An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Seawall Meeting Saturday, July 24, 2010

  2. Welcome! • Introductions • Committee Chairman: Gov. Rick Myers • ME Engineering : David Walker • From ODNR: Chuck Wadley • Advisory committee: Girard Besanceney

  3. The Project • Evaluation and Planning • Engineering and Design • Construction

  4. Evaluation & Planning • Shirk and O’Donovan • Evaluate existing conditions • Determine need • Devise plan

  5. Engineering and Design • ME Engineering • Design and Specifications • Estimate costs • Solicit bids from contractors • Evaluate bids and recommend contractor

  6. Construction • Phase I • the “L” wharf • Phase II • the “T” wharf • Phase III • the island & bridge

  7. Financing • Cost of project • Estimated at this time • Based on engineering and informal talks with contractors • Cost of funds • Recommendations of advisory committee • Discussion with banks

  8. Cost of project • Estimated (maximum amounts) • Phase I $367,200 • Phase II $312,840 • Phase III $125,460 • Total $805,500 • Phase in over time

  9. Cost of Funds • Advisory committee recommendations • Sell rental houses • Apply funds raised to principle • Temporary capital assessment • Incentive for members

  10. Cost of Funds • Discussion with banks • Funds are available • Recommend selling houses • Demonstrate member willingness to accept assessment

  11. Cost of funds • Interest only on the first year of each phase • Current rates: prime + 0.5% • Today: 3.75% • Can lock in fixed rate at our option

  12. The big question • WHAT WILL IT COST ME???? • Using current maximum cost estimates and 5% rate (today is 3.75%)… • $150.00 per member per year • Temporary.. Earmarked to Seawall • This would retire debt in 17 years

  13. Member resistance -vs_ Support • Current bill : Proposed: • Dues 675 -Dues 675 • Capital 100 -Capital 250 • ILYA 1 -ILYA 1 • Tax 54 -tax 65 • Total 830 -Total 992

  14. Current Issues • Presently being discussed by board • How to get the $150 • 1- increase capital contribution • 2- spread cost among dues and rentals • 3- combination of 1 and 2 above

  15. Current Issues • Presently being discussed by board • Member incentive • Bring a new member, your $150 is waived • Lump sum payment • Pay principle only, reduce payback time • Donations • Fund raisers • Commodore association • Auxillary