An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Florida’s Turnpike Enterprise ITS Project Update John R. Easterling, IV District Traffic Operations Engineer

  2. Florida’s Turnpike System TOLL 429/ WESTERN BELTWAY TOLL 417/ SEMINOLE EXPWY SUNCOAST PARKWAY TOLL 528/ BEACHLINE EXPWY VETERANS EXPRESSWAY FLORIDA’S TURNPIKE MAINLINE POLK PARKWAY TOLL 417/ SOUTHERN CONNECTOR EXT. HOMESTEAD EXTENSION OF FLORIDA’S TURNPIKE SAWGRASS EXPWY

  3. FTE Program Overview • Focus on Three Main FDOT Goals • Safety • Service • Mobility • Leveraging Partnerships With: • Public safety (FHP & Emergency Management Community) • Tow/recovery operators • Via other sponsorships

  4. TMC—ITS Program Overview • Pompano and Turkey Lake TMC Locations • 317 Fixed CCTV cameras (+200 more by Dec.) • 10 Highway advisory radio transmitters • 320-Mile fiber optic backbone • Staffed by 100% contract employees • Equipment procured through public-private partnership (T-Mobile) • Two centers back each other up • Co-location with FHP in Troop K’s Regional Dispatch Center

  5. ITS Project Updates • Fiber Deployments Began in 2002 • Phases 1-4 Now Complete • Sawgrass Expressway / SR 869 • First segment complete • Remainder in Sawgrass widenings – 2008 completion • Off-Mainline • Mid-2008 completions • Central Florida - Toll 417, 429 & Beachline/528 • West Florida - Veterans, Suncoast & Polk • South Florida CCTV & Northern Detection • South Florida Part A and Incident Detection projects with late 2008 completion dates

  6. Sawgrass Smart-Highway Project • Early Winners Project Part of the Turnpike’s Larger Smart-Highways Initiative • Deploys the Following on Sawgrass: • Arterial DMS prior to each interchange • AVI/Travel time system • Speed monitoring sites (passive) • RWIS stations • Design/Build Contract Underway • Summer ‘08 completion

  7. Southern Arterial DMS • Arterial DMS Added to 10 New Locations on Turnpike Mainline in South Florida • Design/Build Contract Underway • Early ‘09 Completion

  8. Transition to a Smarter Highway • Our Safety Mission To have the safest limited access facility in North America by reducing incidences, eliminating fatalities and reduce duration of incident impact by 2020. • Focus Areas • Using technology to improve customer safety • Roadway and infrastructure improvements • Optimizing system operations • Implementation of a dashboard

  9. Infrastructure Planned or Underway • Travel Time (SunPass) System • Speed Monitoring Systems • Road Weather Information Stations • Environmental Warning and Alert Systems • ITS Cable Detection System

  10. Visibility Monitoring/Alert System Task:Develop low cost systems to allow our TMC operators to quantify sight restrictions due to fog, smoke, heavy rain, or a combination of all the above / And additional ways to advise customers of these conditions

  11. Visibility Assessment Markers • Place markers at 300, 600, and 1000 feet from select cameras in fog prone areas as well as control burn areas which will allow operators to advise FHP and others of reduced visibility. • One set per 10 miles in rural sections

  12. Visibility Assessment Markers

  13. Visibility Assessment Markers

  14. C.B. Radio Alert System • Two Test Locations: • Turkey Lake Service Plaza at milepost 263 • Turnpike and I-95 at milepost 152 • System Uses Voice-over-IP (VoIP) Technology to Send Audio • System Uses “Off the Shelf” CB Radio • Connected From TMC to Test Locations Over Turnpike ITS Fiber Network • Broadcast Range of 5 to 15 Miles Depending on Conditions and Antenna Height

  15. C.B. Radio Alert System 18' antenna is mounted at the top of selected camera poles. The height from the ground to the top of the antenna is no more than 60'. A power supply, an “off the shelf” CB radio, and a radio controller are the components inside of the cabinet on the camera pole

  16. Questions? John R. Easterling, IV Florida’s Turnpike 954-934-1292 John.Easterling@dot.state.fl.us