An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LIU Wire scanners Ray Veness

  2. Why meet now? • Mechanics production is ‘basically finished’ • Installation dates are agreed for 2019 • Prototype control and acquisition installed and tested in PS • Preliminary results are good, looks like we will have the go-ahead to replace existing systems from all machines (ie, PS) • Next steps involve a broadening of interfaces and activities • Series production, assembly test and installation of electronics and acquisition hardware • Firmware specification, writing, and hand-over to software team • Software writing and hand-over to OP team for operational software • Commissioning in the different machines • Hand-over to operations • Issues: • Interfaces between the different teams and groups • Managing expectations of the OP team in the early days/weeks • Resource management with BI experts and succession planning

  3. How can we make sure this works? • Continue the ‘electro-mechanical’ meetings, which follow-up on the technical progress and issues • Expand them to include SW team (Loic, +??) • Invite OP?? • Do we need more ‘steering’ meetings like this one? • Is the resource allocation clear/sufficient? • How do we manage these hand-overs? • Firmware to software, software to operations, ‘expert’ to operations • Do we need one or more internal ‘reviews’ to make sure we are all agreed?

  4. Main Project Milestones (as of Sept 2017)

  5. Mechanics Production status Metallic optical disc quality issue (from supplier in NL) appears to be fully resolved. 15/30 accepted as of 15/11/18 – good work from Dmitry and Jose! The rest should be complete before end of Nov. MME visited tank supplier on 8/11. First deliveries before end of November

  6. Mechanics Production Status • Instruments • Vacuum acceptance now in-progress with the series discs integrated • Preliminary results are good • Tanks • Delivery should start before end of Nov. • Pre-series of 4 tanks, will be used to accelerate vacuum tests of instruments • UHV cleaning process of the supplier has been qualified, but pre-series will be re-tested at CERN • Support structures • In production, components expected before end 2018. • Assembly and test in early 2019

  7. BE-BI works as part of the E5R4 BWS Sectorisation15-04-19 8:00 AM - 30-04-19 5:00 PM Installation of BWSRC_41667 & BWSRC_41678 in SPS LSS402-12-19 8:00 AM - 06-12-19 5:00 PM Miseen Place de 2 BWSRC in SPS LSS402-09-19 8:00 AM - 09-09-19 5:00 PM BE-BI works as part of the E5L4 BWS Sectorisation01-04-19 8:00 AM - 12-04-19 5:00 PM Install 4 horizontal BWS in PSB ring, Period 403-06-19 8:00 AM - 07-06-19 5:00 PM SPS LSS5 Dismantling: Removal of BWSA 5199512-02-19 8:00 AM - 15-02-19 5:00 PM Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Start01-02-19 Finish01-07-20 Installation L4T.BWS.124716-04-19 8:00 AM - 16-04-19 5:00 PM Install 4 verticle BWS in PSB ring, Period 1104-06-19 8:00 AM - 11-06-19 5:00 PM Re-installation of LSS5: Installation of BWSD 516xx15-06-20 8:00 AM - 19-06-20 5:00 PM Removal of BWSRE 5174022-02-19 8:00 AM - 27-02-19 5:00 PM Re-installation of SPS LSS5: Installation of BWSRC_516xx & BWSRC_516xx03-12-19 8:00 AM - 09-12-19 5:00 PM Miseen Place de 2 BWSRC in SPS LSS514-10-19 8:00 AM - 18-10-19 5:00 PM Removal of BWSD 5173122-02-19 8:00 AM - 27-02-19 5:00 PM *Except 01/07/19 – 25/08/19 BWS January 2019 to June 2020 SPS from Sept. to Dec. 2019 2020 2019 PSB in June 2019 LINACs / Transfer lines PSB PS SPS LHC Wire scanner electronics upgrade in LHC10-12-18 - 09-03-20 Courtesy Ana Miarnau

  8. New Wire scanners in the PS02-07-19 8:00 AM - 21-08-19 3:00 PM New Wire Scanner in SS6502-07-19 10:00 AM - 03-07-19 5:00 PM New Wire Scanner in SS5423-07-19 8:00 AM - 21-08-19 3:00 PM New Wire Scanner in SS8515-07-19 3:00 PM - 19-07-19 3:00 PM New Wire Scanner in SS6802-07-19 1:00 PM - 04-07-19 12:00 PM 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 Start01-07-19 8:00 AM Finish22-08-19 5:00 PM New Wire Scanner in SS6402-07-19 8:00 AM - 03-07-19 3:00 PM Installation LBE.BWS2523-07-19 8:00 AM - 24-07-19 5:00 PM Installation LBE.BWS3023-07-19 1:00 PM - 25-07-19 12:00 PM New LBE line10-07-19 8:00 AM - 02-08-19 5:00 PM BWS from 01-07-19 to 22-08-19 PS in July-Aug. 2019 LINAC to PSB transfer lines PSB PS SPS LHC Courtesy Ana Miarnau