger la présentation

Introduction Procurement status Main milestones

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Schedule Guillaume Prévôt APC, Paris • Introduction • Procurement status • Main milestones

  2. Introduction • The schedule(EUSO-SCH-INST-005-APC_V1.0)has been made frommid 2012 to March 2014 with: • 3 weeks of margins • 7 weeks of holydays / year. Schedule

  3. Procurement status • - Lenses:willbemanufactuedfromDecember the 10th.The 3 lenseswillbefinishedJune, the 10th. • Deliveryat IRAP of the 3 lensesaftermeasurements in US: July, the 27th • - Mechanical structure: will be received by IRAP June, the 10th. • - EEE: every electronics components are supplied or foreseen to be. No long-span delivery identified. • PDM: • -EC_ASIC board: EC_ASIC board FM will be produced April, the 2ndby LAL. • -HVPS boards: HVPS boards FM will be delivered April, the 2nd at APC. • PDM board: PDM board FM will be delivered March, the 12ndat APC. • DP: • -All the subsystems will be produced and tested April, the 2nd. Schedule

  4. Main milestones Main milestones: - CRE AIT EC Unit May, the 29th - CRE AIT PDM July, the 3rd - CRE AIT DP June, the 25th - CRE AIT PDM + DP communication September, the 13rd - CRE AIT Instrument (after a rehaearsal of a campaign), ready to fly November, the 19th - Delivery at Timins, Canada (after 30 days shipment) February, the 18th - Ready to fly March, the 6th Schedule