1 / 33

Update on FCPS Construction/Renovation Projects

Update on FCPS Construction/Renovation Projects. September 2009. Cassidy Elementary – Renovation. Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date: August, 2010 GC Contract Sum: $9,061,000 Total Project Cost: $11,067,360

ray
Télécharger la présentation

Update on FCPS Construction/Renovation Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on FCPS Construction/Renovation Projects September 2009

  2. Cassidy Elementary – Renovation • Architect: Tate.Hill.Jacobs: Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • GC Contract Sum: $9,061,000 • Total Project Cost: $11,067,360 • Change Orders to Date (1): $3,152 • Current Phase: 1 (On Schedule) • Estimated Completion: 34%

  3. Cassidy Elementary – Renovation Rendering of Final Façade

  4. Cassidy Elementary – Renovation • Work Completed in Last 30 Days: • Concrete seating walls complete at playground and mulch in place. • Storm sewers at rear of building complete. • Morton parking lot extension complete. • Second floor joist and slab structure complete at new additions. • Masonry load bearing walls complete on Admin Addition. Brick Veneer complete on rear addition. • Mechanical and electrical work rough-ins continue in new additions.

  5. Cassidy Elementary – Renovation • Current Work Effort (September): • Storm sewer and underground detention system to complete. • Stage floor to be poured and masonry load bearing walls installed. • Roof joists and deck to be installed. Roofing finish to start before end of month. • Interior metal framing to begin in enclosed areas. • Elevator installation to be complete by end of month. • Sprinkler rough-ins to begin. • Rooftop mechanical units to be installed. • Electric transformer to be installed.

  6. Cassidy Elementary – Renovation New Admin. Addition New Classroom Wing Corridor 2nd Fl New Media Center from 2nd Fl. New Stage Addition

  7. Russell Cave Elementary – Renovation • Architect: Pearson & Peters Architects • General Contractor: Congleton-Hacker Construction • Substantial Completion Date: August, 2010 • GC Contract Sum: $5,001,150 • Total Project Cost: $6,103,400 • Change Orders to Date (2): $11,180 • Current Phase: 1 (On Schedule) • Estimated Completion: 42%

  8. Russell Cave Elementary – Renovation Rendering of Final Façade

  9. Russell Cave Elementary – Renovation • Work Completed in Last 30 Days: • Roof at new addition is complete and the addition is dried in. • Renovation of (4) classrooms on the south side continues, demolition is complete, new mechanical and electrical rough-in is in process. • Stone veneer on addition base is in process. • New windows have been installed at (4) classroom renovation. • Current Work Effort (September): • Interior ramp and stair in new addition will be poured. • New horizontal blinds will be installed in cafeteria. • Framing for knee walls at new windows and soffits in renovated classrooms will be installed. • Block filler and painting will begin. New floor material will be delivered the first week of September • Demolition of the general construction items will begin in the gymnasium.

  10. Russell Cave Elementary – Renovation New Classroom Windows New Media Center Interior of Cafeteria New Kitchen

  11. Arlington Elementary – Renovation • Architect: RossTarrant Architects • General Contractor: WS Construction • Substantial Completion Date: August, 2010 • GC Contract Sum: $9,920,194 • Total Project Cost: $12,450,800 • Change Orders: $36,900 (#1--Demo) • Current Phase: 1 (On Schedule) • Estimated Completion: 17%

  12. Arlington Elementary – Renovation Rendering of Final Façade

  13. Arlington Elementary – Renovation • Work Completed in Last 30 Days: • Mock up of exterior wall materials has been completed. • Water detention system is in place. • Joists have been set in the gymnasium and the slab is scheduled to be poured on 9/16. • CMU walls continue in the kitchen. • Current Work Effort (September): • Demolition is almost complete. • The shoring of the existing structure is in place and reconstruction of the bearing wall between existing and new construction has begun. • Mechanical, electrical and plumbing work continues on site and in the existing building. • Foundations continue at the main entry and in the media center.

  14. Arlington Elementary – Renovation Water Detention System New Walls for Kitchen Bearing Wall Between Old & New Construction Mechanical, Electrical Plumbing Work

  15. Bryan Station Middle – Renovation • Architect: Clotfelter-Samokar Architects • General Contractor: Preston Construction Group • Substantial Completion Date: August, 2010 • GC Contract Sum: $10,769,400 • Total Project Cost: $13,345,600 • Change Orders to Date (1): $9,118 • Current Phase: 1A (On Schedule) • Estimated Completion: 39%

  16. Bryan Station Middle – Renovation Rendering of Final Façade

  17. Bryan Station Middle – Renovation • Work Completed in Last 30 Days: • Renovated Cafeteria now being used. • Media Center Renovation nearing “finishes” stage. • Science Room renovation work in progress. • New Music Suite Addition progressing well. • Current Work Effort (September): • Science and Computer room renovation to progress rapidly to meet November 1 scheduled substantial completion date. This also includes kitchen and Media Center. • New addition to progress to the point where roof joist can begin installation. • HVAC preparations to be made for switchover in phasing. • Site-work to develop so that bus lane can be reinstalled.

