Lockwood place Baltimore, Maryland

This presentation outlines the structural redesign of Lockwood Place, a mixed-use development in Baltimore, Maryland. It covers the existing conditions, objectives, measure of success, two-way post-tensioned floor system, concrete columns and shear walls, mechanical retrofit, and cost and schedule analysis.

simmers
Télécharger la présentation

Lockwood place Baltimore, Maryland

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lockwood placeBaltimore, Maryland Monica Steckroth- Structural Option

  2. Presentation Outline • Project Introduction & Building Background • Existing Conditions • Objectives & Measure of Success • Structural Redesign • Two-Way Post-Tensioned Floor System • Concrete Columns & Shear Walls • Mechanical Retrofit • Cost & Schedule Analysis • Conclusions & Recommendations Monica Steckroth- Structural Option

  3. Lockwood Place Use: Mixed-Use Development Location:Baltimore, Maryland Construction: June 2003 -September 2004 Envelope:Glass Curtain WallAbuts a Covered Mall and Adjacent Parking Deck Monica Steckroth- Structural Option

  4. Lockwood Place Size:302,348 sq.ft. Height:13 Stories13.5’ Typical Story Height194’ tall Cost:$28 million base cost$8 million change orders Monica Steckroth- Structural Option

  5. Lockwood Place • Owner: TC MidAtlantic Inc. • Managing Partner: Kravco Company • Developer: Lockwood Associates, LLC • Vertical Transportation Consultant: Lerch Bates & Associates • Lighting Design Consultant: The Lighting Practice, Inc. • Structural Engineer: Hope Furrer Associates, Inc. • MEP Engineer: B&A Consulting Engineers • Civil Engineer: STV Incorporated • General Contractor: Helix Construction Services, Inc. Monica Steckroth- Structural Option

  6. Presentation Outline • Project Introduction & Building Background • Existing Conditions • Structural Redesign • Two-Way Post-Tensioned Floor System • Concrete Columns & Shear Walls • Mechanical Retrofit • Air Distribution System Resized • Cost & Schedule Analysis • Conclusions & Recommendations Monica Steckroth- Structural Option

  7. Existing Conditions Gravity System: Composite Steel Typical Bay Size:30’-0” x 45’-0”30’-0” x 30’-0” f’c= 3500psify= 50ksi Lightweight Concrete 6-1/4” slab3”, 20 gage Composite Deck 3/4” Ø, 5-1/2” long shear studs Monica Steckroth- Structural Option

  8. Existing Conditions Lateral System: Eccentric Braced Frames:W14x90 – W8x31 Moment Frames Monica Steckroth- Structural Option

  9. Existing Conditions Foundation: Drilled Caissons:2-6” to 6’-0”f’c= 4500psiDrilled 1’-0” to 5’-0” into Gneiss Bedrock Grade Beams:Between Pile Caps18”x24” to 24”x42” Monica Steckroth- Structural Option

  10. Presentation Outline • Project Introduction & Building Background • Existing Conditions • Objectives & Measure of Success • Structural Redesign • Gravity System • Lateral System • Mechanical Retrofit • Cost & Schedule Analysis • Conclusions & Recommendations Monica Steckroth- Structural Option

  11. Objectives • Eliminate Cost and Labor Created by Holes • Allow More Mechanical Flexibility Additional $150,000 in Cost of Steel! Over 200 Holes per Typical Floor! Monica Steckroth- Structural Option

  12. Measure of Success Monica Steckroth- Structural Option

  13. Presentation Outline • Project Introduction & Building Background • Existing Conditions • Objectives & Measure of Success • Structural Redesign • Two-Way Post-Tensioned Floor • Concrete Columns & Shear Walls • Mechanical Retrofit • Cost & Schedule Analysis • Conclusions & Recommendations Monica Steckroth- Structural Option

  14. Structural Redesign Monica Steckroth- Structural Option

  15. Structural Redesign • Shear Resistance • 18” Column Capitals • 8’-0” x 8’-0” Monica Steckroth- Structural Option

  16. Structural Redesign • Tendon Layout (12) 320K Additional 4@4’o.c. 60K/FT (14) 372K (32) 692K (24) 639K (4 @4’o.c.) 32K/FT East/West Large Banded Tendons North/South Small Banded Tendons Monica Steckroth- Structural Option

