An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Successful decommissioning of a nuclear plant Evelyn HooftBart Thieren 20 june 2008

  2. Introduction • NIRAS: public institute responsible for the safe management of radioactive waste in Belgium. Has developped a coherent and central management system • Belgoprocess: industrial daughter of NIRAS, main activities are treatment and storage of radioactive waste and decommissioning of shut down nuclear installations

  3. Introduction • NIRAS is charged by the belgian State with the clean up of nuclear liabilities = task of public benefit • 1986 : site BP 1 (Eurochemic) • 1989 : site BP 2 (Ex waste department of SCK.CEN) • 1991 : installations and fission products originated from research reactors and other installations of the SCK.CEN

  4. Foto site 1

  5. Eurochemic

  6. Eurochemic • First reprocessing plant in Europe • Goal • Research and development in the field of reprocessing spent fuel originated from nuclear reactors • Construction of a pilot plant

  7. Reprocessing ? • Definition: Reprocessing = recycling • Spent fuel (nuclear fuel) can be recycled • 97% of the material can be reused for electricity production (U and Pu) • 3% is waste and is vitrified, interim stored awaiting for disposal.

  8. History of Eurochemic • 1957 Constitution of Eurochemic • 1960 Start construction • 1966 Start up and active operation • 1974 Shutdown • 1978 Take-over by the Belgian State with the intention to continue reprocessing • 1984 Constitution of Belgoprocess • 1985 Belgoprocess takes over the personnel

  9. History of Eurochemic • 1986 Decision to end reprocessing in Belgium  Transfer actions to NIRAS • 1987 Start decommissioning studies • 1989 Start decommissioning pilot project • 1990 Start decommissioning Eurochemic • 2008 Start conventional demolition

  10. Pilot project • Decommissioning of two smaller buildings for endproducts originated from reprocessing • To demonstrate that decommissioning is feasible • To demonstrate that costs can be managed • To develop and optimise dismantling techniques • To train personnel

  11. Before and after

  12. Main lessons learned • Emphasis should be put on: • Decontamination of metal components • Automation of concrete decontamin-ation

  13. Clean-up of Eurochemic

  14. Clean-up of Eurochemic • Main data • Length 90 m, width 27 m, height 27 m • Volume: 56.000 m³ • Concrete volume: 12.500 m³ • Concrete surface: 55.000 m² • Metal: 1.500 ton • 7 levels, 40 main cells • 106 cell structures

  15. Clean-up of Eurochemic • Radiological status in 1981 • Contamination level up to 200 Bq/cm² (alpha) and 125 Bq/cm² (beta) • Sometimes contamination in depth • Hot spots up to several mSv/h • No activation

  16. Used techniques • Removal of metal components • Decontamination of concrete surfaces • Removal of contamination in depth • Removal of pipe penetrations • Techniques for working on heights

  17. Removal of metal components

  18. Removal of metal components

  19. Decontamination of concrete surfaces

  20. Decontamination of floor

  21. Removal of contamina-tion in depth

  22. Removal of pipe penetrations

  23. Working at height

  24. Working at height

  25. To decontaminate • Main streams • Metal • Concrete

  26. To decontaminate • Main streams • Metal 1.494 ton • Concrete 2.913 ton (incl. barytes blocs) (period 1988 – 2007)

  27. Metal decontamination

  28. Before and after

  29. Concrete sampling

  30. Clearance measures • 100 % surface measurement • Taking samples and analyses • Procedure is representative and approved by the department of fysical control • Control organism (Bel-V) subsidiary of FANC

  31. Clearance measurement

  32. Safety • Top priority for Belgoprocess • Radiation dose • Contamination risque • Conventional safety

  33. Safety • Top priority for Belgoprocess • Radiation dose (average < 2 mSv/year.person over 1990-2007) • Contamination risque (Protective clothes including full-face mask) • Conventional safety • Circumstances as on a construction warf • Vibration stress

  34. Protective clothes

  35. Protective clothes

  36. Isolation of a module

  37. Demolition • Method

  38. Result: • Production streams • Men-hours • Budget • Planning

  39. Result: production DECOMMISSIONING & CONTAMINATED MATERIAL & & & UNCONTAMINATED MATERIAL DECONTAMINATION OF MATERIALS RADIOACTIVE WASTE & & & & RECYCLING WASTE PROCESSING

  40. Result: production 4.588 t DECOMMISSIONING (31/12/2007) & 2.501 t CONTAMINATED MATERIAL 1.530 t 557 t & & & 2.356 t 145 t UNCONTAMINATED MATERIAL DECONTAMINATION OF MATERIALS RADIOACTIVE WASTE & & & & 2.913 t 63% 1.675 t RECYCLING WASTE PROCESSING

  41. Result: production 4.588 t DECOMMISSIONING (31/12/2008) +9.552 t & 2.501 t CONTAMINATED MATERIAL 1.530 t 557 t & & & 2.356 t 145 t UNCONTAMINATED MATERIAL DECONTAMINATION OF MATERIALS RADIOACTIVE WASTE & & & & 2.913 t 63% -> 88% 1.675 t +9.552 t RECYCLING WASTE PROCESSING

  42. Result: men-hours • Initial estimation: 403 man-year • Current estimation: 600 man-year • Difference explained by: • Decontamination until clearance • Differences with the initial inventory • Labour-intensive clearance measurements and procedures

  43. Result: budget Forced decontamination till clearance Less treatment, interim storage and disposal End result remains equal

  44. Result: planning • Conventional demolition • East part: september 2008 • Central part: einde 2010 • West part : einde 2012 • Distribution of water, air, steam,.. for neighbouring buildings remains

  45. Result: planning 2008 2010 2012

  46. Ambitions • Safety • Environment • Socio-economical • Exploitation of the disposal site for category-A waste • International partner

  47. Conclusion • Start of the conventional demolition of Eurochemic • In 2012 completely demolished • Cleaned-up historical heritage • Know-how to recycle >90% Belgoprocess and NIRAS decommission succesfully a nuclear plant

  48. More information • Websites • Eurochemic www.eurochemic.be • Belgoprocess www.belgoprocess.be • NIRAS www.nirond.be