1 / 20

Hydraulic Analysis Pumping Costs for PVC and Ductile Iron Pipe

This paper addresses the inaccurate hydraulic claims made by the Ductile Iron Pipe Research Association (DIPRA) and<br>shows that when industry-accepted data are used, PVC pipe is more energy efficient, cost effective, and sustainable than<br>ductile iron (DI) pipe. DIPRA maintains that DI pipe has lower pumping costs than PVC pipe. The claim is that DIu2019s larger<br>inside diameters (ID) offset PVCu2019s better flow characteristics. However, DIPRAu2019s brochures and on-line calculator contain<br>misleading information and erroneous hydraulic assumptions, generating biased results.

Manish77
Télécharger la présentation

Hydraulic Analysis Pumping Costs for PVC and Ductile Iron Pipe

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INSTALLATIONGUIDEFOR SOLID-WALL PVCSEWERPIPE

  2. SEWERPIPE TABLEOFCONTENTS Introduction............................................................................................................................................................3 Receiving................................................................................................................................................................4 UnloadingandHandling......................................................................................................................................5-6 Storage...................................................................................................................................................................7 Trenching................................................................................................................................................................8 De-Watering...........................................................................................................................................................9 FieldCutting.........................................................................................................................................................10 LoweringPipeintotheTrench..............................................................................................................................11 CleaningandInspection.......................................................................................................................................12 Lubrication............................................................................................................................................................12 JointAssembly......................................................................................................................................................13 TrenchConstruction.............................................................................................................................................14 Foundation...........................................................................................................................................................14 Bedding................................................................................................................................................................15 Haunching............................................................................................................................................................15 InitialBackfill........................................................................................................................................................16 FinalBackfill..........................................................................................................................................................17 AcceptanceTesting...............................................................................................................................................17 SpecialConsiderations....................................................................................................................................17-18 Checklist...............................................................................................................................................................19 Uni-BellLiterature................................................................................................................................................19 2 UNI-BELLPVCPIPEASSOCIATIONWWW.UNI-BELL.ORG

  3. SEWERPIPE • INTRODUCTION • ThisdocumenthasbeendevelopedbytheUni-BellPVCPipeAssociationforuseasafieldinstallationguide. Generalinformationregardingthecorrectinstallationofgasketed-jointsolid-wallPVCsewerpipeisincluded. Relevantproduct standardsare: • ASTMD3034“StandardSpecificationforTypePSMPoly(VinylChloride)(PVC)SewerPipeandFittings” • ASTMF679“StandardSpecificationforPoly(VinylChloride)(PVC)Large-DiameterPlasticGravitySewerPipe andFittings” • Formoredetailedtechnicalinformationandforinformationonprofile-wallPVCpipes,consultthepipe manufacturerorrefertoASTMD2321,“StandardPracticeforUndergroundInstallationofThermoplasticPipe forSewersandOtherGravity-FlowApplications..”TheHandbookofPVCPipe:DesignandConstructionprovides additionalguidanceonPVCpipedesignandinstallation.Forinformationonthispublication,pleasecontactUni- Bell. • TheUni-BellPVCPipeAssociation,formedin1971,fundsPVCpiperesearchanddevelopment,providestechnical serviceandsupport,developsrecommendedstandards,andpromotesproperuseofPVCpipewithgasketed joints. • Uni-BellmembersaremanufacturerswhoarededicatedtoproducinghighqualityPVCpipeproductsforthe • industry. • ThestatementscontainedinthisinstallationguidearethoseoftheUni-BellPVCPipeAssociationandarenot warranties,noraretheyintendedtobewarranties.Inquiriesforinformationonspecificproducts,theirattributes andrecommendeduses,andthemanufacturer’swarrantyshouldbedirectedtomembercompanies. 3 INSTALLATIONGUIDEFORSOLID-WALLPVCSEWERPIPE

