An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MTI Activities LHC LS1 – low beta magnets and interconnections BE/ABP-SU during LHC LS1 CERN, 07.11.2012 INDICO 213914

  2. Introduction interconnection alert systems

  3. Introduction low beta magnets monitoring and repositioning systems

  4. Responsabilities Andreas • Alignment systems (HLS, WPS, DOMS sensors): • Preventive and corrective maintenance + validation of alignment systems • Consolidation systems (filling/purging, wire displacement systems) • Standard measurements on triplets (tilts, levelling w.r.t. deep references) • RSSO of the section and TSO of UPS galeries and TT1 tunnel Mateusz • Installation and validation of load sensors • Preventive maintenance of motorized jacks and associated control/command system • Integration of new devices (sensors and motors) in the existing control system and preparation of visualizations for new consolidation systems Antonio • Interconnectionalert system • Acquisition system: • Displacement of racks from UJ56 to bypass • Replacement of SAS acquisition systems • Various electronics tasks: capacity measurements, control of temperature probes, connectors,…

  5. System andConfiguration low beta magnets monitoring systems • Monitoring systemsinstalled on all lowbetamagnetsand UPS • HydrostaticLevelling System • Wire Position System • Invar Radial System • Temperatureprobes • Monitoring systemsinstalled in ATLAS and CMS • HydrostaticLevelling System

  6. System validations low beta magnets monitoring systems • System validation (at least) threetimesduring LS1 • Atthebeginning (assoonasaccessispossible) • Atthelatestpossible (just beforeclosureofthesector) • After reinstallationofdismountedcomponents • Whendoubt on systemperformance • Modus operandi • HLS: fillingpurgingofthesystem • WPS: wiredisplacement • IRS: roddisplacement Concept · Procedures· Infrastructure · Analysis methods Scheduledfor LHC access access in ATLAS and CMS has tobetimed, especially YB0 REF

  7. Network measurements low beta magnets monitoring systems • Deepreferencemeasurements • Atthebeginningcombinedwith LSS measurements • Sensor measurementsneeded • Providemeasurementsandresultsto SU-EM • Inconsistency in somepoints • Confirmobservationtopreviousyears • Evaluatemethodstoidentifyfaultyvalue on site Concept · Analysis methods · Procedure Infrastructure Evaluation 2011 · identify fault values · in situ calibration

  8. System upgrade low beta magnets monitoring systems • Installsystemsthatallow remote check ofmonitoringsystems (ALARA) • automaticfilling / purgingof HLS • automaticdisplacementof WPS Concept · Procedures· Infrastructure · Analysis methods access in ATLAS and CMS hastobetimed, especially YB0 REF

  9. General maintenance low beta magnets monitoring systems • Knownissues • Mightrunshort on WPS wireascalibratedwithinstalled WPS • Need toorganizewastewater: RP check, treatment, wastemanagement • Havenocalibrationfacilityforirradiatedsensors • Bldg. 867 not readyforirradiatedsensors • Noofficialtemporarystorageofactivated material • Calibrationbenchesforirradiatedsensors not ready • Open «Red End Zone» doorsarekeytoefficientworkingconditions (IP1 and IP5) • Proposals • Install spare sensorcablesthroughboreholes • On site «light» calibrationmethods

  10. Externalimpact low beta magnets monitoring systems • UJ56 constructionwork • knowndates, sensorprotection in collaborationwith R2E • Cabling on triplet in 8R • Transport ofmagnets 2L / ALICE • hastobecheckedwhenandwhathas tobedismounted • Blast doors UPS54/56 • Configuration will not bechanged • keysrequestedtohave easy access • Cablingrequest UPS14/16 • Way through UPS triestobeavoided • Interconnections opened on triplets? • Total lossofthemonitoringsystems • ATLAS / CMS systeminstallations • Rightsideinstallations

  11. Internal impact low beta magnets monitoring systems • UJ56 relocation • R2E movingfrom UJ56 tothebypasstunnel in point5 • System not availableforsomeweeks • SAS exchange • Operation ofoneday per triplet • Triplet realignment • Systems havetobe online andvalidated • Mechanicalchangeof THN • concepttobeintegrated • at same time asmaintenancework • downtimeofsystem 2 weeks per triplet • Wiremeasurementsalongtriplet • Do someof MTI componentshavetobedismounted • Force sensorinstallation • Systems havetobe operational

  12. Summary low beta magnets monitoring systems • Readyforstandardoperations • Conceptclearforsystem upgrade, timingandcomponentavailabilitytobechecked • Externalissues, e.g. damageofequipment, hardtoestimate • On sitecalibrationsdepend on variationsseenduringchecks • All thishasnottakenintoaccount • New FSU hastobetrained • Estimatedworkload in theplanning 1.3 yearsfortunnelworknot including «externalimpact» • Analysis in officehastobedone, not takenintoaccount in planning

