Provident Adora De Goa | flat for sale in Dabolim

Adora De Goa is situated on a hilltop in Dabolim, South Goa. The intelligent location of the project promises the delight of a perfect view of the sea from every 2 BHK flat in Dabolim. Besides the beautiful view, the location of the project proves to be ideal because of its excellent connectivity and strong vicinity. For more visit @ https://www.providenthousing.com/adoradegoa/

Télécharger la présentation

Provident Adora De Goa | flat for sale in Dabolim

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. May 2021 September 2021

  2. Tower 18 18B 18C 18D 18A TOWER STATUS MILESTONES ACHIEVED • Tower 18 A Kitchen dado completed. UPVC Door window installation work in progress. OHT work completed Tower 18B UPVC Door Window Installation WIP. Lobby flooring WIP. OHT work completed. Tower 18C UPVC Door Window Installation WIP. Tower 18D Gypsum, Flooring and dado WIP. Tower 18E Terrace slab completed Tower 18F Terrace Slab WIP. Tower 18G 1st slab completed. • 18F 4th Slab completed. • • 18E 18F 18G UPCOMING MILESTONES • • 18F Completion Terrace Slab. 18G Completion of 2nd Slab. 18C Completion of Flooring & Windows. • • • • Actual site photograph • • PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  3. Tower 17 17BC4 17CC2 17AC2 TOWER STATUS MILESTONES ACHIEVED • • Tower 17AC2 Terrace, Balcony Railing & Kitchen Platform WIP. Tower 17BC4 Terrace, Balcony Railing WIP. Tower 17CC2 Terrace, Balcony Railing WIP. T17 – A, B, C – Terrace slab completed. • • UPCOMING MILESTONES Actual site photograph • T17 – A, B, C – Completion of Flooring & windows. PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  4. Tower 16AC5 TOWER STATUS MILESTONES ACHIEVED • • Terrace slab completed. Terrace Slab completed. UPCOMING MILESTONES • Completion of Flooring & windows. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  5. Tower 15AC5 TOWER STATUS MILESTONES ACHIEVED • • Above terrace works are in progress. Gypsum work completed. Terrace Slab Completed. • UPCOMING MILESTONES • Completion of Flooring & windows. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  6. Tower 14AC5 TOWER STATUS MILESTONES ACHIEVED • • Above terrace works are in progress. Gypsum works completed. Terrace Slab completed. • UPCOMING MILESTONES • Completion of Flooring & Windows. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  7. Tower 13AC5 TOWER STATUS MILESTONES ACHIEVED • • Above terrace works are in progress. Flooring WIP. Gypsum WIP. Terrace Slab Completed. • • UPCOMING MILESTONES • Completion of Flooring & Windows. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  8. Tower 12 12BC3 12AC6 TOWER STATUS MILESTONES ACHIEVED • • Tower 12AC6 Gypsum & Flooring WIP Tower 12BC3 Vitrified flooring works are in progress. T12-A & B Terrace slab completed. • UPCOMING MILESTONES • T12-A & B completion of Flooring & Windows. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  9. Tower 11AC6 TOWER STATUS MILESTONES ACHIEVED • • Above terrace works are in progress. Flooring & Gypsum works in progress. Terrace slab completed. • UPCOMING MILESTONES • Completion of Flooring & Windows. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  10. Tower 10 10BC6 10CC3 10AC4 TOWER STATUS MILESTONES ACHIEVED • • Tower 10AC4 Above terrace work in progress, Windows fixing in progress. Flooring completed. Tower 10BC6 Above terrace works in progress, Flooring completed. Tower 10CC3 Above Terrace works in progress. Gypsum completed. T10 A,B,C – Terrace slab completed. • UPCOMING MILESTONES Actual site photograph • • T10 – A & B completion of Flooring & Windows PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  11. Tower 9 TOWER STATUS MILESTONES ACHIEVED • • Tower 9AC6 Plinth Beam work in progress. Yet to achieve. UPCOMING MILESTONES • Tower 9AC6 completion of plinth. