An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HBD upgrade status. Sasha Milov Jan 11, 2006 Sasha Milov DC meeting Jan 11, 2006

  2. Progress: • Mechanical assembly • Mechanical parts are being produced • PCB design finalized, Itzhak is at CERN negotiating production time. A backup option considered. • Photocathode production and measurement • SUNYSB to start weekly cycles of evaporating and measurements • Testing • GEM testing box is in work, needs to be equipped with LEMOs • BNL makes preparations to measure CF4 scintillation • LEGS beam test is not happening soon (as planned) • Electronics and monitoring status • ADC unit works yet without real input and looks good (see a backup slide) • Takao shown framework to monitor HBD performance Sasha Milov DC meeting Jan 11, 2006

  3. Mechanical parts and PCB. PCB final design. Quick MC shows no difference with standard cells Entrance window frames are ready, the window itself to be tight between them Sasha Milov DC meeting Jan 11, 2006

  4. Gas monitoring system. Input and two outputs measured by switching gas Input and two outputs measured by moving mirror. More expensive but clearly better Sasha Milov DC meeting Jan 11, 2006

  5. SUNYSB starts evaporation cycles. • Status: • Evaporator – OK, as it was last time • Laminar table – OK. Filters replaces, ready to go. • Vacuum storage – almost OK, matter of days. • Frames to hold GEMs are manufactured. • Test box arrived needs connectors (~2 weeks) • Glove Box new is still in the bidding stage, INFN may get some improvement for to be used for gearing up • Gas system in assembly stage • Strategyis to start weekly cycles of going from start to end getting more and more operations in routine from cycle to cycle. • Use laminar table assembly • Pump to water drop, as seen last time • Evaporate and measure Q.E. in situ • Get chicklets to Bob A. for Q.E. control • Next cycle (reusing the same GEM for evaporation): • Improve in situ Q.E. control • add GEM triplet gain measurement Sasha Milov DC meeting Jan 11, 2006

  6. Back to prototype? 1R, Bertan (4100V), I~330mA 1R, LeCroy (2400V), I~194mA 2R, Bertan (4100V), I~165mA 2R, LeCroy (4100V), I~165mA • With “unexpected” return of Run6 we need to make sure the full scale prototype can go in and work to have something better. Bob checked that the LeCroy power supply can be used. It requires divider resistance to be doubled. No extra noise detected. Sasha Milov DC meeting Jan 11, 2006

  7. Important standing Issues. • PCB (Itzhak) • Gas Monitoring System (Craig) • Glove Box (SUNYSB) • Signal Cables (BNL + Chi independently) • Infrastructure preparation in the IR (Don+) Sasha Milov DC meeting Jan 11, 2006

  8. Summary: • Mechanical assembly is on its way. Pad plane design is finalized • SUNYSB is starting cycle to get up to a reliable routine operation. • First look at the ADC modules is encouraging. More to come when a preamp board prototype is attached to it • Glove Box is still waiting bids to come back. There are other items with long lead time and we are working on getting them out soon. • Prototype needs to be in a good shape no matter what. It can operate on LeCroy PS, which is available. However the gas tightness might limit gas purity one can achieve with it. • GEM testing box in in work. We might be able to measure GEM stacks in weeks from now. BNL will try to do a scintillation measurement. Sasha Milov DC meeting Jan 11, 2006

  9. BACKUPS Sasha Milov DC meeting Jan 11, 2006