1 / 12

Procurement including order processing

Procurement including order processing. G.K.Bhoi Dy. Manager (CS),Itarsi. Purpose.

zulema
Télécharger la présentation

Procurement including order processing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Procurement including order processing G.K.Bhoi Dy. Manager (CS),Itarsi

  2. Purpose The Works and Procurement Policy and Procedure document (hereinafter referred to as the ‘WP Policy and Procedure') provides guidelines to expedite decision making process in POWERGRID by consolidating, simplifying and streamlining the various steps to be followed in the process of award of contracts for procurement of goods, works & services as well as during its implementation on the ground. POWERGRID-CS-ITARSI

  3. The intent of the document is also to make the policies and procedures more systematic, transparent and easy to administer with major thrust on expeditious and decentralized decision making, accountability & responsibility, during different stages of processing of award of contracts including its implementation on the ground. POWERGRID-CS-ITARSI

  4. Primary Considerations While undertaking the actions towards award of Contracts and its implementation on the ground, the same shall be generally guided by the following primary considerations: (a) To make available the needed goods, equipment, material, works and services in the right quality and quantity, at the right time and at the right price after giving fair and equal chance to tenderers/ bidders, so as to obtain the optimum value for each unit of expenditure. (b) Economy and efficiency in implementation of the project procurement of goods, works and services in question. (c) To provide an opportunity to all eligible qualified bidders to compete for providing goods, works and services. POWERGRID-CS-ITARSI

  5. (d) To encourage the development manufacturing industries/ agencies. (e) Transparency in the procurement process and timely actions. • Thus It should be kept in mind that all actions towards award of Contracts and its implementation on the ground have to be fair, consistent, transparent and based on highest standard of ethics. • The requirements and objectives can be best realized in an efficient and effective manner through the WP Policy and Procedure which have been elaborated under Pre-Award (covered in this volume i.e., Vol.-I) and Post-Award • (covered in Vol.-II). POWERGRID-CS-ITARSI

  6. PRE-AWARD ACTIVITIES • Approval of Project concept by ED(Engg.) • Advice to Region for walk-over survey by SEF • (System Engineering and Feasibility) • Advice to Region for Preliminary Survey by SEF • 4 Advance Expenditure Sanction for Preliminary • Survey, Press Notifications, etc. • In-principle approval of the project/scheme by CEA (Internal Zero Date) • Input from region for FR based on walk-over survey POWERGRID-CS-ITARSI

  7. 7. Preparation of FR (feasibility report) • 8. Internal approval of FR by CMD • Finalisation and approval of Package List • Techno Economic Clearance of CEA(Central electricity authority)/ FR clearance by Sub-Committee of POWERGRID Board. • 11 Input from region for BOQ and NIT cost estimate • based on preliminary survey • Finalisation of BOQ for NIT Cost Estimate POWERGRID-CS-ITARSI

  8. 13 Preparation and approval of NIT cost estimate • 14 Preparation of following sections/ part of bidding • documents including approval thereof from • Management, wherever required: • (a) Qualifying Requirements • (b) Technical Specifications • (c) Bill of Quantity (BOQ) • (d) Data Requirement Sheets and other technical • documents • (e) GCC. • Bid Proposal Sheets (BPS), SCC etc • 15 Compilation and preparation of complete set of • bidding documents • 16 Approval for calling of tenders i.e. approval of NIT • Proposal. POWERGRID-CS-ITARSI

  9. Issuance of NIT i.e. publication of NIT in newspaper • Period for sale of Bidding Documents( 45days) • Submission of bids (both envelopes) & Opening of 1st envelope (7 days after close of sale of bidding documents) • 20 Examination of 1st envelope, seeking clarification, if required, and submission of recommendation by tender committee. • Approval for opening of 2nd envelope in respect of qualified bidders only • Opening of 2nd envelope POWERGRID-CS-ITARSI

  10. 23 Evaluation of techno-commercial & price bids by tender committee and submission of evaluation report with recommendations to Management (within 4 weeks of bid opening) 24 Approval of recommendations for award of Contract by POWERGRID Management 25 Post bid discussions/ negotiations with bidder and its approval 26 Placement of LOA after vetting by Finance,Engineering and QA&I POWERGRID-CS-ITARSI

  11. CHECK LIST FOR PROPOSAL/NIT/LOA • FOR PROPOSAL POWERGRID-CS-ITARSI

  12. 2. FOR NIT / LOA POWERGRID-CS-ITARSI

More Related