Recommendations. General Change work hour for supervisors to start 30 minutes per shift – Impact 1 hour / day Command gains 400 MH per day . Note: for shops with 2 shifts the supervisor will have 1 hour of OT / day. Safety

toki
Télécharger la présentation

Recommendations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Recommendations General • Change work hour for supervisors to start 30 minutes per shift – Impact 1 hour / day Command gains 400 MH per day. Note: for shops with 2 shifts the supervisor will have 1 hour of OT / day. Safety • Safety should be responsible for conducting and resolving mishaps and reports – Impact 2 hours / mishap

  2. Recommendations WAF Process • Planner should list system tag outs in the initial conditions block of the AWR or FWP – Impact 1 to 3 days routing time • Get customer involved in process by showing urgency of opening AWR/CWPs and WAFs – Impact – Save tracking / interruptions

  3. Recommendations Work Packages • AWR and WAF should be sent electronically to save routing time as well as to perfect AWR / WAF • Work packaging to attend shops production meetings – Impact .5 hours to 1 hour / day

  4. Recommendations Planning • Code 400 should be over work package control and writing and AWRs and WAFs • Planners need to provide direction for assist needs in AWR – Impact .5 hours / day • All job requests (green hornets) should go through planning if material determination / requirements are necessary – Impact .5 hours / day • Planner feedback and evaluation done by GF, Supervisor as well as Code 400

  5. Recommendations Status Information • One production meeting held at 0630 to communicate work plan for the next 24 hours with Refit Manager expediting / coordinator to meet goals for the next day and data sent electronically. • PSR should be updated and real-time available • Better planning among General Foreman contingent on early production meeting

  6. Recommendations Timeline Schedule • Refit Manager or Zone Managers should write all time lines with shop input – Impact 2 to 3 hours / week • Refit Manager assumes responsibility to provide real-time communicate coordinating trades. Impact 1 hour / day

  7. Recommendations Systems IT • Barcoding for time keeping, training, and tracking work packages – Impact 30 minutes / day • For changes to instructions include synopsis of change in e-email or change – Impact 2 hours / week • Establish a universal password to eliminate multiple passwords –Impact .5 hours / week

  8. Recommendations Training • Do not require 1 hour shop level training each week – do training as required. – Impact 2 hours / month • A training leader billet assigned to larger groups – Impact 6 hours / week • Lessons plan made by 367 for all use and supervisor performs training – Impact 4 hours / week • Establish central location for approved lesson plan – Impact 2 hours / week