1 / 24

SPECIALISED BLASTING By Mutale Chipoma- Explosives Engineer

SPECIALISED BLASTING By Mutale Chipoma- Explosives Engineer. Wealth Unearthed. BRIDGE ACROSS LUAPULA RIVER. BACKGROUND. AEL invited to conduct blasting under water across the Luapula river A total of 8 points under water for the construction of abutment pillars were blasted.

rob
Télécharger la présentation

SPECIALISED BLASTING By Mutale Chipoma- Explosives Engineer

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPECIALISED BLASTINGBy Mutale Chipoma- Explosives Engineer Wealth Unearthed

  2. BRIDGE ACROSS LUAPULA RIVER

  3. BACKGROUND • AEL invited to conduct blasting under water across the Luapula river • A total of 8 points under water for the construction of abutment pillars were blasted. • The areas to be blasted were surrounded by sheets of steel to keep the water from flowing through.

  4. BLAST DESIGN • The first area to be blasted was 16m x 16m. • Drilling was achieved by pneumatic drills with hole diameters of 45mm • A walk-way 1m wide was to be left around the blasted area to be used during construction • Holes drilled at 1m burden and spacing • Perimeter holes drilled at 0.5m around the blast area • Hole depth of 1.5m

  5. CHOICE OF EXPLOSIVES • The rock at the river bed was classified as medium to soft material and powder factor was selected on this basis • A technical powder factor of 0.39 kg/m3 was selected • A water-proof explosive was needed because blast holes were in water • Magnum bustergel 32 x 200 was selected

  6. CHOICE OF EXPLOSIVES CONT’ND • Uncharged collar of 0.5m was left in the main blast holes • Holes charged with five cartridges • Two cartridges tied to cordtex10 at a spacing of 0.8m centre to centre were charged in the perimeter holes. • For the perimeter holes, cordtex10 was used to connect the de-coupled charge only. Initiation was done using Smartdets

  7. CHOICE OF INITIATING SYSTEM • In order to reduce vibration , single-hole firing was required • Use of Smartdets was decided upon to achieve single-hole firing and to blast perimeter holes as pre-split together with the ‘production’ holes • Hand lashing using buckets was employed therefore fine fragmentation required

  8. CHALLENGES • Choosing a Powder factor to produce fine fragmentation without causing damage to steel works that kept water away • To reduce to minimum the blast induced vibrations so as to keep the steel works intact • Communication difficulties with customer during operations as only one was able to speak English.

  9. BLAST PATTERN

  10. DRILLED AREA READY FOR CHARGING

  11. CHARGING IN PROGRESS

  12. TIMING WITH SMARTDETS

  13. BLAST AREA CHARGED

  14. LAST PILLAR READY FOR CHARGING

  15. FRAGMENTATION

  16. FRAGMENTATION

  17. FIRST PILLAR CONSTRUCTED

  18. PILLAR CONSTRUCTED

  19. COMPLETED PILLARS ACROSS THE RIVER

  20. COMPLETED BRIDGE

  21. COMPLETED BRIDGE

  22. CUSTOMER SIGN - OFF

  23. WITH CUSTOMER

  24. Thank you Thank You

More Related