炼钢厂 9 月 29 日汇报内容(一)

炼钢厂 9 月 29 日汇报内容(一). 一、上周指标完成情况: 1 、产量完成情况: 2 、成本指标完成情况:. 炼钢厂 9 月 29 日汇报内容(二). 二、产量和成本未完成原因: 钢坯产量未完成原因,注意是铁水少造成,其中铁耗影响产量 900 吨;白灰亏产的原因主要是炼钢白灰窑的检修 5 天造成。

Télécharger la présentation

炼钢厂 9 月 29 日汇报内容(一)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 炼钢厂9月29日汇报内容(一) 一、上周指标完成情况: 1、产量完成情况: 2、成本指标完成情况:

  2. 炼钢厂9月29日汇报内容(二) 二、产量和成本未完成原因: 钢坯产量未完成原因,注意是铁水少造成,其中铁耗影响产量900吨;白灰亏产的原因主要是炼钢白灰窑的检修5天造成。 钢坯成本超支原因,主要一是受到产量影响,7天亏计划7514吨,造成铸机非计划成本0.75元,能源增加成本10.7元,固定费用增加18元;二是受到铁水成份的影响,造成我厂成本16.15元;三是由于终点低,钢水硫高,为了保证产品MN/S比,合金成本增加8.2元;四是入炉原料的配比影响,铁耗超计划19公斤,影响成本5.1元,外购废钢增加8.4公斤,由于外购出水率低,影响成本5.04元,自产废钢比计划少9.6公斤,造成成本增加8.2元。影响白灰成本主要是固定费用的增加,因产量低造成。 三、上周重点工作完成情况: 1、着重做好内部联查,规范现场管理,为迎接中秋和国庆做好准备。。 2、利用拉下时间,做好三期旋流井的清理工作 3、着重做好炼钢白灰窑检修和改造工作 4、全力做好成本压缩、节支、挖潜工作 四、下周重点工作: 1、着重抓好双节期间的安全管理,重点抓好领导值班、员工出勤工作。 2、抓好炉前化渣剂的代替工作,“由氧化铁皮代替铁矾土工作” 3、抓好转炉装入制度落实工作,稳定装入量,做好成本精细化管理。 4、抓好5#机进度的管理工作,设备专业全部介入,做好设备工程质量管理。

More Related