Mechanical, Electrical, and Plumbing Introduction Lee Harrelson, PE, LEED ® AP Principal, TM/R Engineering

Mechanical, Electrical, and Plumbing Introduction Lee Harrelson, PE, LEED ® AP Principal, TM/R Engineering. Agenda. Building Systems Planning Room Sizes and Area %’s Mechanical Systems Equipment Identification and Application Considerations Outside Air Electrical Systems

Sharon_Dale
Télécharger la présentation

Mechanical, Electrical, and Plumbing Introduction Lee Harrelson, PE, LEED ® AP Principal, TM/R Engineering

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mechanical, Electrical, and Plumbing IntroductionLee Harrelson, PE, LEED® APPrincipal, TM/R Engineering

  2. Agenda • Building Systems Planning • Room Sizes and Area %’s • Mechanical Systems • Equipment Identification and Application Considerations • Outside Air • Electrical Systems • Equipment Identification and Application Considerations • Energy Code Considerations • Plumbing Systems • Equipment Identification and Application Considerations

  3. Building Planning • Q: How much space for MEP systems? • A: Who knows? It depends on many factors: However, this website is a great starting point. http://www.repwars.com/PSP/mechroom.html

  4. Mechanical Systems • Packaged Rooftop AHUs • Application Considerations • Exhaust fans more than 10 feet away from OA intake • Roof slopes coordinated with equipment • Clearance on one side of unit equal to unit width http://www.trane.com

  5. Mechanical Systems • Modular Indoor AHUs • Application Considerations • Clearance on one side of unit equal to unit width • Space for duct connections (large turning radius) http://www.trane.com

  6. Mechanical Systems • Fan Coil Unit • Application Considerations • Cannot place systems furniture partitions in front of unit • Minimal air-throw, cannot serve large space • Can be concealed in a perimeter millwork “bench” http://www.trane.com

  7. Mechanical Systems • Air-Cooled Chiller • Application Considerations • Located Outdoors • Very Noisy • No harmful plume http://www.trane.com

  8. Mechanical Systems • Water-Cooled Chiller • Application Considerations • Located Indoors, but extremely noisy • Needs 5 feet clearance on 3 sides and entire length of unit on end • Must be connected to a Cooling Tower (outside) http://www.trane.com

  9. Mechanical Systems • Open Cooling Tower • Application Considerations • Located outdoors, noise and vibration • Emits a saturated air plume which can cause damage to nearby buildings • Screening must have high free area http://www.baltimoreaircoil.com

  10. Mechanical Systems • Outside Air Requirements • Fresh Air is brought into the building to dilute the contaminants in the space. • Offices – 7 people/1000 ft2 and 20 CFM/person • Auditoriums – 150 people/1000 ft2 and 15 CFM/person • Classrooms – 50 people/1000 ft2 and 15 CFM/person • Libraries – 20 people/1000 ft2 and 15 CFM/person • Corridors and Storage – 0.10 CFM/ft • Why does this matter? • Large duct sizes, excessive loads that strain existing infrastructure requiring more mechanical space.

  11. Mechanical Systems • Duct Shaft Sizing • How much space required for mechanical duct chases? • Rule of Thumb – Assume 1 CFM per square foot and assume 1000 feet per minute duct velocity • Example: Suppose an AHU serves a 20,000 ft2 floorplate. The AHU is located in the basement and serves the 2nd floor. • 20,000 ft2 needs roughly 20,000 CFM or 20,000 ft3/minute • Divide 20,000 ft3/minute by 1000 feet/minute to get duct cross sectional area. • 20,000/1000 = 20 ft2 required duct area • Remember…that’s just for the supply duct! We also have a return duct, outside air duct, exhaust ducts and we need space for piping.

  12. Electrical Systems • Transformers • Application Considerations • Near electrical service entrance, inside or outside • Generate lots of heat • Service clearance depending on voltage, 3 to 5 feet typically

  13. Electrical Systems • Switchgear • Application Considerations • Service clearance depending on voltage, typically 3 to 5 feet

  14. Electrical Systems • Distribution Panel boards • Application Considerations • Service clearance depending on voltage, typically 3 feet

  15. Electrical Systems • Bus duct Risers • Application Considerations • Should not offset. Bends are large, expensive, and very difficult to install • Space is required around the bus duct to install the disconnect switches

  16. Electrical Systems • Electrical Room Stacking • Application Considerations • Prevents offsetting of vertical power distribution such as bus ducts or cable in conduit • Increases system efficiency by reducing cabling run distances

  17. Electrical Systems • Energy Code and Lighting Power Allowances • Application Considerations • Most code reviewers are enforcing the International Energy Efficiency Code – 2003. • 1.1 watts/ft2 for offices • 1.4 watts/ft2 for classrooms and lecture halls • 1.9 watts/ft2 for workshops areas • 0.9 watts/ft2 for corridors • This often precludes reuse of existing inefficient lighting in renovation projects. T-5 fixtures are preferred.

  18. Plumbing Systems • Plumbing Piping Note: Drains sloped at 1/4” to 1/8” per foot of run depending on size Hubless Sanitary Vent Piping Hubless Sanitary Drain Piping Storm Drain Piping Insulated Domestic Cold Water Piping

  19. Plumbing Systems • Double Check Backflow Preventers • Application Considerations • Used to prevent contamination of city water supply • Installed at water service entrance to building • Typically require a floor drain • Must be accessible for inspection and repair

  20. Plumbing Systems • Roof Drains • Application Considerations • If parapet wall is installed, a secondary drain path must be provided to discharge above grade. Use scuppers or internal secondary system which is very costly. • Must drain by gravity

  21. Plumbing Systems • Toilet Room Stacking • Should stack to minimize drainage stack offsets. • Drainage stack offsets (a bend greater than 45o) must be separately vented, increasing cost and required space • Venting is required to prevent backpressure in the piping, which will prevent proper draining

  22. Plumbing Systems • Toilet Room Stacking • Venting an offset

  23. Plumbing Systems • Stormwater Harvesting http://www.constructionresources.com/images/products/services/rainwater_system.jpg

  24. MEP Introduction • Questions?