1 / 44

Invitation to dialog Call for tenders for Horns Rev 3 and Kriegers Flak

Invitation to dialog Call for tenders for Horns Rev 3 and Kriegers Flak. Director Hanne Windemuller. Today. Introduction Presentation of Horns Rev 3 and Kriegers Flak Presentations and discussions on the 12 questions for dialog

rhett
Télécharger la présentation

Invitation to dialog Call for tenders for Horns Rev 3 and Kriegers Flak

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Invitation to dialog Call for tenders for Horns Rev 3 and Kriegers Flak Director Hanne Windemuller

  2. Today • Introduction • Presentation of Horns Rev 3 and Kriegers Flak • Presentations and discussionson the 12 questions for dialog • Summary of the result of the firstround of dialog concerningpre-investigations. Coffee break at 14.25

  3. New offshore projects Horns Rev 3: 400 MW Kriegers Flak: 600 MW Tender for 450 MW near shore wind farms Horns Rev 3 50 MW turbines for research and development Kriegers Flak

  4. Role of the Danish Energy Agency Responsible for the call for tenders Contracting authority Responsible authority for EIA offshore One-stop-shop for permits

  5. Role of Energinet.dk Finance, construct and operate platform and sea cable Bringing power from new OWF ashore and strengthen grid Secure that grid connection is available in due time Conduct pre-investigations and EIA for the offshore wind farms

  6. The tender proces Negotiated procedure withprequalification and dialog Focusoncompetition and dialog The dialog: Bilateral meetings May 27 – 30 Deadline for written contributions June 7

  7. Horns Rev C Platform Design 400 MW Transformer Platform Point of interface to the ConcessionOwner

  8. Horns Rev 3: Layout of the Grid-connection Platform, 3 pcs. 140 MVA transformers Blåbjerg, new 220 kV GIS Cable Station, Platform HRC Blåbjerg Offshore cables, 220 kV Location B: 34 km Onshore Cables, 220 kV HR2 rute: 58,0 km Shortrute: 47,0 km Overheadlines, 400 kV Total OHL length:29,3 km Endrup Revsing Holsted Onshorecables, 150 kV Rute:15 km

  9. Horns Rev 3: Platform location • Platform located 34 km from the Coastline • Water depths at platform positions: app. 18 meters • Platform to belocated at the perimeters of the area for the turbines.

  10. Kriegers Flak • Combined Grid Connection • Wind Farm and Interconnector • Cooperation with 50Hertz Transmission GmbH • CO-financed by the European Union • In operation from July 1st 2018 • Grid connection – two AC platforms • 400 kV AC connection in Ishøj

  11. Kriegers Flak 600 MW in the Baltic Sea Pre-investigation area devided in two: West 69 km2 East 110 km2 Central area reserved for gravel extraction Platform locations fixed: West 200 MW AC East 400 MW AC (+ 600 MW HVDC platform) Kriegers Flak Wind Turbine location allowed within West and East area.

  12. Conditions for prequalification • DEA will conduct a prequalification of potential tenderers • Requirements for financial and technical capacity • Only prequalified tenderer will be entitled to submit a tender • Requirements adapted to the company set-up of the individual applicants

  13. Requirements for financial capacity • Expected projectsum may amount to no more than 25 % of the tenderer’s business (or parent company) • Equity-ratio requirement of 20 % • Credit rating of BBB- with ”Standard & Poors”, ”Moody’s” or ”Poors” • Submit general financial information on earnings for the past 3 years, equity capital, equity ratio and EBIT margin (all in the consortium)

  14. Requirements for technical capacity • Documenting experience in: • project development and establishment of offshore wind farms or other large –scale offshore installations or • operation of large offshore wind farms above a specific size, e.g. 100 MW • Question:Any questions to the requirements under consideration for financial or technical capacity?

  15. Compliance with tender • Compliance penalty • Bank guarantee placed as collateral for the penalty • 400 mill. for Horns Rev 3 and 600 mill. for Kriegers Flak • Bank (first of declaration of intention and later of guarantee) needs ratings with “Standard & Poors” of A-, with Moody’s” of A3 and with “Fitch” of A-. • Guarantee released when spent 1 bn. in establishment of Horns Rev 3 or 1 ½ bn. on Kriegers Flak • Question: Will the intended model on compliance penalty influence interest in tendering the wind farms? Will this affect the price offered?

