1 / 33

The Australian Energy Technology Assessment 31 July 2012

The Australian Energy Technology Assessment 31 July 2012. Professor Quentin Grafton Executive Director/Chief Economist Bureau of Resources and Energy Economics (BREE). The Economic Club of Canada Ottawa, Canada 21 February 2012. Outline. I. AETA Overview

Télécharger la présentation

The Australian Energy Technology Assessment 31 July 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Australian Energy Technology Assessment31 July 2012 Professor Quentin Grafton Executive Director/Chief Economist Bureau of Resources and Energy Economics (BREE) The Economic Club of Canada Ottawa, Canada 21 February 2012

  2. Outline I. AETA Overview II. Assumptions, Costs and Technologies III. AETA Model IV. Levelised Costs of Electricity Technology Comparisons V. Levelised Costs of Electricity International Comparisons VI. Key Findings

  3. I AETA Overview

  4. AETA – Aim and Frequency AETA provides the best available and most up-to-date estimate of current and future costs (component cost and levelised costs) of a 40 electricity generation technologies. Full report and ‘bottom up’ study to be undertaken biennially, but opportunity for technology updates of cost and performance parameters biannually (March 2013 is next planned update).

  5. AETA 2012 Timelines Project initiated on 4 October 2011 to assess LCOE for 40 different technologies by state (and some cases sub-state) for 2012, 2020, 2030, 2040 and 2050. Work undertaken jointly with AEMO (Stage I). WorleyParsons (WP) has been primary contractor to deliver component costs and LCOE. WP sub-contracted ACILTasman to provide fuel costs and CSIRO provided use of its ‘learning rate’ model for long-term cost projections. Release of AETA Report and AETA Model 31 July 2012.

  6. Approach Component costs have been developed through a bottom-up engineering analysis of each of the technologies. Parameters provided for each electricity generation technology (capital costs, O&M costs, fuel costs, thermal efficiency, capacity factors, emission intensity, etc). AETA has been managed by a Project Steering Committee (PSC) Chaired by Professor Quentin Grafton (BREE) and including: Professor Ken Baldwin (ANU), Dr Alex Wonhas (CSIRO), Dr Arif Syed (BREE), Rob Jackson (AEMO), Rick Belt (RET) and Mark Stevens (RET).

  7. Stakeholder Participation AETA has been supported by inputs from wide range of stakeholders with expertise in a large number of the technologies (coal, gas, solar, wave, geothermal,…) In addition to stakeholder meetings in Stage I, BREE has Chaired two meetings of the Stakeholder Reference Group (SRG) that included 42 organisations/agencies/companies for feedback and inputs (10 February and 13 June 2012 ). Members of SRG were invited to provide written submissions on approach and parameters by COB 6 July. BREE received 13 written submissions.

  8. AETA Report and Model AETA Report: Details the technologies and methods and provides comparisons to other studies AETA Model: Downloadable model that provides component costs and levelised cost of electricity for 40 technologies that needs to be used in conjunction with AETA Report.

  9. II Assumptions, Costs and Technologies

  10. Key Assumptions AETA was developed to be consistent with the Australian Energy Market Operator’s (AEMO) National Transmission Network Development Plan (NTNDP), and its ‘planning scenario’. Key assumptions include: (1) economic growth of 2.5%; (2) $23/tonne CO2-e leading to a 5% reduction in CO2 by 2020, and 80 % by 2050; (3) AUD moving to peak of 1.13 USD/AUD by 2016-17 and low of 0.86 USD/AUD by 2031-32. Capital costs are provided on the basis of an Nth-of-a-kind (NOAK) plant in Australia and at a utility-scale.

  11. Key Assumptions AETA was developed to be consistent with the Australian Energy Market Operator’s (AEMO) National Transmission Network Development Plan (NTNDP), and its ‘planning scenario’. Key assumptions include: (1) economic growth of 2.5%; (2) $23/tonne CO2-e leading to a 5% reduction in CO2 by 2020, and 80 % by 2050; (3) AUD moving to peak of 1.13 USD/AUD by 2016-17 and low of 0.86 USD/AUD by 2031-32. Capital costs are provided on the basis of an Nth-of-a-kind (NOAK) plant in Australia and at a utility-scale.

  12. Component Costs Capital Costs (local & international components) Operation & Maintenance (fixed and variable) Fuel costs (provided by ACIL Tasman) Carbon sequestration and storage Owner’s costs Not included are decommissioning costs, network or transmission costs or additional local, site specific costs.

  13. Levelised Cost of Electricity (LCOE)

  14. AETA Technologies 40 electricity technologies evaluated: Coal-based (14 options with different fuels & technologies) Gas-based (CCGT with various options) Solar-thermal (CLFR, parabolic trough, central receiver) Solar-thermal hybrid (solar-coal & integrated solar combined cycle) Photovoltaic (fixed and tracking) Wind (on-shore and off-shore) Wave (reaction point absorber) Biomass (landfill, sugarcane & other) Geothermal (HSA and EGS) Nuclear (Generation III)

  15. III AETA Model

  16. AETA Common Technology Parameters

  17. AETA: Specific Technology Parameters

  18. AETA: Regional Costs

  19. AETA: Component Costs

  20. AETA: LCOE Over Time

  21. IV LCOE Technology Comparisons

  22. V LCOE International Study Comparisons

  23. Comparison with international studies, current costs

  24. VI Key Findings

  25. Key Findings (1) Estimated costs of solar photovoltaic technologies have dropped dramatically in the past two to three years as a result of a rapid increase in the global production of photovoltaic modules. Differences in the cost of generating electricity, especially between fossil fuel and renewable electricity generation technologies, are expected to diminish over time. Biogas (landfill and sugar cane) electricity generation technologies in 2012 are some of the most cost competitive forms of electricity generation (LCOE basis) and are projected to remain cost competitive out to 2050.

  26. Key Findings (2) By 2030 some renewable technologies, such as solar photovoltaic and wind onshore, are expected to have the lowest LCOE of all of the evaluated technologies. Among the non-renewable technologies, combined cycle gas (and in later years combined with carbon capture and storage) and nuclear power, offer the lowest LCOE cost competitive with low cost renewable technologies. For some technologies, LCOE is projected to increase over time due to: projected weakening of the Australian-dollar exchange rate, rising carbon price and cost escalation factors.

  27. Download AETA Report and ModelatWWW.BREE.GOV.AU bree.gov.au

More Related