  4. SEWERPIPE RECEIVING Whenaloadofpipearrivesatthejobsite,itisyourresponsibilitytocheckitthoroughly.Ifpossible,inspecteach piecefordamage.Checkquantitiesagainsttheshippinglist.Notethatthepolicyofmostpipemanufacturers isthatoncethepipeleavesthemanufacturer’splant,itbecomesthepropertyoftheshippingcompany.Any damagedormissingitemsshouldbedocumentedonthebilloflading.Setasideanydamageditemsand notify the shipper. 4 UNI-BELLPVCPIPEASSOCIATION WWW.UNI-BELL.ORG

  5. SEWERPIPE • UNLOADINGANDHANDLING • Itisalsoyourresponsibilitytounloadtheshipment.UNLOADWITHREASONABLECARE.Carelessunloadingcan • resultindamagedproductor personalinjury. • Useaforkliftorafront-endloaderwithforkattachment,ifavailable.Makesurethattheforksaresufficiently longtosupportthebundles.Whenunloadingbyhand,removeonepieceatatimeandblocktheshipmentto keeppipefromrollingoffthetruck. • Observethefollowingprecautions: • DONOTdroppipeoffthetruck. • DONOTinsertaforkliftforkintoapipeendtotransport. • Lowerthepipeintotheditch.DONOTdrop. 5 INSTALLATIONGUIDEFORSOLID-WALLPVCSEWERPIPE

  6. SEWERPIPE Thetablesbelowareprovidedforuseasguidesinselectionofhandlingequipment: APPROXIMATEWEIGHTOFPIPELENGTHS(lbs) 6 UNI-BELLPVCPIPEASSOCIATIONWWW.UNI-BELL.ORG

  7. SEWERPIPE STORAGE Ifyoucanunloadtheshipmentinunitpackages,thepipewillbeeasiertostore.Stackthepackagesonreasonably levelground.Ifyouunloadonepieceatatime,placethepipebeveltobell.Neverstackovereightfeetinheight. Donotstackthepipenexttoheatsourcesorengineexhausts. Gaskets shouldalsobeprotectedfromheat,oil, andgrease. 7 INSTALLATIONGUIDEFORSOLID-WALLPVCSEWERPIPE

  8. SEWERPIPE TRENCHING Donotlettheexcavatedmaterialblocksidewalks,drives,orutilityoutlets.Followallsafetyrulesandregulations. Protectworkersbyusingsheetingandtrenchboxesinhazardousareasandbyslopingthetrenchwallsindry soils.Whensheetingoratrenchboxismoved,makesurethatthepipeisnotmovedandthattheside-support materialisnot disturbed. 8 UNI-BELLPVCPIPEASSOCIATION WWW.UNI-BELL.ORG

  9. SEWERPIPE DE-WATERING Dokeepthetrenchasdryaspossibleuntilthepipehasbeeninstalledandenoughbackfillplacedtoprevent thepipefromfloating.PVCpipewillfloatifnotfilledwithwaterorweighteddown.Theheightofloosebackfill materialrequiredtopreventflotationofemptypipeisconservativelyequalto1½timesthepipediameter. 9 INSTALLATIONGUIDEFORSOLID-WALLPVCSEWERPIPE

  10. SEWERPIPE FIELDCUTTING PVCpipecanbeeasilycutwithapowerhandsaworpower-drivenabrasivedisc.Besureyoumakeasquarecut. Beveltheendwithabevelingtool,woodrasp,orpowersandertothesameangleandlengthasprovidedonthe factory-finishedpipe. Redrawtheinsertion lineonthespigotusinga factory-markedspigotasa guide. 10 UNI-BELLPVCPIPEASSOCIATIONWWW.UNI-BELL.ORG

  11. SEWERPIPE LOWERINGPIPEINTOTHETRENCH Placethepipeandfittingsintothetrenchusingropesandskids,slingsonthebackhoebucket,orbyhand.Do notthrow the pipe or fittings into thetrench or allowany part of thepipeto take anunrestrained fall ontothe trenchbottom.Atthispoint,thepipeandotheraccessoriesareinagoodpositionforfinalinspection.Ensure therearenodamagedmaterialsbeforeassemblybegins. 11 INSTALLATIONGUIDEFORSOLID-WALLPVCSEWERPIPE

