Low Level Commissioning 2005/2006 Collaboration Meeting, Baton Rouge Mark Krasberg April 12 th , 2006

Low Level Commissioning 2005/2006 Collaboration Meeting, Baton Rouge Mark Krasberg April 12 th , 2006. Commissioning a DOM at The Testing DAQ Level. Commissioning plan pretty much followed. Could not study string 29 during freeze-in

Mia_John
Télécharger la présentation

Low Level Commissioning 2005/2006 Collaboration Meeting, Baton Rouge Mark Krasberg April 12 th , 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Low Level Commissioning 2005/2006Collaboration Meeting,Baton RougeMark KrasbergApril 12th, 2006 Mark Krasberg U of Wisconsin

  2. Commissioning a DOMat The Testing DAQ Level Mark Krasberg U of Wisconsin

  3. Commissioning plan pretty much followed • Could not study string 29 during freeze-in • Ended up taking more data than original plan (not a bad thing) • Cold temperature problem meant that not all elements of the plan could be followed Mark Krasberg U of Wisconsin

  4. Problem Quads • Leaking Quads • 12/25 String 29 all quads • 01/04 String 39 none (quad 7 SJB problem) • 01/08 String 38 leak-checked late (oscillations) • 01/14 String 30 quads 4, 7 (quad 14 SJB prob) • 01/18 String 40 quads 13 and 14 • 01/22 String 50 leak-checked late (damaged) • 01/25 String 59 leak-checked late (swamped) • 01/29 String 49 quads 6, 9 and 10 • Anomolies • Any DOM which exhibited anomolous behavior was unplugged • Several wire pairs had high currents and their quads were unplugged and periodically tested • Communications Issues • Encountered a cold temperature (cold reboot) problem • Issue was a moving target as DOMs cooled and changed temperatures • Problem seems to be understood (final fix not applied at Pole yet) Mark Krasberg U of Wisconsin

  5. String 39 two-week freeze-in movie Mark Krasberg U of Wisconsin

  6. Triboluminescence • Had a longstanding plan on how to cope with the triboluminescence: (>40 kHz individual DOM rates!) • Use LC up.AND.down (“Triple Local Coincidence”) • Use Scaler Deadtime (reduces LC trigger rate) • The plan worked! • able to take over 1 terrabyte of data during season and hand-carry north Mark Krasberg U of Wisconsin

  7. Data-taking during Triboluminescence Approximate maximum trigger rate for normal TestDAQ data-taking frozen-in LC rate Mark Krasberg U of Wisconsin

  8. Surface DAQ Hardware • Jan 15: string 21 hub stopped working, probably overheated • Did not operate all hubs simultaneously after this event until the power distribution and cooling fan problems in the TCH were solved • Jan 30: string 59 DSB card didn’t work – was replaced • String 59 DOMHub suffers from domhub-app JVM crashes. This is the only hub which has had more than one JVM crash with TestDAQ. RealDAQ has had problems with other hubs. Mark Krasberg U of Wisconsin

  9. Cold Temperature Problems • DOMs found to have temperature-related problems (“cold reboot problem”) • Problems occur primarily at top of string (colder) • THIS MADE IT IMPOSSIBLE TO COMMISSION ANY DOMs at Pole • communications problems were a moving target • the list of DOMs which would not communicate properly would change daily, as the DOMs cooled down. • Particularly problemmatic temperature is ~-28C Mark Krasberg U of Wisconsin

  10. Study of cold reboot problem in ice • Used internal heating of mainboard to probe a temperature range (like in FATs) • String 29 “Farsta” • 57 reboots between -34.44 C and -27.25 C • 49 successful cold reboots • All reboots (8) failed between -31.25 C and -30.56 C • No successful reboots in this range • Just as during FAT testing, the problem is isolated to a specific, narrow temperature range Mark Krasberg U of Wisconsin

  11. Effect of cold temperature problems on Commissioning Mark Krasberg U of Wisconsin

  12. Able to deal with the expected unexpected problems fairly easily(part of the plan!) • When we hook up DOMs in a new environment we often encounter problems • Each DOMHub had a full TestDAQ development workspace (ie all the code needed for data-taking could be modified and recompiled at pole). • Patches could be emailed through Iridium satellite • Patches could then be installed, recompiled, and tested within minutes • Feedback could be given to the north almost instantaneously using Iridium satellite – we did not have to wait for TDRS satellite. If we had, then the resulting code iterations would have gone on for days! Mark Krasberg U of Wisconsin

  13. Communications now stable • TestDAQ softboot problem eliminated March 8. • DOM communications fix waiting to be deployed at pole • Data taking became stable with TestDAQ as of March 8th (600 DOMs at that time) except for occasional string59 domhub-app crashes. • DOMs can be commissioned since the communications problems have effectively been eliminated and data-taking is stable. • AMANDA mainboards have been included in the readout in almost all TestDAQ runs since February Mark Krasberg U of Wisconsin