  16. Award criteria • Lowest price is the only award criterion • Open to include other criteria than price, if • the criteria are reasonable and relevant • contribute to increased competition • without additional costs for the tenderer • Question:What criteria other than price could be relevant ?

  17. Financial terms • The price supplement is the difference between the ”price pr. kWh bid” and the spot price for electricity • The supplement will be given for the first 20/30 TWh • No price supplement in hours with negative spot prices • Compensation for delayed grid connection and for limits on production. • Questions: • Is the supplement for 20/30 TWh the right level? • Other comments?

  18. Timetable for tendering procedureHorns Rev 3 2013 2014 2015 … 2020 September 2013 Contract notice 2 September 2014 Deadline for preliminary tenders From 1 January 2017 Guaranteed connection to the grid Early 2015 Concession contract and construction permit 1 December 2014 Deadline for binding tenders Early 2020 Full operation of offshore farm 29 November 2013 Deadline for prequalification

  19. Timetable for tenderingprocedureHorns Rev 3 2013 2014 2015 … 2020 Early 2015 Concession contract and construction permit September 2013 Contract notice 29 November 2013 Deadline for pre-qualification From 1 January 2017 Guaranteed connection to the grid 1 January 2020 Full operation of offshore farm 2 September 2014 Deadline for preliminary tenders 1 December 2014 Deadline for binding tenders • Questions: • Timing of prequalification? • Othercomments?

  20. Timetable for tendering proceduresKriegers Flak 2013 2014 2015 … 2020 From 1 July 2018 Guaranteed connection to the grid February 2014 Contract notice 29 April 2015 Deadline for preliminary tenders Early 2020 Full operation of offshore farm 29 April 2014 Prequalification 31 August 2015 Deadline for binding tenders September/October 2015 Concession contract and construction permit

  21. Timetable for tendering proceduresKriegers Flak 2013 2014 2015 … 2020 September/October 2015 Concession contract and construction permit From 1 July 2018 Guaranteed connection to the grid 1. January 2020 Full operation of offshore farm February 2014 Contract notice 29 April 2014 Prequalification 29 April 2015 Deadline for preliminary tenders 31 August 2015 Deadline for binding tenders • Questions: • Timing of prequalification? • Othercomments?

  22. Compliance with deadline for completing the wind farms The politicalenergy agreement: The twowind farms are in fullproduction from 1 January 2020. Questions: • How can DEA ensure a fair and sufficient incentive to complete the farms before 2020? • Will an economicincentive/sanctionaffect the interest in the tender? • Will the incentiveaffect the price offered?

  23. Capacity of the farms A required minimum of 395/595 MW and a maximum of 405/605 MW for Horns Rev 3 and Kriegers Flak respectively.

  24. Horns Rev 3 area is reduced

  25. Maximum area for construction Maximum area: 44 km2 per 200 MW is being considered. • Question: Would a smaller area than 44 km2 per 200 MW be acceptable and if so, how small could the area be?

  26. Concession for Kriegers Flak - one or two? Question: Should it be possible to split Kriegers Flak into two concessions? Kriegers Flak

  27. Horns Rev C Platform Design 400 MW Transformer Platform Point of interface to the ConcessionOwner

  28. Horns Rev 3: Platform location • Platform located 34 km from the Coastline • Water depths at platform positions: app. 18 meters • Platform to belocated at the perimeters of the area for the turbines.

  29. Horns Rev C Platform – Design decisions • HRC willbedesignedbased on the Anholt platform • 3 pcs. of 140 (200) MVA transformere to beinstalled at the Topside – point of interface to the ConcessionOwner • LV-supply (auxiliary power): 3 pcsaux.transformers and 2 pcs of dieselgenerators • MV earthing resistors to bedesigned and installed by ConcessionOwner

  30. Horns Rev Platform – Electrical diagram

  31. Horns Rev 3 - Timeline Kriegers Flak – MV specification same date as for Horns Rev 3 Kriegers Flak – MV switchgear delivery early 2017

  32. Technical Project Descriptionfor both sites arepublished– and wewouldlikeyourcomments! Pre-investigations and EIA for: Horns Rev 3, Project manager: BetinaHaugaard Heron, Energinet.dk Kriegers Flak, Project manager: Pernille Skyt, Energinet.dk In brief we will present the technical project description for Horns Rev 3 and Kriegers Flak – our main question to you is: • Will the current draft technical project description ensure the flexibility necessary to select technical solutions for projects on Horns Rev 3 and Kriegers Flak?

