An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LAT Planning Meeting Mechanical/Thermal Systems November 2004 Marc Campell

  2. THE GRID IS HERE!

  3. MECH Milestones Dates TBR

  4. LM ETC • Formal ETC from LM is in progress. This data has not been submitted by LM.

  5. LM Risks • Radiator • Timely headcount roll-off • First time use of bonding/assembly tool & procedures (No full sized Dev hardware). MFG marching army costs • Radiator Assembly design doesn’t accommodate repairs • Handling risks – large, fragile hardware • Cost over runs in testing • Fixture design (Acoustic) • Facility scheduling – competing with other LM priority programs • Resolution of TCS anomalies during Thermal Balance testing. Test marching army costs • Satisfactory replacement of key personnel

  6. LM De-scope Options • Radiator Vibe testing • Current plan • 5-150 Hz low level sine sweep in 3 axes • 5-50 Hz sine sweep in 2 axes • 5-150 Hz low level sine sweep in 3 axes • Acoustic test • 5-150 Hz low level sine sweep in 3 axes (plan to substitute - 6 dB acoustic run for this)

  7. LM De-scope Options (cont) • Radiator Vibe testing - De-scope options • Defer 5-150 Hz sine sweep until LAT level • Perform twang and/or tap test of Radiator for model validation (first modes only) • Delete 5-150 Hz sine sweep for post test signatures • Perform -6 dB Acoustic runs before & after P/Qual level Acoustic test for pass/fail evaluation • Delete 5-50 Hz sine sweep • Qual by analysis (LM is defining where there are inadequate margins for this) • Interface potted inserts are tested by witness coupons that are bonded simultaneously on the sides of the Radiator panel during layup • These actions carry low to moderate risk per J. Ku • Cost savings ~$160,000 (8 LM EM x .75 month)?

  8. LM De-scope Options (cont) • X-LAT Thermal Testing • Perform Thermal Cycle test in air instead of thermal vacuum • This is primarily a workmanship test and there is low risk. • Violates MAR requirement for 4 Thermal Vacuum cycles. • Tom McCarthy indicated that 8 thermal cycles in air would be acceptable to him. • Need to implement now to maximize savings (test preparations are underway). • LM will investigate the feasibility of this change. • Cost Savings ~$50,000 (~1/2 of quoted cost)

  9. Grid #2 Static Load Test To Go • SLT budget • Grid Box #2 Assy Operations $34,170 • Design & Fab MGSE/fixtures $78,650 • Test $180,000 • Total $292,820 • Note: This test does not drive LAT schedule • Risks • Test house not selected • If FE model doesn’t correlate then additional test cases will be required • There is sufficient budget for these contingencies • De-scope options • None. This test allows deletion of LAT Sine Vibe (LAT de-scope). • The number of load cases required has been reduced.

  10. BACK-UP

  11. MECH ETC

  12. MECH BOE Mechanical Systems Labor Increases $140.5K • This increase consists of $40K for the Multi- Layer Insulation (MLI) blanket design. Very early on in the program, the ACD subsystem was responsible for the LAT MLI design and fabrication. Because of the complexity of the MLI interfaces with the Spacecraft, Radiators and LAT external features, it was decided to pull this work back to SLAC. Additionally, Thermal Engineering support is now available at SLAC to support this task. • $100.5K has been added for Mechanical Systems support of the LAT I & T efforts at the end of FY05. These tasks include X-LAT Plate installation and Radiator fit check and shimming operations on the LAT prior to LAT shipment.

  13. MECH BOE (con’t) Mechanical Systems Material Increases $1,620.5K This increase consists of $1,580.5K (TBR) additional funding to complete the Lockheed Martin contract. There are two main cost drivers: 1) Lockheed schedule delays and 2) SLAC imposed changes. • 1) LM overran the following tasks: • Radiator design, • Radiator analysis (structural development), • Radiator tooling design & fab, • Radiator Thermal Controls design and • X-LAT Plate analysis. • These overruns have left insufficient budget for the remaining tasks to be completed.

  14. MECH BOE (con’t) • 2) The following changes were made after Lockheed submitted their February 2004 cost proposal and resulted in extra costs (WAG $150K). • Additional thermal analyses for the X-LAT plate to electronics box interface, for the thermal combs (heat shunt for the GASU box) and for the U-shaped heat pipes that were added then removed from the X-LAT plate, • MLI blanket design consultant, • Radiator EMI coupon testing, • Added keying features to the Radiator There is also an additional $40K for the Multi- Layer Insulation (MLI) blanket fabrication. Very early on in the program, the ACD subsystem was responsible for the LAT MLI fabrication. Because of the complexity of the MLI interfaces with the Spacecraft, Radiators and LAT external features, it was decided to pull this work back to SLAC.