An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CASS, MarsfieldPhil Diamond4 October 2011 SKA Pre-Construction Phase: Where we are, and what we’re trying to achieve?

  2. Outcomes from recent SKA Founding Board • Met at LHR on 29 September • FB appointments: • Michiel van Haarlem (ASTRON) Exec Officer until legal entity est. • Select Interim Director by 1 November • Proceed with appointment of D-G, but will not appoint until after site decision • Site Selection Advisory Cmte: • Evaluation plan approved • Legal Entity: • Incorporation by mid-November 2011 • Members, at minimum: UK, NL, IT, AU, NZ, RSA, CA, China • Resourcing: • Committed cash for SPO < required (16.6MEuro vs. 27.5MEuro) • Enough for Year 1 plan • Work on basis others will join and funding will ramp up • Business Plan group draft a revised plan to reflect expected growth in membership

  3. Outcomes from recent SKA Founding Board • SPO Building: • To be located at Jodrell Bank • Planning application to be submitted on 14 Oct • Contractor appointed by 31 Jan 2012

  4. PEP Overview CSIRO: PEP

  5. Stage 1 engineering work in the Pre-Construction PhaseSPDOFB meeting, 29 September 2011

  6. Context for Pre-Construction Phase PEP Stage 1 PEP Stage 2

  7. Stage 1: System and Element Work in 2012-3 SPDO/SPO Planning Science Requirements Technical Requirements 1 SRR System level Stage 1 Stage 2 Work Package definition and contracting Stage 2 Detailed Work Breakdown Structure 4 3 WPCs Apr12 Q4/12 2 Planning RFP Bid Contract Stage 1 Element Work Finish CoDRs Element SRR Element level Stage 1

  8. Conceptual Design Reviews in 2011 • 23-25 Feb System delta-CoDR on SKA1 • 14-15 Apr Signal Processing • 19-20 Apr Aperture Arrays • 28-30 Jun Signal Transport & Networks • 13-15 July Dish and Dish Arrays • 2-3 Feb CoDR Dish Verification Antenna #1 • 5-7 Oct PDR Dish Verification Antenna #1 • 9-11 Nov Monitor & Control • DecSoftware & Computing

  9. Allocation of Requirements from System to Element level System Level (SPDO/SPO) System RR • 1st allocation is science requirements, operations requirements (Instrument Requirements Review). • Later allocations are extensibility requirements and non-functional requirements. 1 Element Level (WPCs) Element SRR 2 Pre-Stage 1 Q4/12 (resource dependent) Apr/12

  10. WPC Element Work in 2012-3 Pre-Stage 1 Stage 1 Element Requirements, WBS Development and Design studies Allocated Requirements Planning CoDR => SRR Work (See next slide) Element SRR Analysis of CoDRs Verification Work

  11. Assembling Element Level RFPs for Stage 1 Work Assemble Work Package Contractor Consortia Pre-Stage 1 Planning Element 1 CoDR-SRR Work Stage 1 Element Contracts Define Top-level WBS SoWs RFPs Bid Planning Element 2 CoDR-SRR Work Planning Element N CoDR-SRR Work Develop Stage 1 Legal, Bid Policy, T&C Contract Templates Apr/12 Nov/11

  12. Pre-Stage 1 : Planning Element CoDR-SRR Work • Purpose of Work • Planning next phase – to Element SRR • What needs to be done? • Which options are to be carried forward? • How much effort? • How much time? • What is the outcome to be presented at the SRR? • Preparation of Statement of Work to reach SRR. • Contract Phases and Milestones • Familiarisation with tasks and inputs • Analysis of input data, identify gaps • 1st draft plan • Presentation and review • Decisions on how to handle gaps and missing information • Finalize plan • Final presentation, review and delivery. • Deliverables • Reports • Scope of requirements analysis for the element level. • Consolidation and recommendation of viable technical options • Architecture documents for viable options. • Outline of work to be done on requirements, and other items identified in the SEMP for the SRR level. • Identification of resources and time to complete actual work to SRR. • Preliminary estimate of work needed to complete detailed design. • Review of gaps or missing information needed to proceed. • Prepared Statement of Work for the period up to SRR.

  13. Assembling Element Level RFPs for Stage 1 Work Assemble Work Package Contractor Consortia Pre-Stage 1 Planning Element 1 CoDR-SRR Work Stage 1 Element Contracts Define Top-level WBS SoWs RFPs Bid Planning Element 2 CoDR-SRR Work Planning Element N CoDR-SRR Work Develop Stage 1 Legal, Bid Policy, T&C Contract Templates Apr/12 Nov/11

  14. Assembling Element Level RFPs for Stage 1 Work Assemble Work Package Contractor Consortia Pre-Stage 1 Planning Element 1 CoDR-SRR Work Stage 1 Element Contracts Define Top-level WBS SoWs RFPs Bid Planning Element 2 CoDR-SRR Work Planning Element N CoDR-SRR Work Develop Stage 1 Legal, Bid Policy, T&C Contract Templates Apr/12 Nov/11

  15. Resources for Planning, Requirements Development, WBS, Stage 1 work • Pre-Stage 1 Planning (Nov11-Apr12) • Assuming 5-8 Elements • 3 people/element from PrepSKA Lead Institutes => 15-24 persons for 5 months (75-120 PMs) • SPDO/SPO Domain specialists at 30% (5 persons) (8 PMs) • System Requirements Development (Nov11-Oct12) • SPO Domain specialists at 30% (5 people) (20 PMs) • Three additional System Engineers at SPO, assumed available immediately (36 PMs) • SPDO/SPO will need TBD assistance with specific tasks during the SRR preparation • Element level Requirements Development (Apr12-Mar13, PEP Table 2) • WPC s: 15 FTE/ WP on average (total: 90 FTEs)

  16. Where are we, and what are we trying to achieve? • Still at planning stages • SPDO/SPO plan for process is solidifying • Method of interaction with SPDO/SPO not yet established • Key triggers: • Appointment of Interim Director • Possibly allows formation of consortia • Site decision: • Releases funding • D-G appointed • We establish a model for Australian participation • We talk to international partners about the formation of potential consortia • We be ready to go as soon as possible.

  17. CSIRO Astronomy and Space Science Philip Diamond Chief Phone: +61 2 9372 4300 Email:phil.diamond@csiro.au Web:www.csiro.au/org/CASS Thank you Contact UsPhone: 1300 363 400 or +61 3 9545 2176Email: Enquiries@csiro.au Web: www.csiro.au