  12. SEWERPIPE CLEANINGANDINSPECTION Removeanymud,sand,orotherforeignmaterialfromthebellinteriorandspigotexteriorthatcouldpreventan effective sealbetweenthebellandspigot.Carefully cleanthegasketarea.Donotremovethegasketfromthe bell.Makesurethegasketisseateduniformlyinthegroovebyrunningyourfingeraroundtheinneredgeof the gasket. LUBRICATION Lubricantshouldbeappliedinaccordancewiththepipemanufacturer’sinstructions.Useonlythelubricants suppliedor recommendedbythepipe manufacturer. 12 UNI-BELLPVCPIPEASSOCIATIONWWW.UNI-BELL.ORG

  13. SEWERPIPE • JOINTASSEMBLY • Pushthelubricatedspigotendpastthegasketintothebelluntiltheinsertionlineonthespigotisevenwiththe edgeofthebell.DONOTOVERINSERT. • Ifyouhavetroublewithassembly,disassemblethejointandexaminethegasket.Ifthegasketisremovable, replaceifdamaged.Ifnon-removablegasketsaredamaged,cutoffthebell,bevelthenewedge,andusea couplingtoassemble.Besurethatthegasketisproperlyseatedandthatbothpipelengthsareinstraight alignment.Repeatassembly stepsabove.Correctassemblyisachievedwhentheinsertionlineonthespigotis linedupwiththeedgeofthebell.Ifmultipleinsertionlinesexist,insertuntilonlyonelineisvisible. • Thebar-and-blockmethodofjointassemblyisrecommended,astheinstallerisabletofeeltheamountofforce beingusedandwhetherthejointgoestogethersmoothly.Largerpipemayrequiremechanicalassistanceto applysufficientforcetoassemblethejoint. • Whenmechanicaldevicesareused,caremustbetakentoensurethatthespigotisinsertedtotheproper depthandthatpreviouslyassembledpipejointsarenotdisturbed.Thisisaccomplishedbyinsertingonlyto theinsertionlineonthespigotend.Ifthespigotisover-inserted,backthepipeoutuntiltheinsertionlineis visible.Inallcases,straightalignmentofthepipeisessentialforproperassembly.Ifthepipeismisaligned,over- inserted,orassembledwithexcessiveforce,thefollowingarepossibleconsequences: • rolledgaskets • failuretopassacceptancetesting(e.g.,low-pressureairtestinganddeflection-mandreltesting) • over-insertionofpreviously assembled joints ManualBar-and-Block Method 13 INSTALLATIONGUIDEFORSOLID-WALLPVCSEWERPIPE

  14. SEWERPIPE TRENCHCONSTRUCTION Termsused in pipeinstallation are illustratedin the trench cross-section below. The use ofproper embedment materialsisveryimportanttotrouble-freeoperationofpipesystems.Theparticlesizeofmaterialincontactwith thepipeshallnot exceed1½inches. FOUNDATION Afoundationisrequiredwhenthetrenchbottomisunstable.Thebottomofthetrenchisover-excavatedand broughtbackuptogradewithsuitablematerial.Whereover-excavationoccurs,ensurethattheelevationunder theentirelengthofthepipeisbroughtup(ratherthanonlyatthebells).Properplacementofnewfoundation materialswillsupportthepipeandpreventsagging betweenjoints. 14 UNI-BELLPVCPIPEASSOCIATIONWWW.UNI-BELL.ORG

  15. SEWERPIPE BEDDING Beddingmaybeusedtobringthetrenchbottomuptogradebeforethepipeisinstalled.Itspurposeistoprovide continuousanduniformsupport.Wherebeddingisrequired,amaximumcompacteddepthof4to6inchesis typical.Holesforpipebellsshouldbeprovidedateachjointtoensureuniformsupportforthepipe.Bellholes shouldbenolargerthannecessaryforpipeassembly. HAUNCHING Placementandcompactionofthehaunchingmaterialarethemostimportantfactorsaffectingpipeperformance anddeflection.Properplacementandcompactionofmaterialinthehaunchreducevoidsandincreasepipe support.Granularmaterialsmaybeproperlyplacedusingtechniquessuchasshovelslicing.Placematerial underthehaunchesandatleasthalfwayupthepipetoprovidesidesupport.Makesurematerialisproperly compacted.DONOTDISTURBSIDESUPPORTWHENMOVINGSHEETINGORTRENCHBOX. 15 INSTALLATIONGUIDEFORSOLID-WALLPVCSEWERPIPE

