1 / 14

South Maple Street Sanitary & Storm Sewer System Improvements Project

South Maple Street Sanitary & Storm Sewer System Improvements Project. October 14, 2014. Project Area. 400 block South Maple Street 12 & 24 College Street 200 block Boone Avenue (east side of Boone) 101 & 117 Belmont Avenue. Project Area…. Project Area…. Area Impact.

Télécharger la présentation

South Maple Street Sanitary & Storm Sewer System Improvements Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. South Maple Street Sanitary & Storm Sewer System Improvements Project October 14, 2014

  2. Project Area. . . • 400 block South Maple Street • 12 & 24 College Street • 200 block Boone Avenue (east side of Boone) • 101 & 117 Belmont Avenue

  3. Project Area…..

  4. Project Area…..

  5. Area Impact . . . • 27 +/- Residences and Properties

  6. Project Disruptions…. • Road Closures / Detours • Noise • Dust • No expected customer sewer service impacts • Construction in back yards • Closure of alley way during construction period

  7. Project Purpose… • US EPA Consent Decree (Not a defined project) • Inflow / Infiltration Reduction • Eliminates any combined sewer connections • Eliminates “Private” Sanitary Sewer Service connections; Publicly owned and maintained • Reduces Public Health Risks • Reduces amount and time period of Storm Water in back yards and alley*

  8. Scope of Work for Maple Street Project… • 741 ft. of 8-inch sanitary sewer • 750ft. of 6-inch sanitary sewer • Six (6) sanitary sewer manholes • 1,740ft. of storm sewer pipe 24” - 12” • 13 storm sewer boxes and other structures • Other necessary construction activities

  9. Maple Street Project Costs . . .

  10. Maple Street Project Funding… • Winchester Municipal Utilities Private Sewer and Main Replacement Funds - Sanitary Sewer Portion of Work • City of Winchester General Fund - Storm Sewer Portion of Work

  11. Maple Street Project Schedule(Anticipated)

  12. Easements…

  13. Summary… • Eliminate combined sanitary sewer and storm connections (if any) • Eliminate “Private” sanitary sewer connections • Reduce amount and time period of storm water on private property • Reduce public health risks

  14. Key Contacts…. Winchester Municipal Utilities City of Winchester 150 North Main Street 32 Wall Street PO Box 4177 PO Box 40 Winchester, KY 40392-4177 Winchester, KY 40392-0040 Phone: (859) 744-5434 (859) 744-2821 Fax: (859) 745-4146 (859) 745-4590

More Related