  14. High Current DOMs • Six high current wire pairs identified at pole • Four of the high currents mysteriously went away (seemingly not related to temperature or freeze-in). One took weeks to go away! • Two remaining high current pairs permanently plugged in at station close • DOMs on both of these pairs have suffered problems in the months since they were plugged in • In the future, high current pairs should not be used in normal data-taking for as long as is feasible (one year?) Mark Krasberg U of Wisconsin

  15. High Current DOM Pairs • High current pairs which are still high current pairs • | 39-07 | Hippophilia | 8b56bf63b908 | UP5P0888 | 0 | 3 | • | 39-08 | Shamal | 7b492c28a830 | TP5P0527 | 0 | 3 | • | 40-51 | Juneberry | ce9692f580c9 | UP4P0086 | 6 | 1 | • | 40-52 | Alfa_Romeo_Spider | 0a9dc8de00c3 | TP5Y0171 | 6 | 1 | • High current pairs which are no longer high current pairs: • | 49-01 | Ceres | 754dad1d3800 | UP4Y0030 | 0 | 0 | • | 49-02 | Marzahn | 60cad4124a82 | TP5Y0161 | 0 | 0 | • | 50-37 | Volkswagen_Beetle | 93c6fcb0fe68 | UP5Y0216 | 4 | 2 | • | 50-38 | Warthog | a095b31f89cf | TP4P0315 | 4 | 2 | • | 40-57 | Tortellini | d54044599535 | UP4P0140 | 7 | 0 | • | 40-58 | Cannelloni | 3dac398e0d9d | TP4P0111 | 7 | 0 | • these DOMs drew an extremely large current initially, before problem went away... • | 30-45 | Capybara | 0d42d3e12c9f | UP4P0276 | 5 | 2 | • | 30-46 | Asparagus | 44c3682eb25c | TP4P0217 | 5 | 2 | • The pair with 50-58 “Universitet” had a marginally high current at pole but was not flagged as high current – it’s LC was determined to be broken as soon as it was turned on. Mark Krasberg U of Wisconsin

  16. Mark Krasberg U of Wisconsin

  17. 40-51 “Juneberry” & 40-52 “Alfa_Romeo_Spider” poor comms 50-58 “Universitet” bad LC 39-08 “Shamal” bad LC 59-59 “Cosmology” poor flash 29-18 “Yurei” PMT? 38-59 “Blackberry” no HV 49-17 “Biometeorology” bad flash 30-23 “Peugeot_505” no power 50-36 “Ocelot” no power 29-59 “Auroraphobia” & 29-60 “Nix” no power Mark Krasberg U of Wisconsin

  18. There are currently 16 strings (not 9)! hole: 21 29 30 38 39 40 49 50 59 strings: 1 1 2 1 2 2 2 3 2 total=16 we had 17 mini-strings in UW FAT #6! broken LC connection between two DOMs Problem DOMs a very short string! cannot be used for hard LC Mark Krasberg U of Wisconsin

  19. STF results for string 38, odd (U) DOMs Mark Krasberg U of Wisconsin

  20. 38-59 “Blackberry” failure Mark Krasberg U of Wisconsin

  21. 38-59 “Blackberry” failure zoom Mark Krasberg U of Wisconsin

  22. Freeze-In: 49-55 “Fusilli”DOM was still in water on Mar 22 Mark Krasberg U of Wisconsin

  23. String 49 – drill stopped for ~one hour at ~2300 meters Mark Krasberg U of Wisconsin

  24. Summary of Commissioned DOMs • To date: the 300 DOMs for which STF ran successfully at Pole can be regarded as commissioned (low level) • when 49-55 “Fusilli” freezes-in STF will be run again, as per initial plan (don’t expect any problems) • Current Status: 600 out of 604 communicating on March 20 • DOMs with serious problems • Three communicating DOMs not useful for hard LC data-taking (this affects 4th DOM) • 2 DOMs (40-51 “Juneberry” and 40-52 “Alfa_Romeo_Spider”) are high current, poorly communicating, have recently degraded and should be unplugged for special testing • DOMs with less serious problems • 2 DOMs (49-17 “Biometeorology” and 59-59 “Cosmology”) have flash problems • 29-18 “Yurei” suffered a 40% gain shift in March • 21-30 “Phenol” has sustained high dark rate problem, operating at lower gain • 21-13 “Wickueler” does not like to be turned off (discovered during this season) • Additional LC problem between 59-51 and 59-52 (broken connection during refreeze) Mark Krasberg U of Wisconsin

  25. Mark Krasberg U of Wisconsin

  26. 49-55 “Fusilli” Mark Krasberg U of Wisconsin

  27. Mark Krasberg U of Wisconsin

  28. Mark Krasberg U of Wisconsin