  16. SEWERPIPE INITIALBACKFILL Keeptheinitialbackfillfreefromrockswhichcoulddamagethepipeduringfinalbackfill.Depthoftheinitial backfillshouldbeatleast6inchesoverthetopofthepipe.Initialbackfillprotectsthepipefromdamageduring finalbackfill.Machinecompactionofinitialbackfilldirectlyoverthepipeisnotdesirableunlessadequatecover has been provided toprotect the pipe. Adequatecover will dependon the type ofcompaction equipment. For adequatecovertopreventpipedamageordeflection,consulttheprojectengineer. 16 UNI-BELLPVCPIPEASSOCIATIONWWW.UNI-BELL.ORG

  17. SEWERPIPE • FINALBACKFILL • Finalbackfillisoften specifiedbytheprojectengineerbasedonsitedesign.Materialselection, placement,and compactionshouldmeettheprojectrequirements. • ACCEPTANCETESTING • AftertheinstalledPVCpipelineisthoroughlycleaned,oneormoreofthefollowingtestsmaybeperformed: • Visualinspection • Deflection test • Leakagetest • Visual Inspection: Sewer pipelines canbe inspected visuallyto verifyaccuracy of alignment andfreedom from debrisandobstructions.Thetestistypicallyperformedby closed-circuitTV. • DeflectionTesting:Deflectiontestingisusuallyperformed withaproperlysized“go/no-go”mandrel.Mandrel sizesfor7½%deflectionofthebaseinsidediameterarefoundintheASTMproductstandards(D3034andF679) andarealsogivenintheHandbookofPVCPipe:DesignandConstruction. • LeakageTesting:Low-pressureairtestingisanacceptablemethodofinsuringintegrityoftheinstalledsewer system.ASTMF1417“StandardTestMethodforInstallationAcceptanceofPlasticGravitySewerLinesUsingLow- PressureAir”providesproceduresforleakagetestingofplasticsewerlines.UNI-B-6 “Recommended Practicefor Low-PressureAirTestingofInstalledSewerPipe”describestestingproceduresandisavailableontheUni-Bell website.Water-infiltrationtestingisanalternativemethodwhichisaccurateonlywhenthepipeiscompletely underwater.Water-exfiltration testingisararelyusedmethodthatcanbecomplicated by entrapped air. • SPECIALCONSIDERATIONS • ChangesinDirection: • Pipebending–Somechangesin direction maybe accomplishedwithouttheuseofbends,sweeps, or other fittings.ControlledbendingwithinacceptablelimitscanbeaccommodatedbyPVCpipe.Ageneralruleof thumbfortheminimumbendingradius(Rb)calculationisRb=200OD.Tighterbendingradiimaybeachieved forcertainproducts.Consultthemanufacturerforspecificproductinformation.Inmostcases,bending should beaccomplishedmanually. Itisnotrecommended to attempt bending pipesgreater than12 inches indiameterduetotheforcesrequired. • Jointdeflection–Changesindirectionmayalsobeaccomplishedthroughjointdeflection.Allowablejoint deflectionisdependentonpipesizeandjointdesign.Jointdeflectionlimitsshouldbeobtainedfromthepipe manufacturer. 17 INSTALLATIONGUIDEFORSOLID-WALLPVCSEWERPIPE

