1 / 50

Tevatron Operations

Tevatron Operations. Ron Moore DOE Tevatron Operations Review March 27, 2007 SC-1 Breakout. Since the 2006 shutdown ended…. 209 HEP stores ( give/take a few…not counting ones lost before HEP) Record delivered lumi / week 24.4 → 44.9 pb -1

schmitz
Télécharger la présentation

Tevatron Operations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tevatron Operations Ron Moore DOE Tevatron Operations Review March 27, 2007 SC-1 Breakout

  2. Since the 2006 shutdown ended… • 209 HEP stores(give/take a few…not counting ones lost before HEP) • Record delivered lumi / week 24.4 → 44.9 pb-1 • Record peak luminosity 180 → 292 1030 cm-2 s-1 • Record # pbars at start HEP ≈ 3072 109 • Delivered > 1 fb-1 to CDF and D0 • Run 2 total delivered now > 2.6 fb-1, recorded > 2.0 fb-1 2007 DOE Tevatron Operations Review – R. Moore

  3. Run II Peak Luminosity 2007 DOE Tevatron Operations Review – R. Moore

  4. 2006 Tevatron Shutdown Tasks • Fixed known cold leaks in E2, A3, B4; replace failed dipole in F4 • Replaced all ≈1200 LHe Kautzky valves • Cause of 2 magnet failures prior in Nov 06 and Feb 07 • Completed reshimming on remaining 228 dipoles • Needed 3 shutdowns to do! Cryostat sagging – causing coupling • Unrolled quads in A3 (~10 mrad); unroll ~60 magnets with small rolls • Installed 2 new separators (B48, A17), replace 3 separators (A49) • Repaired TEL-1 and installed TEL-2 • Pulled cables for new sextupole circuits (2nd order chromaticity correction) • Completed IPM detector installation • Completed ring-wide hydrostatic level sensor installation • Many smaller tasks, lots of maintenance… • Smooth start-up after such a long shutdown • Run II upgrades effectively complete 2007 DOE Tevatron Operations Review – R. Moore

  5. Highlights since 2006 Shutdown • More pbars to HEP • Thanks to Pbar Source and Recycler • More protons to HEP • Injecting more protons • Better lifetime @ 150 GeV from new helical orbit • Improved luminosity lifetime • Additional separators increase beam-beam separation • Commission TEL-2 • Spare abort gap cleaner & demonstration of beam-beam compensation • Smooth orbits to desired HEP position every store • Improvement on orbit stabilization • Faster halo removal – save few minutes • Get to HEP sooner • Online luminosity fits and model comparison • New tools based on SDA/SuperTable data 2007 DOE Tevatron Operations Review – R. Moore

  6. 2006 shutdown Injecting More Proton and Pbars 2007 DOE Tevatron Operations Review – R. Moore

  7. 2006 shutdown Improved Proton Efficiency @ 150 GeV 2007 DOE Tevatron Operations Review – R. Moore

  8. Improved Proton Efficiency vs Pbar Intensity • New injection helix increased separation between beams (Yu. Alexahin) 2007 DOE Tevatron Operations Review – R. Moore

  9. FY07 Integrated Luminosity A18 vacuum leak E39/43 vacuum failure D32-5 failure feeder 46B fault 2007 DOE Tevatron Operations Review – R. Moore

  10. 2006 shutdown Getting More Proton and Pbars to HEP 2007 DOE Tevatron Operations Review – R. Moore

  11. Luminosity Lifetimes • Long-range beam-beam effects degrade lumi lifetime + integral • Nearest parasitic crossings (≈59 m from IPs) especially bad • Additional separators installed to allow increased separation • More separation  reduced beam-beam effects • ~20% increase @ upstream IP • Not as much @ downstream IP • Luminosity lifetime improved ~20% compared to pre-shutdown • Increased integrated luminosity per store (for similar luminosities and store lengths) 2007 DOE Tevatron Operations Review – R. Moore

