1 / 8

DoD Title 40/CCA LSS Initiative

DoD Title 40/CCA LSS Initiative. AoA Team Presentation October 7, 2008 William May ASD(NII)/Acquisition. AoA – Customers, Requirement and Impacts. “CCA Compliance” Customers: Congressional Defense Committees Milestone Decision Authority DoD (DCIO, PA&E, PM, PEO, CAE)

shania
Télécharger la présentation

DoD Title 40/CCA LSS Initiative

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DoD Title 40/CCA LSS Initiative AoA Team Presentation October 7, 2008 William May ASD(NII)/Acquisition

  2. AoA – Customers, Requirement and Impacts • “CCA Compliance” Customers: • Congressional Defense Committees • Milestone Decision Authority • DoD (DCIO, PA&E, PM, PEO, CAE) • Minimum Requirements - evidence of a “compliant” AoA: • AoA is completed before other planning activities begin • Compliance: Binary determination through D, PA&E assessment. • Either adequate or not adequate for compliance • Evidence: • D, PA&E analyst agrees with AoA document • D, PA&E formal review report (favorable) • Impact: • Other planning activities (e.g., EA, TDS, TES) will be more effectively and efficiently addressed during planning activities of the program • Reduction of negative impacts on cost, schedule and performance Selection of the best alternative drives other program planning activities

  3. AoA – Key Stakeholders • Key Stakeholders in the ACAT IAM AoA process: • Principal Staff Assistant • Functional Sponsor • Requirements Manager • PMO • System User organizations • D, PA&E • DCIO Analyst • MDA Analyst Stakeholder involvement is simple: Do you agree with the functional sponsor’s approach and selected alternative?

  4. AoA Process for ACAT IAM Programs N Acceptable? Functional Sponsor Reviews AoA Guidance Functional Sponsor Provides AoA Plan PA&E Provides AoA Guidance Start Y N Acceptable? D, PA&E Reviews AoA Plan Functional Sponsor provides AoA D, PA&E Reviews AoA Y N N Acceptable? Acceptable? MDA Reviews D, PA&E Provides Independent AoA Assessment to MDA Y Y Y MDA Approves By Certifying CCA Compliance End Average ACAT IAM AoA takes 15 months

  5. AoA – Key Success Factors • What do “successful” ACAT IAM AoAs have in common? • Well-written ICD that defines requirements and solid metrics • Early D,PA&E involvement • Knowledgeable, trained professionals performing AoA under proactive functional sponsor leadership • Component PA&E organization supporting the AoA process • Delay other planning activities until preferred alternative selected • Components self-identify Pre-MAIS to OSD early in the process • Holding a Materiel Development Decision vice proceeding directly to Milestone B • Synchronize funding requirements with PPBE process “Success” is an AoA that is completed and approved before Beginning other planning activities

  6. AoA – Critical Content Criteria • Top-level AoA contents (must be preceded by approved AoA Plan) • Introduction • Ground Rules • Alternatives • Determination of Effectiveness Measures • Effectiveness Analysis • Cost Analysis • Cost-Effectiveness Comparisons • Organization and Management Source: Section 3.3, Defense Acquisition Guidebook

  7. AoA – Key Lessons Learned • Key Lessons Learned in the AoA process: • Short, well thought out AoAs are preferred over lengthy “boilerplate” documents • Setting AoA page limits should be considered • Early Pre-MAIS self-identification to OSD is essential • Early D, PA&E involvement is key to good AoAs • Working on other planning documents before selecting a preferred alternative is counter productive • Knowledgeable, trained professionals are essential • Consider AoA team training early in the process • Proactive functional sponsor leadership • Consider requiring government people to complete DAU CLM 041 and RQM 101 courses Example documents are good but … IT ALL DEPENDS!

  8. AoA – Barriers/Obstacles/Problems • ACAT IA functional sponsor comes to OSD with: • Preferred alternative already identified • Most planning documents well along in planning process • OSD staff not previously part of the planning process • Functional sponsor views AoA as non-value added “paperwork exercise” vice a key planning element • “Alternative already selected – just let me buy it!” • Component seek entry into AMS at Milestone B without really thinking through the AoA and other key planning activities • Recent MITRE study showed a direct correlation between increased planning time and lower cost increases AoA is in the critical path … must precede other planning documents

More Related