  18. SEWERPIPE • Combinedpipebendingandjointdeflection–Eitherjointdeflectionorlongitudinalbendingmaybeusedfor changesindirection,BUTNOTBOTHonthesamelengthofpipe. • ManholeConnections:Propermanholeconnectionsareessentialtogoodsystemperformance.Thefollowing precautionsarerecommended: • Insurestable foundation and beddingfor the manholeand connectingpipe to prevent shiftingwhich could damagethe connection. • Useawater-stopgasketproducedfromelastomericmaterialwhichpreventsleakagewhileallowing • longitudinalpipemovement. • Useanon-shrinkingorexpansivetypegroutformakingconnectionsofpipeandwater-stoptomanhole • walls. • ColdWeatherInstallation:Extremelycoldtemperaturesresultinincreasesinpipestiffnessandtensilestrength anddecreasesinimpactstrength.Thedecreaseinimpactstrengthrequirescareinhandlingduringinstallation incoldtemperatures. • Risers:Sewerrisersorverticalstacksmayberequiredindeepsanitarysewerstominimizeexcavationforservices lines.Risersaregenerallypermittedwherethemainsewerlineisdeeperthan7feet. • Theverticalriserpipecreatesaloadscenarionotcommoninothersewerinstallations.Anysettlementof materialalongsidetheriser produces a“drag-down”loaddue tothefrictionalforcesatthepipe/soilinterface. Additionally,settlement ofthelateralfittingassemblyproducesasimilardrag-download.Theseloadsmustbe mitigatedortransferredharmlesslyoffthestacktopreventproblemssuchasover-insertion,fittingfracture, mainsewerlinedeflection/misalignment, etc. • Thefollowingpracticesareconsideredappropriateforallriserinstallations: • Transitionsfromhorizontaltoverticalshouldbesmoothandwellsupported.Thismaybeaccomplishedwith fittingcombinations,gradualbendsand/ortrenchgeometry. • Servicelateralsfromthemainsewershouldexitatananglenogreaterthan45degreesfromthehorizontal. Asinglelengthoflateralpipeshouldbeusedfortherisersectionwheneverpossible. • To minimizeoreliminatesettlementandtheresultingloading,compactioniscritical beneaththemainline sewerandlateralconnections. • SoilMigration:Whererunningorstandingwateroccursinthetrenchorsubstantialseasonalwatertablechanges areexpected,considerationmustbegiventopreventingsoilmigration.Migrationcouldcauselossofsoilsupport forinstalledpipe.Materialsusedforunderdrains,bedding,andhaunchingshouldbeofpropergradationand thicknesstopreventmigrationofmaterialfromfine-grainednativesoils. 18 UNI-BELLPVCPIPEASSOCIATIONWWW.UNI-BELL.ORG

  19. SEWERPIPE • CHECKLIST • Takeallprecautionsnecessarytoprotectworkersandmaterials. • Planaheadforfittings. • Usetrenchboxesorshoringinunstableconditions. • Donotdisturbinstalledpipewhenmovingtrenchboxesorshoringmaterials. • Properlyassemblepipejointsbyinsertingthespigotenduntiltheinsertionlineisevenwiththebell lip. • Insurewatertightsealsatmanholeconnections. • Keepthetrenchbottomasdryaspossible. • Fordetailedinstallationrecommendations,seeASTMD2321“StandardPracticeforUndergroundInstallation of ThermoplasticPipeforSewers andOtherGravity-FlowApplications.” • Consultthepipemanufacturerforspecificsregardinggasketsandlubricants. • Checkwiththeprojectengineerregardingspecifications and procedures. UNI-BELLLITERATURE RecommendedStandards UNI-B-6“RecommendedPracticeforLow-PressureAirTesting ofInstalledSewerPipe” Technical Reports UNI-TR-1“Deflection:ThePipe/SoilMechanism” UNI-TR-3 “MaintenanceofPVCSewer Pipe” UNI-TR-5“TheEffectsof UltravioletRadiationonPVC Pipe” UNI-PUB-06-21 19 INSTALLATIONGUIDEFORSOLID-WALLPVCSEWERPIPE

  20. UNI-BELLPVCPIPEASSOCIATION 201E.JohnCarpenterFreeway Suite750 Irving,TX75062 (972)243-3902 WWW.UNI-BELL.ORG

More Related