An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Portable Broadband Seismology Part 8: Best Field Practices Jakarta, Indonesia May 11-13, 2006 Bruce Beaudoin Marcos Alvarez

  2. Pre-deployment Equipment QA • QA all of your equipment in a controlled, lab environment prior to deployment. • Test your recording parameters in the lab. • Know your equipment: • Be familiar with your installation plan. • Practice setting up a station in the lab and in a simulated field environment.

  3. Prepare • Develop deployment and servicing sheets. • Know the metadata you will require before you are in the field. • A well stocked tool box is a must. • Think spares, especially small items that can be misplaced. • Identify and collect the construction materials you will need for your seismic station.

  4. Site Selection • Far from human-generated noise (roads and machinery) • In a temperature-stable environment • Far from the ocean • On solid (competent) rock • Sky view • Good Drainage • Secure

  5. Vault & Site Construction • Provide sensor coupling to Earth • Protect the instruments: • Flooding • Temperature fluctuations • Animals • Secure

  6. Field Practices • Take comprehensive field notes. • If it is not documented, it didn’t happen • Take your time. • Make sure you will record useful data. The “Fort Five” • Do you have power? • Does the seismometer produce signal? • Is your instrument programmed correctly? • Do you have timing? • Is your data being telemetered or stored on-site?

  7. Monitor Your Site & Data • Monitor your sensor outputs before you close the vault and/or leave the site. • Do a service run within 2 weeks of the initial deployment. • Monitor your state-of-health channels. • Look at waveforms.