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  12. Tower 8 TOWER STATUS MILESTONES ACHIEVED • • Tower 8BC5 Footing completed. Walls up to Plinth WIP. Yet to achieve. UPCOMING MILESTONES • Tower 8BC5 completion of Plinth. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  13. Tower 7 7DC3 7BC6 TOWER STATUS MILESTONES ACHIEVED • • Tower 7DC3 Walls up to 1st Slab WIP. Tower 7BC6 Footing work in progress. T7D plinth completed. • UPCOMING MILESTONES • Tower 7BC3 completion of Plinth. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  14. Tower 6 6BC4 6CC5 6AC4 TOWER STATUS MILESTONES ACHIEVED • • • Tower 6AC4 1st Slab work in progress. Tower 6BC4 1st slab completed. Tower 6CC5 Walls up-to 1st slab completed. Tower 6DC6 5th Slab WIP. Tower 6EC3 Terrace slab completed. 6EC3 Terrace Slab completed. 6DC6 4th Slab completed. • • 6DC6 6EC3 UPCOMING MILESTONES • • • 6DC6 completion of Terrace Slab. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  15. Tower 5 5BC5 5AC5 TOWER STATUS MILESTONES ACHIEVED • • Tower 5AC5 1st Slab work in progress. Tower 5BC5 1st Slab completed. Tower 5CC5 1st Slab completed. Tower 5DC3 Terrace OHT Works in progress. T5D Terrace Slab Completed. • • 5CC5 5DC3 UPCOMING MILESTONES • • T5C -completion of 2nd slab. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  16. Tower 4 4BC4 4CC6 4AC4 TOWER STATUS MILESTONES ACHIEVED • • Tower 4AC4 5th slab work in progress. Tower 4BC4 1st Slab Completed. Tower 4CC6 Walls up to stilt WIP. Tower 4A 4th Slab completed. • • UPCOMING MILESTONES Actual site photograph • Tower 4A completion of Terrace Slab. PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  17. Tower 3 3B 3C 3A TOWER STATUS MILESTONES ACHIEVED • • Tower 3A Terrace Slab completed. Tower 3B OHT Works in progress. T-3A & B Terrace slab completed. • UPCOMING MILESTONES Actual site photograph • T-3C completion of 2nd slab. PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  18. Tower 2 2B 2A TOWER STATUS MILESTONES ACHIEVED • • Tower-2A 2nd Slab pour 1 completed Pour2 work in progress. Tower-2B terrace slab completed. UPCOMING MILESTONES • Tower-2A completion of 2nd Slab. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  19. Tower 1 1B 1A TOWER STATUS MILESTONES ACHIEVED • • Tower 1A Excavation completed. Tower 1B Foundation works are in progress. Yet to achieve. • UPCOMING MILESTONES • Completion of Tower 1B Plinth. Actual site photograph PROGRESS TIMELINE August 21 September 21 Construction Updates

  20. Other activities TOWER STATUS • STP-1 STP walls in progress. • UG Sump Raft work in progress. • Entrance Portal Block work in progress. • Compound wall Block work in progress. • Blu Area Excavation work in progress. • MUC STP & UG Raft reinforcement work in progress. • STP-2 Excavation completed. • Road Excavation work in progress. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  21. Site Office : Provident Adora de Goa Sy.No.198, Zuari Nagar, VidhyanagarColony, Chicalim, Goa – 403726. Regional Office : Provident Housing Limited No.8, UlsoorRoad, Bengaluru- 560 042 Tel: 080-44555544 Email : crm@providenthousing.com(Subject line – Project name/ unit number) Call Us : +91 - 80-67724001 / 1 860 208 0000 Web : www.providenthousing.com RERA Registration Number : RERA No.: PRGO02190645 (ROW 5 & 6) RERA Nos.: PRGO02180009 (Row 10,11 & 12), PRGO07180544 (Row 13) PRGO07180560 (Row 14), PRGO07180561 (Row 15)