1 / 18

Trigger Upgrade

Trigger Upgrade. Valerie Halyo. Outline. Motivation for the upgrade Plans production and commissioning TSF status ZPD status Interface cards DCT software Detailed preliminary commissioning. Physics. z 0 of all tracks in L-1 events. Background. DCT Upgrade – Motivation.

rod
Télécharger la présentation

Trigger Upgrade

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Trigger Upgrade Valerie Halyo

  2. Outline • Motivation for the upgrade • Plans production and commissioning • TSF status • ZPD status • Interface cards • DCT software • Detailed preliminary commissioning

  3. Physics z0 of alltracksin L-1events Background DCT Upgrade – Motivation Goal: reduce the L1 trigger rate due to beam-related background by cutting on track z0

  4. General Goals • Jun/16 : Parallel commissioning of new DCT connected to one quadrant of the DCH. • Oct/03 : Full commission of the new DCT in parallel to current system including test of the new trigger • Dec/03 : Switch to the new DCT triggering BaBar

  5. Future configuration • Current DCT use only r-f information • New DCT expands this to 3-D • ZPD replaces PTD to add 3-D track fitting • TSF must ship fine-f info for stereo layers  New TSF • Interface cards (TSFi, ZPDi, GLTi) handle added signals BLTi BABARDriftChamber BLT Level-1Accept TSFi ZPDi GLTi TSF ZPD GLT

  6. New Hardware • Mini detector in the GltLab allows us full algorithm and calibration • tests. • New DctOnline code is added and being tested in the Lab and IR2 • Reconfiguration of the Glt during the shutdown

  7. Commissioning Readiness • Goal: Instrument one quadrant of the DCH • Needed for full pT acceptance Learn as much as we can from the beams in June Continue usefulsystem tests during the shutdown z

  8. TSF Status • One prototype assembled • with 3 FPGA • The input Formatter and FCT • chip are fully tested • Algorithm engine is being tested • DAQ was tested in the simulator • not on the board yet but • no conceptual problem anticipated. • Configuration loaded from flat • file was tested successfully • Few prototype boards are supposed • to arrive today. • Production during the shutdown

  9. ZPDi ZPD 153 segments MegaBus Receiver/Driver AlgorithmEngine 0 AlgorithmEngine 1 AlgorithmEngine 2 AlgorithmEngine 3 AlgorithmEngine 4 AlgorithmEngine 5 Fit Results DecisionModule 4 to GLT 8-bit decisions C-link FCCDecoder FPGAConfig Memory access, DAQ control, etc. D-link ZPD Status: • Design and Prototype • Testing • Algorithm test with • MC events: no bit errors • 2. DAQ firmware in • progress • Production: • 13 Production PCB’s were made • 2 loaded and tested • 1 at SLAC 1 in Harvard

  10. ZPDi GLT ZPD TSFi TSF TSFi GLTi TSFi TSF TSFi TSF TSF Interface Cards BLT BLTi TIOM DCC SlowMon TSFi : Arrive early next week. ZPDi: Will arrive during the run Glti: Is tested in teststand. (No for June) IFR EMT

  11. DAQ/Online Software L1DctCalOep L1DctCalOdf L1DctTeststand L1DctOep L1DctCalOnline L1DctOdf L1DctDiagOnline L1DctOnline

  12. Online • All Configurations of the new DCT will be loaded from XTC • or flat ascii files • Double the DCT data: • Every module TC is doubled having two different TC id’s • for production and parasite TC • 1. New ZPD TC and Fex exist and tested • 2. For the TSF Fex is in progress (L1Accept Action almost • ready) • 3. The additional TC’s are transparent to the current system • The new Online code will able to handle two TSF type in one • ROM

  13. New Setup DCH TSFY TSFX/Y DAQ BLT/PTD GLT BLT/ZPD TSFX Rack 23 Rack 24 Rack 25

  14. Operation schedule • June 16: • We are probably going to start by commissioning DCT • Corresponding to 1/8 of DCH namely 2TSFX + 1TSFY • We are going to run parallel but only the current system will trigger. • Occupy rack 25 in the EH with 2 crates in June • The rack is already powered and today the hit exchange • was installed • might have data taking with one ROM handling both TSFX,Y • This configuration enable a use of 3 instead of 4 ROMS • We are getting one DCH DAQ crate for hosting all the roms

  15. Operation schedule • Once TSF FEX is ready we will request an online build • and would like to request COSMIC run hopefully next week • Split all 24 DCH Glink (TIOM->TSFi) to supply DCH data • to old and new TSF • The patch panel to hold the splitters are almost ready • Part of the fiber splitter arrived today • DCT SlowMon for the fiber optical yield was installed but is being debugged with Ray’s slow mon teststand. • In the earliest opportunity we will move to the DCH-MON IOC • We are making full system test at the DCH-DCT teststand at the • GltLab in central Lab before coming to IR2 • (DCH-proto TSF old/new BLT ZPD MasterCrate)

  16. Shutdown Plan • TSF board will be in production • Continue studying and testing the boards and study the result • of this parallel run • Paul .D. has the conceptual design for the new EMT patch panel • which will be done by Paul S. • Su Dong is going to remove the extra 80ms from the BLT/GLT • and add about 8ms for the reading the data to prevent the • corruption of the fifth event coming • Many Thanks to all dataflow (Chris, Matt,Amadeo) • for their continuous help • Thanks to Ray R. Lupe S. Gibson L. Mark F. Jim H.

  17. Potential Issues • We are going to run parallel but the question is • How are we still affecting the main stream • Oep will ignore any damage from the new DCT • so that data logging wont be affected.(report the damage in Jas) • If the dead time cause by New DCT • increases our crate should be taken out of the crate mask • Reframing of the new TSF : • In event of any significant reframing rate (one per minute) • take out the New DCT • Automatic detection of the board will be in both boot and configure • code

  18. Inputs Up to 12 seeds • Each ZPD receivesdata from 9 TSFs • 3/8 in f • Seed segments inthe middle 1/8 ofSL7 and SL10 • 14 bits × 153 segments/CLK4 • Challenge 1: Moving around 8 Gbit/s • Backplane: 153 pins @ 60 MHz • Megabus: 75 LVDS pairs @ 120 MHz 1: mask4: cell location6: f in the cell3: error in f 144used

More Related