OPPD’s Wind Development in Nebraska

OPPD’s Wind Development in Nebraska. Nebraska Wind Energy Conference November 9, 2009 Christene Bywater, P.E. Project Manager. Sustainable Energy & Environmental Stewardship. Goal of 10% Renewables by 2020 About 400 MW Why? Helps to defer baseload generation

Télécharger la présentation

OPPD’s Wind Development in Nebraska

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. OPPD’s Wind Development in Nebraska Nebraska Wind Energy Conference November 9, 2009 Christene Bywater, P.E.Project Manager

  2. Sustainable Energy & Environmental Stewardship • Goal of 10% Renewables by 2020 • About 400 MW • Why? • Helps to defer baseload generation • Helps minimize the risk of a RES • Will help minimize carbon tax costs to OPPD

  3. OPPD Wind Projects • Valley Turbine – 660kw • 10 MW from Ainsworth Wind Farm • 25 MW from Elkhorn Ridge Wind Farm • Possible new site on Interstate 80 west of Omaha

  4. OPPD Wind Projects • 80 MW RFP • Released in Aug 2008 • Received bids in Oct 2008 • 12 Proposals • Anticipated Award on April 1, 2009 • April 1, 2009 also Transition Date from MAPP to SPP • Actual Award August 14, 2009

  5. SPP Transition • Approvals Needed • Interconnection • Delivery • MAPP – 6 months • SPP – 2 years

  6. Flat Water Wind Farm • 60 MW Flat Water Wind Farm • JW Prairie Wind Power • Richardson County, NE • 42% Capacity Factor • 40 GE 1.5 MW Turbines • Construction of Substation started in October, 2009 • COD is anticipated June 30, 2010

  7. Substation Design • Site Grading Plan and Substation Ground Plan Designed by Both Parties

  8. Substation Design • All Metering by OPPD on Our Sub Site • 34.5 kV Underground Collector System • Breakers – Both Subs • 34.5/161 kV Transformer • 40/53/66 MVA

  9. Transmission Line Details • Line 138, Single Circuit 161 kV Transmission Line • From KS/NE border to NPPD Sub 975 in Humboldt, NE • Weathering Steel H-frame Structures • 2 New 70 ft. Substation Deadend Structures

  10. USFW & NGP • Precautionary Measures for Migratory Birds • Asking JW Prairie for Bird Diverters on Shieldwires • Negotiations are still underway

  11. Thank You