  12. Comparing HEP Stores to Model without Beam-Beam • After shutdown, luminosity evolution agrees better to model without beam-beam effects • Most pbars lost during HEP are burned in luminosity • That’s good! • Protons suffer more from beam-beam effects • Especially with smaller pbars V. Lebedev 2007 DOE Tevatron Operations Review – R. Moore

  13. Better Lifetime  More Delivered Luminosity Based on luminosity lifetime fits and adjusting to 24 hour store duration 2007 DOE Tevatron Operations Review – R. Moore

  14. Bunch-by-Bunch Tune Shifts: Store 5245 • Higher pbar intensities  proton/pbar head-on tune shifts ≈ equal! • Proton / pbar intensity ≈ 3, but proton/pbar emittance ≈ 3, too! • Consistent beam intensities store-to-store is helpful operationally • Otherwise, tune changes needed in advance to prevent lifetime problems • Pbar intensities vary more - lost stores, problems in upstream machines, etc. • Bunch leveling in Recycler also helpful for Tevatron and experiments • More uniform bunch dynamics, more uniform bunch-by-bunch luminosity 2007 DOE Tevatron Operations Review – R. Moore

  15. Tune Footprint Currently operate between 7/12 and 3/5 for collisions Considering moving near ½ integer 2007 DOE Tevatron Operations Review – R. Moore

  16. Beam Lifetimes • Pbar lifetime dominated by luminosity – good • Most protons lost in non-luminous processes – not so good Store 5245 Luminosity [μb-1/s] Proton Lifetime / ExpectedLifetime from Luminosity Pbar Lifetime / ExpectedLifetime from Luminosity 2007 DOE Tevatron Operations Review – R. Moore

  17. Smaller Pbar Emittance  Worse Proton Lifetime 2007 DOE Tevatron Operations Review – R. Moore

  18. Schematic of Beam-Beam Force on Proton Bunch 2007 DOE Tevatron Operations Review – R. Moore

  19. Example of Tight Tune Space for Protons Store 5008 L = 207 Longitudinal shaving Operator error – tune pushed too high 2007 DOE Tevatron Operations Review – R. Moore

  20. Store 5245 – Comparison to Model w/o Beam-Beam Initial Lumi = 286 μb-1/s ~10% loss from beam-beam 2007 DOE Tevatron Operations Review – R. Moore

  21. Reliability • Replaced all He Kautzky valve poppets in 2006 shutdown • Successfully tested higher bandwidth quench protection electronics (VFCs) • Implemented in 3 houses, gradually propagate to whole ring • Helps detect quench and pull abort in ≈350 μs (< 20 turns) • Migrated control applications from VMS to Linux • A BIG job requiring careful testing and implementation in operational environment • 2 Tevatron failure-driven shutdowns since June 2006 • Mouse-induced feeder glitch resulted in D3 dipole failure (Oct) • Failed O-ring caused loss of E3 cryo insulating vacuum (Nov) • New pbar cogging for ramp since early Jan 2007 • Pbars were in the abort gap previously – quench if abort up ramp • Now clear abort gap should prevent needless quenches (OK in only “trial” so far) • Implement new BLM electronics to allow aborts on high beam losses • Current system too inflexible – BLM aborts masked out during HEP 2007 DOE Tevatron Operations Review – R. Moore

  22. Tevatron Reliability 2007 DOE Tevatron Operations Review – R. Moore

  23. Integrated Lumi and Store Hours per Week 5 store running average scaled to 1 week 2007 DOE Tevatron Operations Review – R. Moore

  24. Looking Ahead • Implement 2nd order chromaticity correct @ low β • Correct second-order chromaticity @ low β better lifetime • Also required for possible new working point (near ½ integer) • Work with experiments in optimizing integrated vs peak luminosity • Multiple interactions cause difficulties for trigger and tracking • When is peak too high? Do we need higher intensities afforded by new working point? • Other minor improvements – they all add up! • Scrape (higher intensity) protons @ 150 GeV • Remove beam that would be lost anyway on ramp and squeeze • Get “brighter” protons to HEP • Investigating new cogging between pbar injections • Reduce beam-beam effects by changing locations of long-range crossings • Improve proton lifetime @ 150 GeV (bunch-dependent) • More reliable tune measurements • New 1.7 GHz Schottky electronics designed by FNAL (LARP) for LHC (better dynamic range) • New digital tune monitor to measure individual bunches (with tickling) • Better helices, improved transfer line matching, faster shot-setups, etc. 2007 DOE Tevatron Operations Review – R. Moore

