Download
slide1 n.
Skip this Video
Loading SlideShow in 5 Seconds..
Robert Kondziolka Salt River Project Manager of Transmission Planning PowerPoint Presentation
Download Presentation
Robert Kondziolka Salt River Project Manager of Transmission Planning

Robert Kondziolka Salt River Project Manager of Transmission Planning

377 Vues Download Presentation
Télécharger la présentation

Robert Kondziolka Salt River Project Manager of Transmission Planning

- - - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

  1. Arizona CorporationCommission Workshop Fourth Biennial Transmission Assessment2006 - 2015 Robert Kondziolka Salt River Project Manager of Transmission Planning June 6, 2006 Phoenix, Arizona

  2. Contingency Planning (N-1-1)For Palo Verde Transmission System Pre-2006 Summer Season • Facilities Out of Service: Fall 2005- June 1, 2006PaloVerde-Devers, Hassayampa-N.Gila, N. Gila- Imperial Valley 500kV Lines;4 Series Capacitors Banks and Westwing 500/230kV Transformer #4 Out of Service • Maximum Scheduling Generation Capacity: 6,107 MW (Will Meet the Expected Power Transfer Need)

  3. Contingency Planning (N-1-1)For Palo Verde Transmission System Pre-2006 Summer Season • Facilities Back Into Service:- After June 1, 2006PaloVerde-Devers, Hassayampa-N.Gila, N. Gila- Imperial Valley 500kV Lines;4 Series Capacitors Banks and Westwing 500/230kV Transformer #4 Back into Service • Maximum Scheduling Generation Capacity: 7,457 MW (Will Adequately Meet Power Transfer Requirement)*