1 / 6

QATARGAS II/SOUTH HOOK PROJECT

QATARGAS II/SOUTH HOOK PROJECT. Presentation to The GIE Annual Conference 28 September 2006. Mohammed Al Naimi Commercial Manager, South Hook LNG Terminal Company Ltd. IRAN. North Field. Doha. QATAR. UAE. KSA. Qatar Overview. Turkey. Turkmenistan. Syria. Iraq. Iran. Jordan.

shona
Télécharger la présentation

QATARGAS II/SOUTH HOOK PROJECT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. QATARGAS II/SOUTH HOOK PROJECT Presentation to The GIE Annual Conference 28 September 2006 Mohammed Al Naimi Commercial Manager, South Hook LNG Terminal Company Ltd

  2. IRAN North Field Doha QATAR UAE KSA Qatar Overview Turkey Turkmenistan Syria Iraq Iran Jordan Kuwait Egypt UAE Saudi Arabia Oman Sudan Yemen Ethiopia Somalia Existing Facilities/Projects • 10 LNG trains • Contracted supply to Japan, Korea, Europe, USA Future Projects • 4 additional LNG trains (30+ MTA additional capacity) Qatar • Population 0.9M • Area 11,400 km2 North Field • World’s largest non-associated gas field • Proved gas reserves of 900 TCF

  3. Project Gas LNG LNG Gas to Pipeline Gas Production Gas Treating & Liquefaction LNG Shipping LNG Regasification $ 13 billion dollar mega-project employing full value chain integration, step-out technologies, and economies of scale to offset distance to market. • Gas from world’s largest gas field; 2.8 BCFD • Two 7.8 million MTA trains will be the largest ever constructed; 60% larger than any to date • A fleet of 14 large LNG ships; at 210 – 265 km3, 70% larger than any ever built • Receiving terminal in the U.K. to re-gasify and deliver 2.1 BCFD approx 20% of UK demand

  4. Qatargas Onshore Plant Layout QGII Trains 4 & 5 QG1 Trains 1 - 3

  5. South Hook Terminal Development Plan • 2.1 BCFD send out capacity • Five 155 km3 full containment LNG storage tanks • Upgrade and refurbishment of existing jetty • Submerged Combustion Vaporizers (SCVs) • Pipeline extension (128 km) to national gas grid to be built and operated by NGG • EPC by Chicago Bridge & Iron • Total capex of $1.4 B • Status • Phase 1 currently 50% complete; Phase II 37% complete • First gas winter 07/08

  6. Thank you