  25. New Sextupole Circuits • Move 22 elements from existing SF&SD circuits to 12 new circuits • Correct 2nd order chromaticity in low-β lattice • Should reduce non-luminous proton losses • Operational with new power supplies since early February • Cables pulled during 2006 shutdown • Still configured as “normal” chromaticity sextupoles • Conducting proton-only studies to implement in final configuration • New circuits to run at zero current except @ low-β • Need short access to flip polarity of some elements when ready • Could be operational in ~1 month • Simulation results in Alex Valishev’s slides 2007 DOE Tevatron Operations Review – R. Moore

  26. Luminosity Projections • Refer to slides in R. Dixon’s talk • Projections assume ≈100 store hrs/week on average • Takes into account possible unplanned downtime (failures) • Based on current pbar stacking rate, appear on track to deliver 5.5-6.5 fb-1 total • Likely need increased stacking rates to go higher • Approaching design 320 μb-1/s peak luminosity • Consult with experiments if higher is OK for them • Goal is to maximize integrated luminosity on tape 2007 DOE Tevatron Operations Review – R. Moore

  27. Peak Pbar Stacking Rates Integrated Luminosity We’re in this area now 2.6 fb-1 ≈22 mA/hr March ‘07 2007 DOE Tevatron Operations Review – R. Moore

  28. One Example of Model Parameters • In general, weekly integrated luminosity ≈ independent of store length in 20-30 hr range → flexible running schemes • Pbar stacking rate important factor 2007 DOE Tevatron Operations Review – R. Moore

  29. Summary • Tevatron delivering record peak and delivered luminosity • Great start-up following long 13-week shutdown • Higher beam intensities to HEP, improved lifetime • Protons suffering more from beam-beam effects • Operationally challenging to stay in desired tune space when pbar intensities vary from store-to-store • Implementing 2nd order chromaticity compensation circuits • Should improve lifetimes in collisions • Prerequisite for investigating ½ integer working point • Maximize integrated luminosity to CDF and D0 • On track for 5.5-6.5 fb-1 at current pbar stacking rates • Let’s find the Higgs! 2007 DOE Tevatron Operations Review – R. Moore

  30. Backup Slides 2007 DOE Tevatron Operations Review – R. Moore

  31. NuMI (120 GeV) MiniBoone (8 GeV) A1 Line P1 Line 2007 DOE Tevatron Operations Review – R. Moore

  32. FY Integrated Luminosity 2007 DOE Tevatron Operations Review – R. Moore

  33. FY07 Peak Luminosity 2007 DOE Tevatron Operations Review – R. Moore

  34. FY05-FY07 Weekly Integrated Luminosity 5 store running average scaled to 1 week 2007 DOE Tevatron Operations Review – R. Moore

  35. FY 2007 Average Store Hours per Week 2007 DOE Tevatron Operations Review – R. Moore

  36. Machine Studies and Maintenance • Averaged ≈6.5 hrs / week since last shutdown • Does not include parasitic studies • Exploit natural breaks in machine operation • Lost stores, pbar stacks, etc. • Exploit end-of-store studies • Focus on specific, well-prepared studies • Be efficient, prevent unnecessary quenches/downtime • Start with proton-only stores before trying in HEP • If we really need study time to implement something new for HEP, will get the time • e.g., proton-only for commissioning new sextupole circuits 2007 DOE Tevatron Operations Review – R. Moore

  37. Proton #1 [E9] Proton #19 [E9] Pbar Int. [E9] Pbar cog [bkts] Proton #22 [E9] Proton #34 [E9] Lifetime of a proton bunch degrades when it has a parasitic crossing with pbar bunch near B13 Bunch-by-Bunch Proton Losses @ 150 GeV 2007 DOE Tevatron Operations Review – R. Moore

