1 / 36

NEPOOL Participant’s Meeting Boston, MA April 2, 2004

NEPOOL Participant’s Meeting Boston, MA April 2, 2004. Stephen G. Whitley Senior Vice President & COO. Agenda. System Operations Market Operations Electric and Gas Wholesale Initiative Back-Up Detail. System Operations. Operations Highlights. Boston & Hartford Weather Pattern:

zasha
Télécharger la présentation

NEPOOL Participant’s Meeting Boston, MA April 2, 2004

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NEPOOL Participant’s Meeting Boston, MA April 2, 2004 Stephen G. Whitley Senior Vice President & COO

  2. Agenda • System Operations • Market Operations • Electric and Gas Wholesale Initiative • Back-Up Detail

  3. System Operations

  4. Operations Highlights • Boston & Hartford Weather Pattern: • March 2004 had near normal or above normal temperatures. The precipitation was below normal, ending on a wet note. Snow fall in the Boston area was above normal; the Hartford area was below normal. • Peak load of 19,233 MW at 19:00 hours on March 16, 2004. • During March: • NPCC Shared Activation of Reserve Events: • March 6 L/O Millstone Point #2 @897 MW • March 13 L/O Bruce #4 @760 MW • March 15 L/O Millstone Point #2 @900 MW • No Fuel Delivery Issues

  5. Market Operations

  6. Day–Ahead & Real-Time Prices, ISO Hub

  7. Congestion Component Congestion Component LMP LMP Marginal Loss Component Marginal Loss Component Day-Ahead–LMP Average by Zone & Hub March 1, 2004 to March 23, 2004 (1.87) (-1.26) (0.36) (0.11) (-1.68) (-1.21) (-2.92) (-8.07)

  8. Congestion Component Congestion Component LMP LMP Marginal Loss Component Marginal Loss Component Real-Time-LMP Average by Zone & Hub March 1, 2004 to March 23, 2004 97.4% (0.80) (-2.00) (0.08) (-1.12) (0.13) (-1.63) (-2.80) (-6.66)

  9. Day - Ahead Market vs. Forecast Load

  10. Day - Ahead LMP

  11. Real - Time LMP

  12. Settlement Data – Real - Time & Balancing Market Percentage of Real-Time Load Fully Hedged Through ISO-NE Settlement System* 80% 77% 75% 75% 75% 75% 73% 73% 73% 73% 72% 73% 72% 73% 71% 71% 71% 71% 70% 70% 71% 66% 65% % RT Load Fully Hedged 60% 55% 50% Jul-03 Jan-03 Jun-03 Jan-04 Apr-03 Nov-02 Nov-03 Feb-03 Mar-03 Feb-04 Mar-04 Oct-02 Oct-03 Dec-02 Sep-03 Dec-03 Aug-03 May-03 Oct-01 - Sep-02 Average Month NOTE: REPRESENTS MARCH 1 - 24, 2004 DATA * Post-SMD data ignores intra-pool LMP differences

  13. Electric and Gas Wholesale Initiative

  14. Electric and Gas Wholesale Initiative • In response to the January 2004 Cold Snap, TEAC’s Fuel Diversity Working Group is charged with the Electric and Gas Wholesale Initiative Project. • High priority issue with N.E. Governors • Workshop #1 – March 19th – Springfield Sheraton • Wide set of Stakeholders • Joint NEPOOL/ISO-NE Cold Snap Task Force • Many problems and key issues identified • Physical, operational, communications, training • Next Meeting – April 12th – Wyndham, Westboro

  15. Electric and Gas Wholesale Initiative • Joint NEPOOL/ISO-NE Cold Snap Task Force • Broad membership: regulatory, electric & gas stakeholders • Non-voting technical & policy advisory group • Developed Mission Statement & Charter • Assess & propose improvements to existing NEPOOL markets, rules & procedures • Collaborate with gas industry for possible changes to practices & procedures • Provide input to potential changes in regional energy policy, laws or regulations to improve electric & gas market reliability and efficiency • Coordinate resolution thru NEPOOL Committee process

  16. Electric and Gas Wholesale Initiative • Timeline • Fully define the problem & key issues - April • Release draft ISO-NE Cold Snap Report - April • Prioritize issues & brainstorm solution sets - May • Present range of solutions w/stakeholders - May • Finalize set of recommendations - June • 30 day public comment period - July • Publish final ISO-NE Cold Snap Report - August • FERC Filings - August • Implement changes - Fall 2004 • Regular interaction with NEGC PPC and regulatory agencies

  17. Back-Up Detail

  18. CT/SWCT

  19. SWCT Transmission • Phase I • Received conditional approval from Connecticut Siting Council 2/11/04 • Phase II • Town hearings completed • “Need” hearings completed • “Underground Technology” segments – May • “Overhead” segments and “East Shore” – May

  20. Demand Response

  21. Demand Response(as of March 29, 2004)

  22. Demand Response(as of March 29, 2004) * SWCT assets are included in CT values and are not included in Total

  23. Northwest Vermont

  24. NWVT Reliability Project Update • State hearing process continues • Technical Hearings complete • Discovery on 115kV line relocations underway, hearings by mid-June • Rebuttal phase delayed until end of July • Decision expected by mid October

  25. New Generation

  26. New Generation Update • No new resources were added in March. • Approximately 400 MW expected on line by the end of the year. • Status of Generation Projects as of March 29, 2004: No.MW In Construction 3 289 with 18.4 approval Not in Construction 7 1,506 with 18.4 Approval

  27. RTEP

  28. RTEP Update • TEAC21 tentatively scheduled for April • RTEP04 to include enhancements to RTEP03 including • Fuel Diversity • Clearer definition of system needs • Interim NEPOOL Project Listing to be updated in April • Many projects have advanced • 5 new projects • 9 cancelled projects • 10 advanced to Planned stage with 18.4 approval • 12 commenced construction • 17 placed in service • 2nd New Brunswick Tie to be changed from Elective to Reliability Project • Project is under review to identify the most effective alternatives • Cost will be subject to 12C review

  29. RTEP Projects Update - NEMA

  30. RTEP Projects Update - SWCT

  31. Compliance

  32. Compliance Update • A4: Maintenance for Bulk Power System Protection • Required response to 2004 ISO-NE survey by 1/5/04 • Level 2 sanctions will apply to three Participants for failure to respond on time. • Six Participants that have not completed their 2003 required maintenance must become compliant by May 31, 2004.

  33. Compliance Update (cont.) • A3: Generator Underfrequency Tripping • All Participants responded to the 2003 ISO-NE Survey by 12/1/03 • Six Participants are non-compliant • Two are exempt • Four have plans for compliance • 2004 Surveys on UFLS and UF generator trip settings were sent out on March 15 and are due May 3.

  34. Sanctions • Level 1 – Letter from Director SP to the relevant functional head (operations, planning) of the Industry Participant with copy to NCWG • Level 2 – Letter from COO to the Chief Executive of the Industry Participant with copy to the relevant functional head, other NEPOOL Participants (the NEPOOL Task Forces, RC, NPC) and NPCC • Level 3 – Letter from the CEO to the Board of Directors of the Industry Participant with copies to Level recipients. Post on the ISO-NE Compliance Website. • Level 4 – same as Level 3 with copies to the appropriate State/Provincial regulatory agencies, FERC, DOE, State Governor and Legislators.

  35. Summer 2004 Capacity Assessment

  36. Summer 2004 Capacity Assessment

More Related