  33. Technical Projects Descriptions – the overall objectives The overall objectives of the published technical project descriptions are: • Provide description of the main technical parts: wind turbines, park layouts, foundations design, inter-array cables and installation methods. • Use this as the technical foundation for the environmental impact assessment • Provide a combination of a “most likely” and a “worst case” approach • Enable the EIA to secure as high degree of flexibility as possible in order to allow the concession winner to design and built the most optimal offshore wind farm.

  34. Horns Rev 3: Location of pre-investigationarea • App. 160 km2 • Has beenreducedsinceFebruary 2013 • The wind farm areawill cover an area of app. 80-90 km2 • Flexibility for coming developer

  35. Kriegers Flak: Location of pre-investigationarea • Overall area: 250 km2 • Water depths 15 - 30 mDistance to shore 15 km • Distance to harbour 20-40 km • Exclusion zone central in the area. Here two-three platforms and export cables to Denmark and Germany, will be established • 200MW turbines west of exclusion zone (pre-investigation area: 70 km2) • 400MW turbines east of exclusion zone • (pre-investigation area: 110 km2) •  Flexibility for coming developer

  36. Specifications for different turbines Smallest turbine for Horns Rev 3 and Kriegers Flak: 3.0 MW Largest turbine for Horne Rev 3 and Kriegers Flak: 8.0 MW Do you agree ?

  37. Different locations and layouts of turbines have been modelled 3.6 MW: NS: 640 m 3.6 MW: EW: 1.170 m 8.0 MW: NS: 1.050 m 8.0 MW: EW: 1.781 m Modelled by DTU Wind Energy, 2013

  38. Kriegers Flak – park layouts Parklayout - 3 MW turbines West: 67 turbines East: 133 turbines Parklayout - 8 MW turbines West: 25 turbines East: 50 turbines Modelled by DTU Wind Energy, 2013

  39. Turbine foundations Three main types are included: • Monopile • Gravitation • Jacket The different types of foundations have different impacts concerning e.g.: • Installation noise • Seabed preparation • Scour protection • ‘Footprint’ • Hydrodynamic impacts • Risk of ship collision All of this will be covered in the EIA

  40. Technical dialogue: Questions related to Geo Investigations (UXO, geophysical, geological, geotechnical issues) Note has been published summarizing the comments in anonymous form, including answers or responses to the input. In summary, the following suggestions have been included in the geotechnical survey program: • More CPTs at both sites • Pressure meter tests • Dynamic laboratory tests • Acoustic Corer will not be part of the program Expected publishing dates: July 2013: Geophysical survey results 31. December 2013: Geotechnical factual reports 28. February 2014: Updated 3D geological models

  41. Technical dialogue: Questions related to MetOcean Note has been published summarizing the comments in anonymous form, including answers or responses to the input. Additionally, methodology notes have been published. In summary: • No met-masts will be established at the two sites • The level for MetOcean studies at the two sites will be identical, with natural differences as existing data from the two areas varies. • Some developers hold more detailed knowledge on MetOcean data than others in the two areas. DEA and Energinet.dk will make efforts to equalize the advantage potential developers may have compared to others. • Estimations on productivity will not be part of the MetOcean studies. • Certification of the conducted MetOcean studies, or a verification of a third party is sought. • Notes describing the methodology for the MetOcean studies are published; please comment! • Metocean studies will be completed as planned, late 2013.

  42. Road map of the technical dialog 2013 • May 13: Kick-offconference. • May 27 – 30: Invitation to participate in bilateral meetings. • May 31: Deadline for writtencontributionsregarding Metocean. • June 7: Deadline for writtencontributions. • Go to www.ens.dk/offshorewind in order to read more about the tenders and to subscribe to the newsletter.

  43. Summary point • The Danish Energy Agency is open to hearing all relevant proposals and input to ensure that the tendering procedures reflect current market conditions. • These may be proposals for contract terms, etc. which may be able to reduce or increase the price, or enhance knowledge about market conditions of significance to the price in the tendering period.

More Related