  38. New Injection Helix blue – oldred – present Separation in σ • Increased separation at “worst” parasitic crossing Parasitic Crossing Number (from B0) 2007 DOE Tevatron Operations Review – R. Moore

  39. New Collision Helix • After adding the A17H and B48V separators in 2006 shutdown blue – oldred – present Separation in σ Distance from B0 [m] 2007 DOE Tevatron Operations Review – R. Moore

  40. Better Lifetime  More Delivered Luminosity Based on luminosity lifetime fits and adjusting to 24 hour store duration 2007 DOE Tevatron Operations Review – R. Moore

  41. Separation at IPs with different cogging at injection S2min Injection cogging ncog=61 S1min ncog - cogging w.r.t. the collision one, ncog=0 Measured helix and optics used, reference emittance 15mmmrad 2007 DOE Tevatron Operations Review – R. Moore

  42. Beam-Beam Resonance Strengths vs Injection Cogging 5Qx Nominal values @ injection ncog=61 (before change) Collision cogging: ncog=0 ncog=-2 is the best for 7Qy ncog=10 is good for 5Qx while not bad for 7Qy Now implemented for ramp 7Qy ncog Yuri Alexahin RDTs (Resonance Driving Terms) calculated for 3 amplitude 2007 DOE Tevatron Operations Review – R. Moore

  43. Kautzky Valve Poppets • During quench, pressure forces valve open, allows He to escape • Poppet can break off, remain in closed position • 1 similar failure in 20 years, then 2 in three months • Replaced all ≈1200 He Kautzky valve poppets during 2006 shutdown • No poppet failures since replacement Broken poppet from B17 spool Kautzky valve Closed Kautzky valve 2007 DOE Tevatron Operations Review – R. Moore

  44. Online Luminosity Evolution Fits • Bunch-by-bunch lumi and beam intensities, too • Different fit functions and results stored in database, spreadsheets, etc. • Useful for Run Coordinator to determine end-of-store time 2007 DOE Tevatron Operations Review – R. Moore

  45. Holes from arcing D32-5 dipole beam tube Flashover in Feeder 46B cubicle D32-5 Dipole Failure in Oct 2006 • Mouse caused feeder fault • Glitch → D3 quench response • Dipole failed during quench • Previous D3 quench 9/11/02 • Failure lying in wait? 2007 DOE Tevatron Operations Review – R. Moore

  46. Tevatron Electron Lenses (TEL) • TEL-1 installed 2001; repaired & reinstalled 2006 • Used mainly to clean abort gap • Few studies demonstrating (horz) compensation on pbars (2003) • Test bed for electron gun designs • TEL-2 installed 2006 • Used as spare abort gap cleaner • Successful (vertical) tune-shifting on protons during HEP! TEL-2 on P12 TEL-2 2007 DOE Tevatron Operations Review – R. Moore

  47. TEL-2 in Action P12/24/36 lowest vertical tune (PACMAN) P12 intensity [E9] TEL-2 ON P12 P36 intensity [E9] TEL-2 off • TEL-2 increases proton lifetime by raising vertical tune away from 7/12 • TEL-1 could do same for horz tune on leading bunches of train • Little emittance growth, little/no increase in losses • Currently doing studies with TEL-1 while TEL-2 cleans abort gap • Could try simultaneous operation to level bunch tunes to help lifetime • TEL-2 Marx generator suffers from radiation damage – added steel shielding 2007 DOE Tevatron Operations Review – R. Moore

  48. IPM • Detectors installation completed during 2006 shutdown • Waiting for full complement of production electronics • Observed TBT quadrupole oscillations on injection • Will improve transfer line matching, emittance dilution Proton Bunch Injection Oscillations Protons & Pbars at Injection 2 RMS size [mm] 1 0 20 Turn # 2007 DOE Tevatron Operations Review – R. Moore

  49. Peak Pbar Stacking Rates Peak Luminosity 2007 DOE Tevatron Operations Review – R. Moore

  50. Peak Pbar Stacking Rates Delivered Luminosity per Week 2007 DOE Tevatron Operations Review – R. Moore

More Related