1 / 8

CIM Integration Update

CIM Integration Update. Linda Clarke David Hackett Murray Nixon. CIM integration continues to be a major challenge for ERCOT. CIM integration is a critical dependency for Nodal Go-Live Challenges for CIM integration include:

trilby
Télécharger la présentation

CIM Integration Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CIM Integration Update Linda Clarke David Hackett Murray Nixon TPTF

  2. CIM integration continues to be a major challenge for ERCOT • CIM integration is a critical dependency for Nodal Go-Live • Challenges for CIM integration include: • Stabilization of CIM schema and addition of extensions as required by EMS and MMS • Finalization (capture, clean up, validation) of CIM data from multiple sources • Coordination of solution across several project teams and several vendors TPTF

  3. Single Entry Model and CIM integration are tightly coupled TPTF

  4. We are closing on CIM Schema changes • Schema • Currently on version 1.16 of CIM Schema • CIM Data • Multiple data sources identified (i.e., Siebel, Registration, Zonal Model seed) • Identifying and resolving issues with data sets • Market Participant support required to clean up RARF data • MMS • All MMS extensions have been incorporated in V 1.16 of schema (except changes for defect fixes) • Approach to generate test data for V1.16 finalized • EMS • Anticipating few more iterations with AREVA for schema • Extent of work will be known once AREVA CIM importer Pre-FAT is complete TPTF

  5. Status of NMMS readiness • EDS 2 Release 4 complete • NMMS software ready for SEM Go-live • NMMS team actively involved in CIM schema finalization and schema data population and validation • Determining need for one additional schema release prior to SEM Go-Live TPTF

  6. Status of MMS CIM importer • MMS CIM importer functioning on V 1.08 of CIM schema • Currently testing MMS with V 1.12 of CIM schema at ABB • Refactoring of CIM importer will commence after valid test data set delivered for V1.16 of CIM • Cannot re-start EDS 4 activities without testing applications on MMS4 using CIM dataset. • Cannot complete EDS 4 or start 168-Hour Test before MMS regression test is complete using final CIM schema and dataset TPTF

  7. Status of EMS CIM importer • EMS CIM importer FAT delayed further • EMS CIM importer Pre-FAT assessment scheduled for week of June 09, 2008 • CIM importer Pre-FAT on V 1.16 of schema • Potential to see further issues with CIM schema and data once Pre-FAT begins • Stage 1 Network Model data validation for Single-Entry Model Go-Live will not start before EMS CIM importer FAT is complete • LFC 8,48 hour tests will re-commence only after data validation is complete The above dates are vendor committed dates TPTF

  8. To summarize.. • Market Participant support is required for RARF data clean up – Dana Showalter will be working with MPs to ensure quality of RARFs • Stage 1 CIM Validation - Data Consistency cannot start until EMS CIM importer FAT is complete and comprehensive data set is available from GENESYS, RARFs and other sources • Data consistency is critical for Single Entry Model Go-Live and subsequently Nodal Go-Live • New target date for Single Entry Model Go-Live will be announced when Nodal integrated schedule is complete • Each of the activities and their dependencies will be incorporated into the Integrated Nodal Program Plan TPTF

More Related