1 / 10

g2p/ GEp Beamline Status

g2p/ GEp Beamline Status. Tim Michalski Project Lead. Overview. Facilitate the design, procurement, and build of the beamline – up to the target chamber Experimental Plan Project Overview Project Status Project Challenges with risk mitigation. Experimental Plan. Target Elevated by ???.

shika
Télécharger la présentation

g2p/ GEp Beamline Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. g2p/GEp Beamline Status Tim Michalski Project Lead

  2. Overview Facilitate the design, procurement, and build of the beamline – up to the target chamber Experimental Plan Project Overview Project Status Project Challenges with risk mitigation

  3. Experimental Plan Target Elevated by ??? *** - FZ1 and FZ2 in position for 2.2 GeV run, but with half field strength on FZs and Target magnets

  4. Project Overview • Design, procurement, component calibration and testing • Now through May, 2011 • Some components arrive after May • Access to Hall A for installation • May 16, 2011 • Installation completion – start of Physics • November 19, 2011

  5. Project Status • Regions 1 and 2 designs complete and material ordered • Region 3 design complete – final review and procurement in coming weeks • Calorimeter controller repaired and SW upgrades nearly complete • I&C electronics designed and being built • Addition of SR PS chamber, w/ cooling • Resource planning integrated into 6MSD schedule • Several changes to the run plan being evaluated

  6. Project Challenges • Instrumentation for Low Current data • BPMs and BCMs • Mitigation • BPM – short M15 style, new electronics, tested • BCM – new receiver • FZ Magnet PS requirements evolving • Need up to 4 kG, requiring 231A for FZ1 • Need up to 8 kG, requiring 465A for FZ2 • Mitigation – assessed capabilities of magnet power supplies in Hall C – meet requirements – assembling spares

  7. Project Challenges • Acquisition of equipment from various sources • FZ magnets, corrector magnets, slow raster, new BPMs, power supplies, controllers • Mitigation – get control as soon as possible, test and calibrate early (before installation) • Resurrection of Tungsten Calorimeter • Reposition in beamline, re-establish functionality, recalibrate • Mitigation – Controller extracted from Hall A, repaired, new PC104 SW nearly complete

  8. Project Challenges • Slow Raster issues raised at last collaboration meeting – waveform generators and “hole” in raster pattern • Mitigation – New function generator – Testing in Progress • Installation at the same time as 12 GeV upgrades during 6 month down • Mitigation – tied to detailed 6MSD planning – all resources identified in schedules – have ~3 weeks float

  9. Project Challenges • Proposed changes to run definition – a) target height when upstream, b) 1.157 GeV run when target at pivot • Mitigation – Run new orbits on optics, address changes in FZ2 magnet position and articulating arm – defined impact to work and calendar time • Maintain strong communication – highlight issues early!

  10. Beam Line Installation Schedule

More Related