  13. Loadsensors low beta magnets repositioning systems • Installation for IP: 1,2,5,8 L&R • 80 sensors + cables + acquisition electronics needed • Partially installed in 2012 (TS2, TS3 → P5; TS3, TS4 → P2) Load sensors solution proposed to monitor connection quality at vertical jacks

  14. Loadsensors· installationprocedure, resources & equipmentneeded low beta magnets repositioning systems • According to impact of diffrent cables lengths impedance effect for measured signal value → IN-SITU calibration needed • A special, mobile test-bench was designed to perform laboratory tests and tunnel calibration • Procedure of sensor instalation inside the triplet’s JACK discussed and approved at LMC meeting 14.09.2011 (description in EDMS 1173532) • 2 persons for preliminary tests and tunnel installation needed (~50% of FTE during LS1 period; M.Sosin + J.Sandomierski)

  15. Loadsensors· preparationstatus & installationschedule low beta magnets repositioning systems • The 90 load sensors received from suppier (HBM, begin of 2012) • 12 WordFIP - Load Sensor Acquisition System (LSAS) crates assembled; 4 crates installed in P5, P2 • Cables for P1, P2, P5 installed; P8 cabling will be performed by EN-EL during LS1 (waiting for final schedule, Jean-Claude Guillaume et.al.) • Software integration with existing control system (FESA/PVSS) was performed by EN-ICE (E.Blanco et.al.) • 50 sensors tested; 23 installed in P5, P2; 40 sensors waiting for preliminary tests • PVSS synoptics integration for P1, P8 needed P5 L + 30% of P2 L 2012-TS3 P1 LS1: 2013.04..06 P5 R 2012-TS2 Finalize P2 L&R ? 2012-TS4 Finalize P2? LS1: 2013.04 P8 - sensors LS1: ? P8 cabling by EN-EL LS1: ?

  16. Upgrade · integrationofnewdeviceswithexistingcontrolsystem low beta magnets monitoring systems • According to radiation level increase in the triplets area – the new devices to provide remote sensors diagnostic & maintenance needed: - HLS filling/purging station - WPS wire displacement device - WPS wire break tester • Integration with SURVEY PVSS/FESA control system needed → requested to EN-ICE (technical spec.under prep.) • Design and tests of dedicated controlers pending (A.Marin, M.Sosin) • Resources for integration (M.Sosin, ~10% of FTE during LS1 period) • Schedule → first full system tests at mid of LS1

  17. Laboélectronique Activités pendant LS1 • Queues De Cochons : • Evaluation position • Démontage et sécurisation avec équipes • Remontage et recentrage • Systèmes d’acquisition: • Déplacement du rack de l’UJ56 au bypass • Installation des patches panels • Contrôle du nouveau câblage. • Inspection électroniques déportées • Remplacement des châssis SAS • Réception, calibration • Divers électronique terrain: • mesures capacité, • contrôles calibration sondes de température.

  18. Comment Laboélectronique • Configuration SAS : EDMS 1250773 • Queues De Cochons : EDMS 1177988 , 791107 et 969917

  19. Matériel Laboélectronique

  20. Quand Laboélectronique • Queues De Cochons : • Dès ouverture pour le relevé de la position du fil. • Démontage à la suite. • Remontage à définir • Systèmes d’acquisition: • Déplacement du rack de l’UJ56 au bypass  A préciser • Installation des patches panels • Contrôle du nouveau câblage. • Inspection électroniques déportées  A coordonner avec Andreas H. • Remplacement des châssis SAS • Nouveaux châssis à tester et préparer • Installation: 2ème semestre 2013. • Divers électronique terrain: A coordonner avec Andreas H. • Mesures capacité, • Contrôles calibration sondes de température.

  21. Par qui Laboélectronique Acquisition de données SAS Queues de Cochons Equipes de terrains Tonio et Michael Udzik Toutes les autres tâches

  22. Status Laboélectronique • SAS : Proto à tester début décembre série estimée mi-février 2012 • Queues de cochons : Bagues de sertissage à faire • Remplissage/Vidange et déplacement fil à distance : Attendons mécanique et électronique/software à assembler avec Mateusz et Michel • Reste des tâches : R.A.S

  23. Summary Laboélectronique

  24. Conclusion • Still a lot of work of preparation, assembly, reception and validation concerning filling/purging and wire displacement systems, as well as acquisition systems (SAS). • «Work preparation» room to be found • Two new persons to be trained • LS1: Work load of 100 % for Andreas and Antonio, 50% for Mateusz. But this is not the only activity of MTI unit. • External issues, e.g. damage of equipment hard to estimate • Budget concerning one FSU + filling/purging and wire displacement systems still pending.