  17. Structural Redesign • Floor Deflection Monica Steckroth- Structural Option

  18. Structural Redesign Monica Steckroth- Structural Option

  19. Structural Redesign • Typical Column 5000psi 6000psi Monica Steckroth- Structural Option

  20. Structural Redesign • Front Column Design Monica Steckroth- Structural Option

  21. Structural Redesign • Shear Wall Thicknesses: 10” N/S, 14” E/W • Controlling Lateral Load Combination: 0.9D+1.6W Wind Displacement Seismic Story Drift Max = 1.78” Monica Steckroth- Structural Option

  22. Structural Redesign • Shear Wall Design Monica Steckroth- Structural Option

  23. Structural Redesign • Shear Wall Design Monica Steckroth- Structural Option

  24. Structural Redesign • Shear Wall Design Monica Steckroth- Structural Option

  25. Structural Redesign • Coupling Beam Monica Steckroth- Structural Option

  26. Structural Redesign • Caisson Adjustment • Caisson Uplift Zero • Diameter Increase 30” $176,800 Foundation Increase 48” Monica Steckroth- Structural Option

  27. Presentation Outline • Project Introduction & Building Background • Existing Conditions • Structural Redesign • Two-Way Post-Tensioned Floor • Concrete Columns & Shear Walls • Mechanical Retrofit • Cost & Schedule Analysis • Conclusions & Recommendations Monica Steckroth- Structural Option

  28. Mechanical Retrofit • Existing Air Distribution System: • AHU located at each typical floor • Distributes 17000cfm • Powered Induction Units Heated Air Distributed to Respective Zones Plenum Air Supply Air 46°F Monica Steckroth- Structural Option

  29. Mechanical Retrofit Objectives: Monica Steckroth- Structural Option

  30. Mechanical Retrofit • Resized Air Ducts According to TRANE Calculator Greatest Change in Diameter = 5”

  31. Mechanical Retrofit • Section Difference +14” Utilized • Change in Air Velocity: 1698ft/min 2275ft/min Monica Steckroth- Structural Option

  32. Mechanical Retrofit Existing Fan Proposed Fan • 40”, TRANE manufactured • 20 Horsepower, 480V/3 Phase • Force Flow Centrifugal Variable Frequency Drive, blow-thru • ∆3.6” static water pressure required • 40” TRANE manufactured • 11.2Horsepower, 480V/3Phase • Type Q • ∆2.83” static water pressure required (0.2” losses provided by the fan) Monica Steckroth- Structural Option

  33. Mechanical Retrofit Centrifugal Blow-Thru Fan www.trane.com Type Q Fan www.trane.com Monica Steckroth- Structural Option

  34. Presentation Outline • Project Introduction & Building Background • Existing Conditions • Structural Redesign • Two-Way Post-Tensioned Floor • Concrete Columns & Shear Walls • Mechanical Retrofit • Cost & Schedule Analysis • Conclusions & Recommendations Monica Steckroth- Structural Option

  35. Cost & Schedule Analysis Cost Consideration: 16% Savings! Monica Steckroth- Structural Option

  36. Cost & Schedule Analysis • Existing Schedule Construction: June 2003- September 2004 3 Sequences constructed – 3 Levels/ Sequence Total Structure Construction = 35 weeks Monica Steckroth- Structural Option

  37. Cost & Schedule Analysis • Proposed Schedule 1Sequence= 1 Level Total Structure Construction= 40 weeks • Comparison 5 Additional Weeks! Monica Steckroth- Structural Option

  38. Presentation Outline • Project Introduction & Building Background • Existing Conditions • Objectives & Measure of Success • Structural Redesign • Two-Way Post-Tensioned Floor • Concrete Columns & Shear Walls • Mechanical Retrofit • Cost & Schedule Analysis • Conclusions & Recommendations Monica Steckroth- Structural Option

  39. Conclusion & Recommendations Decrease Structural Floor Depth with Concrete System Larger Air Duct and Smaller Fan Size Requiring Less Energy Reasonable Cost & Schedule Differences Monica Steckroth- Structural Option

  40. Acknowledgements My Family & Friends Dr. Linda HanaganThe Pennsylvania State University, Faculty Advisor Architectural Engineering FacultyThe Pennsylvania State University Carol Hayek, PhDSD Post-Tensioning Hope FurrerHope Furrer Associates, Inc. B&A Consulting Engineers Milton Steel, Inc. Jason WittermanPenn State AE Mechanical Option Todd PovellPenn State AE Construction Option Monica Steckroth- Structural Option

  41. Questions? Monica Steckroth- Structural Option