  18. Bryan Station Middle – Renovation Renovated Cafeteria Media Center Science Room Renovation New Music Suite Addition

  19. Leestown Middle – Renovation • Architect: Lucas/Schwering Architects • General Contractor: D.W. Wilburn, Inc. • Substantial Completion Date: August, 2010 • GC Contract Sum: $11,182,000 • Total Project Cost: $13,682,854 • Change Orders to Date (1): $2,874 • Current Phase: 1, 1a, 1b (On Schedule) • Estimated Completion: 24%

  20. Leestown Middle – Renovation Rendering of Final Façade

  21. Leestown Middle – Renovation • Work Completed in Last 30 Days: • Phase 1 A, B & C demolition efforts on-going. • Phase 1B Asbestos abatement on-going. • Phase 1 A, B & C hollow metal door frames. • Phase 1 A & B interior masonry wall erection on-going. • Phase 1 A & B interior masonry in-fill & patch work started. • Phase 1 A, B & C Erection of Structural steel started. • Phase 1 A, B & C setting of bar joists started. • Court yard seating walls and concrete paving are on-going. • Foundations for the courtyard addition are on-going. • Metal stud walls in Administration Suite are complete. • Cafeteria soffits are on-going. • Above ceiling ductwork has started in the Cafeteria.

  22. Leestown Middle – Renovation • Current Work Effort (September): • General demolition in Phases 1A, B & C will continue. • Plumbing, HVAC, electrical demolition on-going. • Structural steel and bar joists will continue to be erected • Metal roof decking to start. • Electrical and Plumbing rough-ins on-going. • Masonry load bearing masonry at Kitchen to be completed. • Phase 1C (Courtyard addition) foundation to be completed. • Phase 1C slab to start. • Erection of two story Fire Wall to begin. • Installation of hollow metal door frames on-going in Phase 1B & C. • Phase 1A & B, Work at existing built-up roofs to start. • Installation of new built-up roof at Phase C.

  23. Leestown Middle – Renovation New Addition at Kitchen Steel Erection at Courtyard Addition New Addition Kitchen Serving Line Seating Wall at Courtyard

  24. Lafayette High Stadium – Replacement • Architect: Strand & Associates • General Contractor: Judy Construction Co. • Substantial Completion Date: Fall 2010 • GC Contract Sum: $4,333,000 • Total Project Cost: $4,899,578 • Change Orders to Date: $0 • Current Phase: Phase 1

  25. Lafayette High Stadium – Replacement Existing Campus

  26. Lafayette High Stadium – Replacement Existing Football Stadium

  27. Lafayette High Stadium – Replacement New Football Stadium

  28. Central Bus Garage – Adaptive Reuse • Architect: Lucas/Schwering Architects • General Contractor: James R. Leake & Sons, Inc. • Substantial Completion Date: August, 2009 • GC Contract Sum: $2,782,000 • Total Project Cost: $5,672,810 • Change Orders to Date (3): $31,275 • Current Phase: Construction • Estimated Completion: 72%

  29. Central Bus Garage – Adaptive Reuse Façade

  30. Central Bus Garage – Adaptive Reuse • Work Completed in Last 30 Days: • All new shop equipment has been delivered with lifts, hose reels, exhaust system and work tables installed. • Paving for car parking has been completed. Striping is complete. • Installation of plant material and sod is proceeding. • Exterior overhead sectional doors have been installed • All masonry is complete • 90% of overhead electric complete • Painting is proceeding. • Installation of floor tile and carpet in the administration area is proceeding. • Ceramic wall tile is proceeding in the toilet areas. • Mechanical work is proceeding. • Installation of electrical devices is proceeding.

  31. Central Bus Garage – Adaptive Reuse • Current Work Effort (September): • Complete installation of all plant material. • Complete administration area and prepare punch list September 23rd. • Owner to start floor waxing floors and move in at the administration area September 25th. • Parking lot light poles to be installed. • Installation of interior doors and hardware proceeding • Continue work on the shop area.

  32. Central Bus Garage – Adaptive Reuse Service Equipment and Lifts at Shop area Administration Area Ceramic Wall Tile at Toilet Rooms Plant Material at Car Parking Lot

  33. Tonight’s Agenda Items

More Related